United States v. Spearin

248 U.S. 132, 39 S. Ct. 59, 63 L. Ed. 166, 1918 U.S. LEXIS 1700, 54 Ct. Cl. 187
Supreme Court of the United States·Decided December 9, 1918·No. 44, 45·Published·Cited by 547 cases

Opinion

Mr. Justice Brandéis

delivered the opinion of the court,

Spearin brought this suit in the Court of Claims, demanding a balance alleged to be due for work done under a contract to construct a dry-doek and also damages for its annulment. Judgment was entered for him in the sum of $141,180.86;' (51 Ct. Clms. ,155) and both parties appealed to this court. The Government contends that Spearin is entitled to recover only $7,907.98. Spearin claims the additional sum of $63,658.70.

First. The decision to be made on the Government’s appeal depends upon whether or not it was entitled to annul the contract. The facts essential to a determination- of the-question are these:

■ Spearin contracted to build for $757,800 a dry-dock at the Brooklyn Navy Yard in accordance with plans and specifications which had been prepared by the. Government. The site selected by it was intersected by a 6-foot brick sewer; and it was necessary to divert and relocate a section thereof before the work of constructings the dry-dock could begin. The plans and specifications provided that the contractor should do the work and prescribed the dimensions, material, and location óf the section to be *134 substituted. All the prescribed requirements were fully complied with by Spearin; and the substituted section was accepted by the Government as satisfactory. It was located about 37 to 50 feet from the proposed excavation for the dry-dock; but a large part of the new section was within the area set aside as space within which the contractor's - operations were to ber carried on. Both before and after the diversion of the 6-foot sewer, it connected, within the Navy Yard but outside the space reserved for work on the dry-dock, with a 7-foot sewer which emptied into Wallabout Basin.

About a year after this relocation of the 6-foot sewer there occurred' a sudden and heavy downpour of rain coincident with a high tide. This forced the water up the sewer, for a considerable distance to a depth of 2 feet or more. Internal pressure broke the 6-foot sewer as so relocated, at several places; and the excavation of the dry-dock was flooded. Upon investigation, it was discovered that there was a dam from 5 to 53^ feet high in the 7-foot sewer;- and that dam, by diverting to the 6-foot sewer the greater part of the water, had caused the internal pressure which broke it. Both sewers were a part of the city sewerage system; but the dam was not shown either on the city’s plan, nor on the Government’s plans and blue-prints, which were submitted to Spearin. On them the 7-foot sewer appeared as unobstructed. The Government officials concerned with the letting of the contract and construction of the dry-dock did not know of the existence of the dam.' The site selected for the dry-dock was low ground; and during some years prior to making the contract sued on, the sewers had, from time to time, overflowed to the knowledge of these Government officials and others. But the fact had not been communicated to Spearin by anyone. He had, before entering into the contract, made a superficial examination of the premises and sought from the civil engineer’s office at the Navy *135 Yard information concerning the conditions and probable cost of the work; but he had made no special examination of„the sewers nor special enquiry into the possibility of the work being flooded thereby; and had no information on the subject.

Promptly after the breaking of the sewer Spearin notified the Government that he- considered the sewers under existing plans a menace to the work and that he would not resume operations unless, the Government either made good or assumed responsibility for the-damage that had already occurred and either made such changes in the sewer system as would remove the danger or assumed responsibility for the damage which might thereafter be occasioned by the insufficient capacity and the location and design of the existing sewers. The-estimated cost of restoring the sewer was $3,875. But it was unsafe to both Spearin and the Government’s property to proceed with the work with the 6-foot sewer in its then condition. The Government insisted that the responsibility for remedying existing conditions rested with the contractor. After fifteen months spent in- investigation and fruitless correspondence, the Secretary of the Navy annulled the contract and took possession of the plant and materials on the site. Later the dry-dock, under radically changed and enlarged plans, was completed by other contractors, the Government having first discontinued the use of the 6-fo'ot intersecting sewer and then reconstructed it by modifying size, shape and material so as to remove all danger of its breaking from internal pressure. Up to that time $210,939.18 had been expended by Spearin on the work; and he had-received from the Government on account thereof $129,75^.32. The court found that if he had been allowed to complete the contract he would have earned a profit of $60,000, and its judgment included that sum.

The general rules of law applicable to these facts are well *136 settled. Where one agrees to do, for a fixed sum, a thing possible to be performed, he will not be excused or become entitled to additional compensation, because unforeseen .difficulties are encountered. Day v. United States, 245 U. S. 159; Phœnix Bridge Co. v. United States, 211 U. S. 188. Thus one who undertakes to erect a structure upon a particular site, assumes ordinarily the risk of subsidence of the .soil. .Simpson v.' United States, 172 U. S. 372; Dermott v. Jones, 2 Wall. 1. But if the contractor is bound to build according to plans and specifications prepared by the owner, the contractor will not be responsible for the consequences of defects in the plans and specifications. MacKnight Flintic Stone Co. v. The Mayor, 160 N. Y. 72; Filbert v, Philadelphia, 181 Pa. St. 530; Bentley v. State, 73 Wisconsin, 416. See Sundstrom v. New York, 213 N. Y. 68. This responsibility of the owner is not overcome by the usual clauses requiring builders to visit the site, to check the plans, and'to inform them-selves of the requirements of the work, as is shown by Christie v. United States, 237 U. S. 234; Hollerbach v. United States, 233 U. S. 165, and United States v. Utah &c. Stage Co., 199 U. S. 414, 424, where it was held that the contractor should be relieved, if he was misled by erroneous statements in the specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

United States v. Spearin, 248 U.S. 132, 39 S. Ct. 59, 63 L. Ed. 166, 1918 U.S. LEXIS 1700, 54 Ct. Cl. 187 (1918).

248 U.S. 132 (United States v. Spearin) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

UNIT Company
Armed Services Board of Contract Appeals, 2018
Rainbow Construction Inc v. Township of Howell
Michigan Court of Appeals, 2017
Pyrotechnic Specialties, Inc.
Armed Services Board of Contract Appeals, 2017
Lakeshore Engineering Services, Inc. v. United States
748 F.3d 1341 (Federal Circuit, 2014)
Spodek v. United States Postal Service
551 F. App'x 781 (Fifth Circuit, 2014)
Los Angeles Unified School District v. Great American Insurance
234 P.3d 490 (California Supreme Court, 2010)
Eastern Electric Corp. v. Shoemaker Construction Co.
657 F. Supp. 2d 545 (E.D. Pennsylvania, 2009)
Southern Electric Corp. v. Utilities Board of Foley
643 F. Supp. 2d 1302 (S.D. Alabama, 2009)
The Blakley Corp. v. EFCO Corp.
853 N.E.2d 998 (Indiana Court of Appeals, 2006)