BAE Systems Ordnance Systems, Inc. v. Fluor Federal Solutions, LLC

CourtDistrict Court, W.D. Virginia
DecidedMarch 30, 2022
Docket7:20-cv-00587
StatusUnknown

This text of BAE Systems Ordnance Systems, Inc. v. Fluor Federal Solutions, LLC (BAE Systems Ordnance Systems, Inc. v. Fluor Federal Solutions, LLC) is published on Counsel Stack Legal Research, covering District Court, W.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BAE Systems Ordnance Systems, Inc. v. Fluor Federal Solutions, LLC, (W.D. Va. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF VIRGINIA ROANOKE DIVISION

BAE SYSTEMS ORDNANCE ) SYSTEMS, INC. ) ) Plaintiff, ) ) Case No. 7:20-cv-587 v. ) ) FLUOR FEDERAL SOLUTIONS, ) LLC, ) ) By: Michael F. Urbanski Defendant. ) Chief United States District Judge

MEMORANDUM OPINION This matter is before the court on defendant Fluor Federal Solutions LLC’s (“Fluor”) motion to dismiss plaintiff BAE Systems Ordnance Systems Inc.’s (“BAE”) complaint, ECF No. 30, BAE’s motion to strike defendant Fluor’s answer to the complaint and counterclaim, ECF No. 36, and BAE’s motion to dismiss Fluor’s counterclaim, ECF No. 38. The issues have been fully briefed, and the court heard arguments on January 14, 2022. For the reasons stated below, the court (1) DENIES Fluor’s motion to dismiss, ECF No. 30, (2) GRANTS BAE’s motion to strike, ECF No. 36, and (3) GRANTS in PART and DENIES in PART BAE’s motion to dismiss, ECF No. 38. I. Background Facts1 The following facts are taken from BAE’s complaint, ECF No. 1, Fluor’s counterclaim, ECF No. 29, and the contract documents referenced therein. This case concerns a subcontract (“Subcontract”) entered into by BAE and Fluor on

December 17, 2015, for the construction of a nitrocellulose (“NC”) facility at the Radford Army Ammunition Plant (“RFAAP”) in Radford, Virginia. BAE Compl., ECF No. 1, at 1. The US Army Joint Munitions Command contracted with BAE to operate and maintain the RFAAP under a basic ordering agreement (“BOA”) dated May 17, 2011. Pursuant to the BOA, the Army issued orders relating to the RFAAP called Task Orders. Under BOA Task Order 002 issued by the Army on January 23, 2012, BAE contracted to replace the legacy NC facility

at the RFAAP with a newer one. This project, referenced herein as the “NC Project,” required construction of four buildings, an acid tank farm, and a cutter warehouse. Id. at 12. BAE initially subcontracted the design of the NC Project to Lauren Engineers & Constructors (“Lauren”) in 2012 but terminated the subcontract in 2015 because BAE found Lauren incapable of completing the work in a timely manner. Id. Despite terminating Lauren, BAE’s

contractually agreed upon timeline to construct the new NC facility remained unchanged and use of the Lauren design was required for the NC Project because the Army had already paid BAE for it. Fluor Countercl., ECF No. 29, at 29, 33. After terminating Lauren, BAE sought another subcontractor for the NC Project. BAE Compl., ECF No. 1, at 13. During the solicitation process, BAE gave interested bidders access

1 Facts taken from BAE’s complaint and Fluor’s counterclaim are presumed to be true for the purpose of this motion. Republican Party of North Carolina v. Martin, 980 F.2d 943, 952 (4th Cir. 1992); Walker Process Equip., Inc. v. Food Mach. & Chem. Corp., 382 U.S. 172, 175, (1965) (Allegations of counterclaim are taken as true on motion to dismiss). to the Lauren design and other documents to expedite the procurement process. Fluor Countercl., ECF No. 29, at 31. These documents included Lauren’s native design files, drawings, and product specifications. BAE Compl., ECF No. 1, at 14. Fluor alleges that BAE

required the Subcontract to be performed in accordance with the Lauren design, that the Lauren design could be relied on for accuracy, and the selected subcontractor only had to complete the unfinished parts. Fluor Countercl., ECF No. 29, at 30. Additionally, BAE allegedly represented that the Lauren design was 85% complete. Id. at 30. BAE solicited bids using a Request for Proposal (“RFP”) which included a Statement of Work (“SOW”) describing the requirements for the NC Project’s design and construction.

BAE Compl., ECF No. 1, at 14. Fluor submitted a request for information (“RFI”) asking BAE about the standards referenced in the SOW. Fluor Countercl., ECF No. 29, at 30. Fluor alleges that BAE responded by emphasizing the importance of compliance with the Lauren design. Id. During the bid and review process, Fluor was unable to determine the completeness of the Lauren design but relied on BAE’s assertions that the design was 85% complete. Id. at 37. Fluor alleges that BAE responded that Fluor’s initial bid was too high given what BAE

had already paid Lauren for its design and that Fluor’s price should be lower because the Lauren design was close to complete. Id. at 33. Fluor lowered its price and submitted a revised bid proposal on November 16, 2015. BAE Compl., ECF No. 1, at 15. Fluor’s bid outlined a firm-fixed price design/build. Fluor said it had the experience and resources to timely complete the NC Project and “Fluor [was] committed to delivering projects safely, on schedule, within budget, and with the quality expected from our Customers.” Id. at 16. Fluor initially forecast thirty-two months to complete the NC Project and listed June 14, 2018, as the completion date. Id. at 16. To allow Fluor to immediately commence work, BAE awarded Fluor an Undefinitized Contract Action (“UCA”) in an amount approximating

$9 million dollars. BAE selected the proprietary equipment systems to manage and control the NC facility. Fluor Countercl., ECF No. 29, at 28. BAE also allegedly retained responsibility for the process design, while Fluor had responsibility for the design and construction of systems to support BAE’s plans. Id. Under the UCA, Fluor began procuring materials and physical construction work before the formal Subcontract was agreed upon. The UCA signified the parties’ intention to enter into a formal agreement as soon as possible. BAE

Compl., ECF No. 1 at 18. The value of the UCA was later increased to approximately $32 million dollars. Id. at 18. On December 17, 2015, BAE and Fluor agreed to a firm fixed price design and build Subcontract. Id. Section 2.13 of the Subcontract provides as follows: “This is a Fixed Price Subcontract. The Buyer shall pay the Subcontractor for the supplies, services and/or data delivered and accepted hereunder the firm fixed price stated in, Exhibit I. The price is not

subject to any adjustment on the basis of the Subcontractor’s cost experience in performing the Statement of Work.” Subcontract, ECF No. 1-2, at 10 (emphasis in original). Fluor agreed to design, construct, and partially commission the Project for $245,690,422, which included the money spent already in the UCA. BAE Compl., ECF No. 1, at 19. The contract contained an unforeseen contingency provision which set aside an additional $14 million, “other than changes to the contract compensable under the Changes clause.” Id. at 12. Section 2.12 of the Subcontract provides as follows: “Subcontractor, as an independent company and not as an agent of BAE Systems, shall provide the necessary facilities, personnel, equipment and materials to accomplish the assigned tasks within the parameters of this

Subcontract Agreement and in accordance with the Statement of Work (SOW). Exhibit E.” Subcontract, ECF No. 1-2, at 10. Section 1.0 of the SOW, headed PROJECT, contains the following description: The objective of this Statement of Work (SOW) is to design, procure, and construct (including construction checkout, and water runs) the new NC Area Acid Tank Farm, a Nitration area, Stabilization area, Dewater/Packout area, Administration building and the supporting areas/processes required to support the new Nitrocellulose Facility at the RFAAP. The Cutter/Warehouse is being built under a separate contract, but this SOW requires installation of process equipment and related mechanical, piping and E&I systems in this building.

Subcontract, ECF No. 1-2, at 75 (emphasis in original).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mutual Life Insurnace v. Hill
193 U.S. 551 (Supreme Court, 1904)
United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Wag More Dogs, Ltd. Liability Corp. v. Cozart
680 F.3d 359 (Fourth Circuit, 2012)
Elayne Wolf v. Federal National Mortgage
512 F. App'x 336 (Fourth Circuit, 2013)
Collelo v. Geographic Services, Inc.
727 S.E.2d 55 (Supreme Court of Virginia, 2012)
Condominium Services, Inc. v. FOA
709 S.E.2d 163 (Supreme Court of Virginia, 2011)
Mongold v. Woods
677 S.E.2d 288 (Supreme Court of Virginia, 2009)
Sunrise Continuing Care, LLC v. Wright
671 S.E.2d 132 (Supreme Court of Virginia, 2009)
City of Chesapeake v. STATES SELF-INSURERS
628 S.E.2d 539 (Supreme Court of Virginia, 2006)
Plunkett v. Plunkett
624 S.E.2d 39 (Supreme Court of Virginia, 2006)
Shepherd v. Davis
574 S.E.2d 514 (Supreme Court of Virginia, 2003)
Asphalt Roads & Materials Co. v. Commonwealth
512 S.E.2d 804 (Supreme Court of Virginia, 1999)
Ward's Equipment, Inc. v. New Holland North America, Inc.
493 S.E.2d 516 (Supreme Court of Virginia, 1997)
R.K. Chevrolet, Inc. v. Hayden
480 S.E.2d 477 (Supreme Court of Virginia, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
BAE Systems Ordnance Systems, Inc. v. Fluor Federal Solutions, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bae-systems-ordnance-systems-inc-v-fluor-federal-solutions-llc-vawd-2022.