BAE Systems Ordnance Systems, Inc. v. Fluor Federal Solutions, LLC

CourtDistrict Court, W.D. Virginia
DecidedJanuary 31, 2024
Docket7:20-cv-00587
StatusUnknown

This text of BAE Systems Ordnance Systems, Inc. v. Fluor Federal Solutions, LLC (BAE Systems Ordnance Systems, Inc. v. Fluor Federal Solutions, LLC) is published on Counsel Stack Legal Research, covering District Court, W.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BAE Systems Ordnance Systems, Inc. v. Fluor Federal Solutions, LLC, (W.D. Va. 2024).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF VIRGINIA ROANOKE DIVISION

BAE SYSTEMS ORDNANCE ) SYSTEMS, INC., ) ) Plaintiff, ) Civil Action No.: 7:20-cv-587 ) v. ) ) FLUOR FEDERAL SOLUTIONS, LLC, ) By: Hon. Robert S. Ballou ) United States District Judge Defendant. ) )

MEMORANDUM OPINION BAE Systems Ordnance Systems, Inc. (“BAE”) initiated this suit against Fluor Federal Solutions, LLC (“Fluor”) alleging breach of contract relating to the design and construction of a nitrocellulose production facility for the United States Army. Fluor counterclaimed for breach of contract or, in the alternative, quantum meruit or unjust enrichment. The contract for the design and construction of the facility (the “Subcontract”) contained three limitation of damages clauses which purport to limit the recovery of damages to $30 million. BAE moves the Court to hold that the limitation on damages clause in the contract limits Fluor’s claims for all Proposed Change Notices (“PCNs”) and other alleged damages to $30 million. Fluor seeks a ruling granting summary judgment that (1) the Subcontract’s limitation on damages provisions in the contract do not limit Fluor’s recovery for costs incurred performing BAE-caused changes on the project, and (2) the Subcontract’s limitation on damages provisions are unenforceable to limit recovery through the Contract Direction/Changes clause (“Changes Clause”) of the Subcontract as a matter of law under Virginia Code § 11-4.1:1. I find that these clauses exclude from their scope any claim which may arise under the changes clause of the Subcontract, and also that § 11-4.1:1 of the Virginia Code renders the limitation of damages clause null and void to the extent that it limits Fluor’s ability to recover for costs arising under the Changes Clause of the Subcontract. Accordingly, I DENY BAE’s Motion for Partial Summary Judgment and GRANT Fluor’s Motions for Partial Summary Judgment. I. Factual Background1

BAE manages an ammunition plant for the United States Army in Radford, Virginia commonly known as the Radford Arsenal. In January 2012, the Army awarded BAE a contract to design and build a new nitrocellulose production facility (“NC Facility”) at the Radford Arsenal which includes (1) a cutter warehouse; (2) an acid tank farm; (3) a nitration building; (4) a stabilization building; (5) a dewater and packout building; and (6) an administrative and laboratory building. On February 8, 2012, BAE entered into two subcontracts with Lauren Engineers and Constructor’s, Inc. (“Lauren”) for the design and construction of the NC Facility. That relationship, however, soured in the following years because of delays and cost overruns causing

BAE to terminate both Lauren subcontracts for convenience on January 28, 2015. BAE and Lauren ultimately resolved their differences in an arbitration proceeding in which Lauren sought payment for work performed. BAE brought a counterclaim against Lauren contending that the design work was “wholly without value” and so defective that it amounted to fraud. The arbitration resolved by settlement. BAE immediately began the process of replacing Lauren as a design/builder for the new NC Facility, and on April 16, 2015, hosted an Industry Day for potential bidders. The BAE

1 The parties sharply dispute many of the facts central to the formation, interpretation, and performance of the contract between BAE and Flour at issue in this case. Both sides have submitted exhaustive statements of facts which each contends are undisputed. Yet, each side has filed detailed counterstatements disputing at length the other’s claimed undisputed facts. presentation at Industry Day provided attendees information about the project and the bidding process to allow them to analyze and assess the scope and nature of the project in advance of submitting proposals. Relevant to this case, BAE toldthose present that it had “obtained native design format design files from [Lauren] that provide an estimated 85% design solution with some areas requiring additional engineering. . .” and listing those areas requiring additional

engineering. BAE also advised potential bidders that the required design work for the project included “[v]alidation of the existing design (estimated at 85%)” and “[c]ompletion of design and validation of mechanical performance.” BAE provided Fluor the Lauren Design documents to use in development of its bid. During the ensuing six months, from June 2015–December 2015, as Fluor put together its bid proposal, BAE regularly updated the Lauren documents with redlines and corrections. In July 2015, Fluor entered into a Teaming Agreement with Burns & McDonnell for design, engineering support, and construction administration services in support of a potential subcontract between BAE and Fluor. Burns & McDonnell agreed to become the Designer of

Record for the project and assume design responsibility under the prospective subcontract between BAE and Fluor. Burns & McDonnell reviewed the Lauren Design and SmartPlant 3D model for approximately four weeks and submitted a proposal to Fluor to validate and complete the Lauren Design for $31.3 million. That same day, Fluor submitted its first proposal to BAE for $306.5 million (inclusive of the Burns & McDonnell proposal) to validate and complete the Lauren Design and to construct the NC Facility. BAE rejected Fluor’s proposal stating, in part, that the Burns & McDonnell design price, was too high. On August 31, 2015, Kelly Bate, BAE’s subcontracts manager emailed Fluor, “I’m concerned that the design portion of your proposal is really far out of whack with our expectations. As a reference point, the entire original design was around $15M, and that should be about 80-90% complete . . . can we chat tomorrow about your approach to that portion of the proposal?” Burns & McDonnell submitted a second proposal for design of the project on September 2, 2015, lowering its costs to $29.5 million. Two days later, Fluor submitted to BAE a revised

price proposal for the whole project of $276.9 million, incorporating the reduced Burns & McDonnell design price and other cost reduction adjustments. Again, BAE rejected this proposal because of cost. On September 24, 2015, Burns & McDonnell submitted its final proposal of $24.5 million for design services which Fluor incorporated into a revised bid of $216.2 million for the design and construction of the NC Facility. Alas, BAE again rejected this proposal because, in BAE’s estimation, Burns & McDonnell did not give sufficient credit to the existing Lauren design, and “wanted to do more than what [BAE] thought was necessary to complete the design.” Fluor then dropped Burns & McDonnell as the designer and turned to Woods Group

Mustang (“WGM”) to perform the design work for the NC Facility. In October 2015, Fluor and BAE entered into a preliminary agreement referred to as an Undefintized Contract Action (“UCA”) which funded and authorized Fluor to begin limited work while the parties negotiated the final subcontract to design and build the NC Facility. The UCA “constitutes an agreement between the parties on the terms and conditions set forth herein and signifi[ng] the intention of the parties to execute a formal, definitive Firm Fixed Price type Agreement . . . .” (emphasis in original). The UCA further provided that “[p]ending execution of the definitive Agreement by the parties, [Fluor] is hereby authorized, and agrees to, commence work under this UCA, including the purchase of necessary materials, if required, starting October 14, 2015.” (emphasis in original). Finally, the UCA provided that “[t]he definitive Agreement bearing the same start date, will supersede this UCA in its entirety . . . .” Fluor conducted work under the UCA for the next six weeks.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mutual Life Insurnace v. Hill
193 U.S. 551 (Supreme Court, 1904)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Condominium Services, Inc. v. FOA
709 S.E.2d 163 (Supreme Court of Virginia, 2011)
City of Chesapeake v. STATES SELF-INSURERS
628 S.E.2d 539 (Supreme Court of Virginia, 2006)
Plunkett v. Plunkett
624 S.E.2d 39 (Supreme Court of Virginia, 2006)
Asphalt Roads & Materials Co. v. Commonwealth
512 S.E.2d 804 (Supreme Court of Virginia, 1999)
Ross v. Craw
343 S.E.2d 312 (Supreme Court of Virginia, 1986)
Bender-Miller Co. v. Thomwood Farms, Inc.
179 S.E.2d 636 (Supreme Court of Virginia, 1971)
Berry v. Klinger
300 S.E.2d 792 (Supreme Court of Virginia, 1983)
D.C. McClain, Inc. v. Arlington County
452 S.E.2d 659 (Supreme Court of Virginia, 1995)
Glover v. Oppleman
178 F. Supp. 2d 622 (W.D. Virginia, 2001)
Ames v. American National Bank
176 S.E. 204 (Supreme Court of Virginia, 1934)
Route Triple Seven Ltd. Partnership v. Total Hockey, Inc.
127 F. Supp. 3d 607 (E.D. Virginia, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
BAE Systems Ordnance Systems, Inc. v. Fluor Federal Solutions, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bae-systems-ordnance-systems-inc-v-fluor-federal-solutions-llc-vawd-2024.