D.C. McClain, Inc. v. Arlington County

452 S.E.2d 659, 249 Va. 131, 1995 Va. LEXIS 10
CourtSupreme Court of Virginia
DecidedJanuary 13, 1995
DocketRecord 940149
StatusPublished
Cited by93 cases

This text of 452 S.E.2d 659 (D.C. McClain, Inc. v. Arlington County) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D.C. McClain, Inc. v. Arlington County, 452 S.E.2d 659, 249 Va. 131, 1995 Va. LEXIS 10 (Va. 1995).

Opinion

JUSTICE HASSELL

delivered the opinion of the Court.

*133 I.

This appeal involves numerous issues arising out of the breach of a construction contract.

II.

D.C. McClain, Inc. (McClain) executed a contract with Arlington County to construct a bridge in Arlington known as the Loop Road Bridge. McClain filed its motion for judgment against the County and the Board of Supervisors of Arlington County (collectively the County). McClain alleged, among other things, that it incurred damages because the County wrongfully terminated the contract, and that the County’s design of the bridge is purportedly defective.

The County filed a counterclaim, alleging that McClain breached the contract and certain express and implied warranties, and filed a third-party motion for judgment against McClain’s performance and payment bonding company, the Fidelity & Deposit Company of Maryland (Fidelity). The County also filed a third-party motion for judgment against the designer of the bridge, Wilbur Smith Associates, Inc. and its related divisions (collectively Wilbur Smith). The County asserted contract, indemnification, and tort claims against Wilbur Smith.

A jury returned a verdict of $569,000 in favor of McClain on its claims of wrongful termination and damages attributed to the purported design errors. The jury also found in favor of McClain and Fidelity on the County’s claims against them. The jury awarded a verdict of $250,000 in favor of the County on its third-party motion for judgment against Wilbur Smith.

The trial court granted the County’s motion to set aside the verdicts and entered final judgment in favor of the County in the amount of $661,000. The court also set aside the verdict against Wilbur Smith. We awarded McClain and Fidelity an appeal.

III.

Wilbur Smith designed the bridge and provided construction phase engineering services. The bridge was designed as a single-span, cast-in-place, post-tensioned bridge, to be situated upon abutments of an adjoining landowner, Westfield Realty, Inc. (Westfield).

*134 A major portion of the bridge construction work involved a process described as “post-tensioning.” This process required prestressing the poured concrete bridge by adding tension to the tendons. “As these tendons are pulled, the bridge rises and the weight of the bridge shifts to its ultimate load bearing point [s] on the abutment [s]. . . . The pulling of the tendons to add tension, and thereby camber the bridge to its ultimate shape and location, is a process called post-tensioning.” Daniel Curtis McClain, McClain’s president, and Dennis Pisarcik, Fidelity’s' assistant managing attorney, testified that McClain was required to provide the means and methods necessary for the post-tensioning of the bridge.

Mr. McClain visited the site where the bridge was to be constructed and reviewed the plans and specifications for construction before McClain submitted its bid to the County. Mr. McClain knew, before he submitted McClain’s bid and signed the construction contract, that there was not sufficient space between the end of the bridge and the existing bridge abutments to locate the mechanical jacks, which are necessary for the post-tensioning process.

VSL Corporation submitted a bid to McClain to perform the post-tensioning of the bridge before McClain signed the County’s contract, but the bid included an express qualification for the need of eight feet of clear space behind the bridge to perform the posttensioning. VSL included this qualification in its bid because the County’s contract documents did not show the existence of an easement to use Westfield’s property. Henry J. Cronin, vice-president of VSL, specifically told Mr. McClain, before McClain submitted its bid to the County, that an easement to use Westfield’s property was necessary for the post-tensioning process.

William G. Brakefield, an employee of Westfield, had informed Mr. McClain that Westfield would not give McClain the necessary easement. Even though Mr. McClain knew on February 15, 1988 that Westfield would not provide an easement, McClain executed the contract on March 16, 1988 to construct the bridge for $789,755.90. Mr. McClain testified that he did not put an exception in McClain’s bid because he had “always been under the premise that you do not put exceptions on bids, or they will throw your bid out.”

McClain was unable to post-tension the bridge without the easement because of the lack of sufficient space. Subsequently, *135 McClain’s subcontractor, VSL, developed an alternative method for post-tensioning of the bridge by utilizing “blockouts.” This method permitted post-tensioning by creating holes, or blockouts, within the bridge. Mechanical devices would utilize the space created by the “blockouts” to post-tension the bridge. McClain was unable to complete the bridge by using this method because the temporary shoring, which was used to support the bridge before post-tensioning, was not capable of supporting the bridge’s weight.

McClain encountered other problems during its attempt to construct the bridge that resulted in work stoppages. Ultimately, McClain and the County executed Change Order No. 4. This change order required the County to pay McClain an additional $365,000 in return for McClain’s agreement to complete the bridge by July 1, 1990. The change order provided that the additional payment would constitute “full compensation” to complete all remaining work on the bridge, including minor revisions.

A few months after Mr. McClain had signed Change Order No. 4, McClain informed the County that McClain would not complete construction of the bridge unless the County agreed to pay an additional $180,000 and provide an easement for posttensioning. The County refused to acquiesce in these demands and, subsequently, on June 15, 1990, the County sent McClain notice of the County’s intent to terminate the contract. The County terminated the contract on July 20, 1990.

IV.

Familiar principles of contract interpretation are pertinent to our resolution of this appeal. We must enforce the contract between McClain and the County as written, and the contract becomes the law of the case unless the contract is repugnant to some rule of law or public policy. Winn v. Aleda Const. Co., 227 Va. 304, 307, 315 S.E.2d 193, 194 (1984); Mercer v. S. Atlantic Ins. Co., 111 Va. 699, 704, 69 S.E. 961, 962 (1911). It is well-established that when a contract is clear and unambiguous, it is the duty of the court, and not the jury, to decide the meaning of the contract. Winn, 227 Va. at 307, 315 S.E.2d at 194; Russell Co. v. Carroll, 194 Va. 699, 703, 74 S.E.2d 685, 688 (1953); Krikorian v. Dailey, 171 Va. 16, 24, 197 S.E. 442, 446 (1938). Words that the parties used are normally given their usual, ordinary, and popular meaning.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sotherly Hotels Inc. v. Fireman's Fund Ins. Co.
Court of Appeals of Virginia, 2024
Entrepreneur Dream Team v. Anchor Assets, LLC
Court of Appeals of Virginia, 2023
LeClairRyan PLLC
E.D. Virginia, 2023
Adams v. Tavenner
E.D. Virginia, 2023

Cite This Page — Counsel Stack

Bluebook (online)
452 S.E.2d 659, 249 Va. 131, 1995 Va. LEXIS 10, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dc-mcclain-inc-v-arlington-county-va-1995.