Dexis Interactive, Inc., etc. v. International Business & Technical Consultants, Inc.

CourtCourt of Appeals of Virginia
DecidedJuly 9, 2024
Docket0689234
StatusUnpublished

This text of Dexis Interactive, Inc., etc. v. International Business & Technical Consultants, Inc. (Dexis Interactive, Inc., etc. v. International Business & Technical Consultants, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dexis Interactive, Inc., etc. v. International Business & Technical Consultants, Inc., (Va. Ct. App. 2024).

Opinion

COURT OF APPEALS OF VIRGINIA UNPUBLISHED

Present: Chief Judge Decker, Judges O’Brien and AtLee Argued at Fredericksburg, Virginia

DEXIS INTERACTIVE, INC., d/b/a DEXIS CONSULTING GROUP MEMORANDUM OPINION* BY v. Record No. 0689-23-4 JUDGE MARY GRACE O’BRIEN JULY 9, 2024 INTERNATIONAL BUSINESS & TECHNICAL CONSULTANTS, INC.

FROM THE CIRCUIT COURT OF FAIRFAX COUNTY Penney S. Azcarate, Judge

Benjamin S. Boyd (Dawn Stern; DLA Piper LLP, on briefs), for appellant.

Matthew E. Feinberg (PilieroMazza PLLC, on brief), for appellee.

Appellant Dexis Interactive, Inc. (Dexis) and appellee International Business & Technical

Consultants, Inc. (IBTCI) are teaming partners on a federal government contract. During the

contract period, a dispute arose over the share of work that IBTCI is obligated to assign to Dexis

after additional funds were unexpectedly allocated to the contracted project. Dexis sued, but the

court sustained IBTCI’s plea in bar and dismissed Dexis’s suit with prejudice, finding that the plain

language of the contract did not support Dexis’s claims. Dexis appeals.

BACKGROUND1

On June 11, 2019, Dexis and IBTCI agreed to pursue a federal government contract with the

United States Agency for International Development (USAID). IBTCI would serve as the prime

* This opinion is not designated for publication. See Code § 17.1-413(A). 1 The material facts dispositive of this appeal are undisputed. contractor and Dexis as a subcontractor for the federal contract. The parties were successful in their

bid, and IBTCI executed a “Prime Contract” with USAID on October 15, 2019, valued at

approximately $70,000,000.

IBTCI and Dexis entered into a subcontract to begin on October 15, 2019, and to run until

October 14, 2024. The subcontract incorporated by reference a “Subcontractor’s Statement of

Work.” The statement of work set a target workshare for Dexis of 40%, with a maximum of 41.5%

and a floor of 38.5%, “as well as 100% of the total [d]irect costs associated with TDM2 for that

labor over the life of the contract,” and IBTCI was obligated to “make a good faith effort to achieve

the agreed-upon workshare.” The subcontract estimated the total cost of the work Dexis was to

perform at $24,776,518, with a fixed fee for Dexis of $1,238,826, for a total subcontract value of

$26,015,344. The statement of work and the subcontract contain no provisions about allocation of

work in excess of total subcontract value.

The subcontract expressly stated that the “[t]otal Subcontract Costs shall not exceed the total

cost and fee” provided above and that the “total cost stated above may not be adjusted without

written modification signed by IBTCI.” The subcontract included an “Order of Precedence”

provision providing that “[i]n the event of an inconsistency or conflict between documents, the

inconsistency shall be resolved by giving precedence” first to the subcontract, then to the statement

of work, then to the other parts of the subcontract in a specified order. The subcontract further

stated that it is “the complete and exclusive statement thereof between the parties and that it

supersedes and merges all prior proposals and understandings, and all other agreements, whether

oral or written, between the parties” and that the contract between them “shall be governed only by

the terms and conditions of this Agreement.”

2 TDM is a “USAID approved Technical Directions Memorandum.” -2- On February 3, 2022—more than two years after Dexis and IBTCI entered into the

subcontract—USAID notified IBTCI that it intended to increase the value of the prime contract

from the initial $70,000,000 by an additional $55,000,000. A dispute arose between the parties as to

what share of the additional contract value that IBTCI would allocate to Dexis. On February 7,

2022, IBTCI notified Dexis that its workshare of the additional $55,000,000 provided by USAID

would be 15%.

Dexis objected to the 15% workshare and invoked the subcontract’s dispute resolution

clause. When the parties were unable to resolve the dispute, Dexis sued IBTCI. Dexis alleged

anticipatory breach of contract and sought declaratory judgment that it was entitled to a 40%

workshare of the additional $55,000,000 provided by USAID, an injunction ordering IBTCI to

allocate a 40% workshare of the new funding to Dexis, and specific performance.

IBTCI filed a plea in bar denying that Dexis was entitled to a 40% workshare of the

additional funds. IBTCI argued that the subcontract itself contradicted Dexis’s claims, and so Dexis

failed to present a justiciable claim.3 In response, Dexis argued that the plea in bar was not a proper

dispositive motion because it constituted “an impermissible plea of the general issue” and violated

Rule 3:8(a). See Rule 3:8(a) (“A general denial of the entire complaint or plea of the general issue

is not permitted.”).

The court sustained IBTCI’s plea in bar and dismissed Dexis’s complaint with prejudice.

The court found that because IBTCI’s defense rested not on disputed facts, but on the text of the

subcontract, a plea in bar was proper. Interpreting the plain language of the subcontract itself, the

court concluded that the subcontract did not cover the additional funding beyond the $70,000,000

3 IBTCI also argued that Dexis’s claim was “premised upon an unenforceable agreement to agree” and that Dexis was not entitled to equitable relief. IBTCI reasserts those arguments on appeal. Because of our ruling that the plain language of the contract does not support Dexis’s claim, we do not reach this issue. -3- originally allocated, that it could not “read that into the contract when it is clear on its own terms,”

and that “because th[e] subcontract speaks for itself, there is not an actual controversy between the

parties” suitable for declaratory judgment. Additionally, the court rejected Dexis’s prayer for

specific performance on the ground that such relief “is not available as a remedy in lawsuits

involving contracts for services of labor,” and rejected its request for injunctive relief, reasoning that

even if Dexis had a valid claim, there would be an adequate remedy at law.

ANALYSIS

Dexis raises ten assignments of error, arguing that IBTCI’s plea in bar was an improper plea

of the general issue, that the court misinterpreted the subcontract, and that the court erred by finding

that there was no justiciable controversy and that Dexis was not entitled to injunctive relief or

specific performance.

“In this case, as in all others, we seek to decide cases, ‘on the best and narrowest ground

available’ from the record.” Foltz v. Commonwealth, 58 Va. App. 107, 114 (2011) (en banc)

(quoting Kirby v. Commonwealth, 50 Va. App. 691, 698 n.2 (2007)), aff’d, 284 Va. 467 (2012).

“This approach encourages ‘judicial self-restraint’ by avoiding the resolution of broad, reasonably

debatable legal issues when narrower, less debatable legal issues fully dispose of the appeal before

the court.” Id. (quoting Cooper v. Commonwealth, 54 Va. App. 558, 566 (2009)); see also

Theologis v. Weiler, 76 Va. App. 596, 603, 605 n.5 (2023) (noting the “large number of issues

presented” in the appeal, finding that the best and narrowest ground on which to decide the case

was on the merits, and “express[ing] no opinion on the other issues” raised by the appellant,

including whether the issues “could be reached on demurrer”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PBM NUTRITIONALS, LLC v. Lexington Ins. Co.
724 S.E.2d 707 (Supreme Court of Virginia, 2012)
Envtl. Staffing v. B & R Const. Mgmt.
725 S.E.2d 550 (Supreme Court of Virginia, 2012)
LANDMARK HHH, LLC v. Gi Hwa Park
671 S.E.2d 143 (Supreme Court of Virginia, 2009)
Eure v. Norfolk Shipbuilding & Drydock Corp.
561 S.E.2d 663 (Supreme Court of Virginia, 2002)
TM Delmarva Power, L.L.C. v. NCP of Virginia, L.L.C.
557 S.E.2d 199 (Supreme Court of Virginia, 2002)
American Spirit Insurance v. Owens
541 S.E.2d 553 (Supreme Court of Virginia, 2001)
Orthopaedic and Spine Center v. Muller Martini Manufacturing Corp.
737 S.E.2d 544 (Court of Appeals of Virginia, 2013)
Foltz v. Commonwealth
706 S.E.2d 914 (Court of Appeals of Virginia, 2011)
Cooper v. Commonwealth
680 S.E.2d 361 (Court of Appeals of Virginia, 2009)
Kirby v. Commonwealth
653 S.E.2d 600 (Court of Appeals of Virginia, 2007)
D.C. McClain, Inc. v. Arlington County
452 S.E.2d 659 (Supreme Court of Virginia, 1995)
City of Chesapeake v. Dominion Securityplus Self Storage, L.L.C.
785 S.E.2d 403 (Supreme Court of Virginia, 2016)
Fluor Enterprises, Inc. v. United States
64 Fed. Cl. 461 (Federal Claims, 2005)
Scott v. Albemarle Horse Show Ass'n
104 S.E. 842 (Supreme Court of Virginia, 1920)
Ames v. American National Bank
176 S.E. 204 (Supreme Court of Virginia, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
Dexis Interactive, Inc., etc. v. International Business & Technical Consultants, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/dexis-interactive-inc-etc-v-international-business-technical-vactapp-2024.