COURT OF APPEALS OF VIRGINIA UNPUBLISHED
Present: Chief Judge Decker, Judges O’Brien and AtLee Argued at Fredericksburg, Virginia
DEXIS INTERACTIVE, INC., d/b/a DEXIS CONSULTING GROUP MEMORANDUM OPINION* BY v. Record No. 0689-23-4 JUDGE MARY GRACE O’BRIEN JULY 9, 2024 INTERNATIONAL BUSINESS & TECHNICAL CONSULTANTS, INC.
FROM THE CIRCUIT COURT OF FAIRFAX COUNTY Penney S. Azcarate, Judge
Benjamin S. Boyd (Dawn Stern; DLA Piper LLP, on briefs), for appellant.
Matthew E. Feinberg (PilieroMazza PLLC, on brief), for appellee.
Appellant Dexis Interactive, Inc. (Dexis) and appellee International Business & Technical
Consultants, Inc. (IBTCI) are teaming partners on a federal government contract. During the
contract period, a dispute arose over the share of work that IBTCI is obligated to assign to Dexis
after additional funds were unexpectedly allocated to the contracted project. Dexis sued, but the
court sustained IBTCI’s plea in bar and dismissed Dexis’s suit with prejudice, finding that the plain
language of the contract did not support Dexis’s claims. Dexis appeals.
BACKGROUND1
On June 11, 2019, Dexis and IBTCI agreed to pursue a federal government contract with the
United States Agency for International Development (USAID). IBTCI would serve as the prime
* This opinion is not designated for publication. See Code § 17.1-413(A). 1 The material facts dispositive of this appeal are undisputed. contractor and Dexis as a subcontractor for the federal contract. The parties were successful in their
bid, and IBTCI executed a “Prime Contract” with USAID on October 15, 2019, valued at
approximately $70,000,000.
IBTCI and Dexis entered into a subcontract to begin on October 15, 2019, and to run until
October 14, 2024. The subcontract incorporated by reference a “Subcontractor’s Statement of
Work.” The statement of work set a target workshare for Dexis of 40%, with a maximum of 41.5%
and a floor of 38.5%, “as well as 100% of the total [d]irect costs associated with TDM2 for that
labor over the life of the contract,” and IBTCI was obligated to “make a good faith effort to achieve
the agreed-upon workshare.” The subcontract estimated the total cost of the work Dexis was to
perform at $24,776,518, with a fixed fee for Dexis of $1,238,826, for a total subcontract value of
$26,015,344. The statement of work and the subcontract contain no provisions about allocation of
work in excess of total subcontract value.
The subcontract expressly stated that the “[t]otal Subcontract Costs shall not exceed the total
cost and fee” provided above and that the “total cost stated above may not be adjusted without
written modification signed by IBTCI.” The subcontract included an “Order of Precedence”
provision providing that “[i]n the event of an inconsistency or conflict between documents, the
inconsistency shall be resolved by giving precedence” first to the subcontract, then to the statement
of work, then to the other parts of the subcontract in a specified order. The subcontract further
stated that it is “the complete and exclusive statement thereof between the parties and that it
supersedes and merges all prior proposals and understandings, and all other agreements, whether
oral or written, between the parties” and that the contract between them “shall be governed only by
the terms and conditions of this Agreement.”
2 TDM is a “USAID approved Technical Directions Memorandum.” -2- On February 3, 2022—more than two years after Dexis and IBTCI entered into the
subcontract—USAID notified IBTCI that it intended to increase the value of the prime contract
from the initial $70,000,000 by an additional $55,000,000. A dispute arose between the parties as to
what share of the additional contract value that IBTCI would allocate to Dexis. On February 7,
2022, IBTCI notified Dexis that its workshare of the additional $55,000,000 provided by USAID
would be 15%.
Dexis objected to the 15% workshare and invoked the subcontract’s dispute resolution
clause. When the parties were unable to resolve the dispute, Dexis sued IBTCI. Dexis alleged
anticipatory breach of contract and sought declaratory judgment that it was entitled to a 40%
workshare of the additional $55,000,000 provided by USAID, an injunction ordering IBTCI to
allocate a 40% workshare of the new funding to Dexis, and specific performance.
IBTCI filed a plea in bar denying that Dexis was entitled to a 40% workshare of the
additional funds. IBTCI argued that the subcontract itself contradicted Dexis’s claims, and so Dexis
failed to present a justiciable claim.3 In response, Dexis argued that the plea in bar was not a proper
dispositive motion because it constituted “an impermissible plea of the general issue” and violated
Rule 3:8(a). See Rule 3:8(a) (“A general denial of the entire complaint or plea of the general issue
is not permitted.”).
The court sustained IBTCI’s plea in bar and dismissed Dexis’s complaint with prejudice.
The court found that because IBTCI’s defense rested not on disputed facts, but on the text of the
subcontract, a plea in bar was proper. Interpreting the plain language of the subcontract itself, the
court concluded that the subcontract did not cover the additional funding beyond the $70,000,000
3 IBTCI also argued that Dexis’s claim was “premised upon an unenforceable agreement to agree” and that Dexis was not entitled to equitable relief. IBTCI reasserts those arguments on appeal. Because of our ruling that the plain language of the contract does not support Dexis’s claim, we do not reach this issue. -3- originally allocated, that it could not “read that into the contract when it is clear on its own terms,”
and that “because th[e] subcontract speaks for itself, there is not an actual controversy between the
parties” suitable for declaratory judgment. Additionally, the court rejected Dexis’s prayer for
specific performance on the ground that such relief “is not available as a remedy in lawsuits
involving contracts for services of labor,” and rejected its request for injunctive relief, reasoning that
even if Dexis had a valid claim, there would be an adequate remedy at law.
ANALYSIS
Dexis raises ten assignments of error, arguing that IBTCI’s plea in bar was an improper plea
of the general issue, that the court misinterpreted the subcontract, and that the court erred by finding
that there was no justiciable controversy and that Dexis was not entitled to injunctive relief or
specific performance.
“In this case, as in all others, we seek to decide cases, ‘on the best and narrowest ground
available’ from the record.” Foltz v. Commonwealth, 58 Va. App. 107, 114 (2011) (en banc)
(quoting Kirby v. Commonwealth, 50 Va. App. 691, 698 n.2 (2007)), aff’d, 284 Va. 467 (2012).
“This approach encourages ‘judicial self-restraint’ by avoiding the resolution of broad, reasonably
debatable legal issues when narrower, less debatable legal issues fully dispose of the appeal before
the court.” Id. (quoting Cooper v. Commonwealth, 54 Va. App. 558, 566 (2009)); see also
Theologis v. Weiler, 76 Va. App. 596, 603, 605 n.5 (2023) (noting the “large number of issues
presented” in the appeal, finding that the best and narrowest ground on which to decide the case
was on the merits, and “express[ing] no opinion on the other issues” raised by the appellant,
including whether the issues “could be reached on demurrer”).
Free access — add to your briefcase to read the full text and ask questions with AI
COURT OF APPEALS OF VIRGINIA UNPUBLISHED
Present: Chief Judge Decker, Judges O’Brien and AtLee Argued at Fredericksburg, Virginia
DEXIS INTERACTIVE, INC., d/b/a DEXIS CONSULTING GROUP MEMORANDUM OPINION* BY v. Record No. 0689-23-4 JUDGE MARY GRACE O’BRIEN JULY 9, 2024 INTERNATIONAL BUSINESS & TECHNICAL CONSULTANTS, INC.
FROM THE CIRCUIT COURT OF FAIRFAX COUNTY Penney S. Azcarate, Judge
Benjamin S. Boyd (Dawn Stern; DLA Piper LLP, on briefs), for appellant.
Matthew E. Feinberg (PilieroMazza PLLC, on brief), for appellee.
Appellant Dexis Interactive, Inc. (Dexis) and appellee International Business & Technical
Consultants, Inc. (IBTCI) are teaming partners on a federal government contract. During the
contract period, a dispute arose over the share of work that IBTCI is obligated to assign to Dexis
after additional funds were unexpectedly allocated to the contracted project. Dexis sued, but the
court sustained IBTCI’s plea in bar and dismissed Dexis’s suit with prejudice, finding that the plain
language of the contract did not support Dexis’s claims. Dexis appeals.
BACKGROUND1
On June 11, 2019, Dexis and IBTCI agreed to pursue a federal government contract with the
United States Agency for International Development (USAID). IBTCI would serve as the prime
* This opinion is not designated for publication. See Code § 17.1-413(A). 1 The material facts dispositive of this appeal are undisputed. contractor and Dexis as a subcontractor for the federal contract. The parties were successful in their
bid, and IBTCI executed a “Prime Contract” with USAID on October 15, 2019, valued at
approximately $70,000,000.
IBTCI and Dexis entered into a subcontract to begin on October 15, 2019, and to run until
October 14, 2024. The subcontract incorporated by reference a “Subcontractor’s Statement of
Work.” The statement of work set a target workshare for Dexis of 40%, with a maximum of 41.5%
and a floor of 38.5%, “as well as 100% of the total [d]irect costs associated with TDM2 for that
labor over the life of the contract,” and IBTCI was obligated to “make a good faith effort to achieve
the agreed-upon workshare.” The subcontract estimated the total cost of the work Dexis was to
perform at $24,776,518, with a fixed fee for Dexis of $1,238,826, for a total subcontract value of
$26,015,344. The statement of work and the subcontract contain no provisions about allocation of
work in excess of total subcontract value.
The subcontract expressly stated that the “[t]otal Subcontract Costs shall not exceed the total
cost and fee” provided above and that the “total cost stated above may not be adjusted without
written modification signed by IBTCI.” The subcontract included an “Order of Precedence”
provision providing that “[i]n the event of an inconsistency or conflict between documents, the
inconsistency shall be resolved by giving precedence” first to the subcontract, then to the statement
of work, then to the other parts of the subcontract in a specified order. The subcontract further
stated that it is “the complete and exclusive statement thereof between the parties and that it
supersedes and merges all prior proposals and understandings, and all other agreements, whether
oral or written, between the parties” and that the contract between them “shall be governed only by
the terms and conditions of this Agreement.”
2 TDM is a “USAID approved Technical Directions Memorandum.” -2- On February 3, 2022—more than two years after Dexis and IBTCI entered into the
subcontract—USAID notified IBTCI that it intended to increase the value of the prime contract
from the initial $70,000,000 by an additional $55,000,000. A dispute arose between the parties as to
what share of the additional contract value that IBTCI would allocate to Dexis. On February 7,
2022, IBTCI notified Dexis that its workshare of the additional $55,000,000 provided by USAID
would be 15%.
Dexis objected to the 15% workshare and invoked the subcontract’s dispute resolution
clause. When the parties were unable to resolve the dispute, Dexis sued IBTCI. Dexis alleged
anticipatory breach of contract and sought declaratory judgment that it was entitled to a 40%
workshare of the additional $55,000,000 provided by USAID, an injunction ordering IBTCI to
allocate a 40% workshare of the new funding to Dexis, and specific performance.
IBTCI filed a plea in bar denying that Dexis was entitled to a 40% workshare of the
additional funds. IBTCI argued that the subcontract itself contradicted Dexis’s claims, and so Dexis
failed to present a justiciable claim.3 In response, Dexis argued that the plea in bar was not a proper
dispositive motion because it constituted “an impermissible plea of the general issue” and violated
Rule 3:8(a). See Rule 3:8(a) (“A general denial of the entire complaint or plea of the general issue
is not permitted.”).
The court sustained IBTCI’s plea in bar and dismissed Dexis’s complaint with prejudice.
The court found that because IBTCI’s defense rested not on disputed facts, but on the text of the
subcontract, a plea in bar was proper. Interpreting the plain language of the subcontract itself, the
court concluded that the subcontract did not cover the additional funding beyond the $70,000,000
3 IBTCI also argued that Dexis’s claim was “premised upon an unenforceable agreement to agree” and that Dexis was not entitled to equitable relief. IBTCI reasserts those arguments on appeal. Because of our ruling that the plain language of the contract does not support Dexis’s claim, we do not reach this issue. -3- originally allocated, that it could not “read that into the contract when it is clear on its own terms,”
and that “because th[e] subcontract speaks for itself, there is not an actual controversy between the
parties” suitable for declaratory judgment. Additionally, the court rejected Dexis’s prayer for
specific performance on the ground that such relief “is not available as a remedy in lawsuits
involving contracts for services of labor,” and rejected its request for injunctive relief, reasoning that
even if Dexis had a valid claim, there would be an adequate remedy at law.
ANALYSIS
Dexis raises ten assignments of error, arguing that IBTCI’s plea in bar was an improper plea
of the general issue, that the court misinterpreted the subcontract, and that the court erred by finding
that there was no justiciable controversy and that Dexis was not entitled to injunctive relief or
specific performance.
“In this case, as in all others, we seek to decide cases, ‘on the best and narrowest ground
available’ from the record.” Foltz v. Commonwealth, 58 Va. App. 107, 114 (2011) (en banc)
(quoting Kirby v. Commonwealth, 50 Va. App. 691, 698 n.2 (2007)), aff’d, 284 Va. 467 (2012).
“This approach encourages ‘judicial self-restraint’ by avoiding the resolution of broad, reasonably
debatable legal issues when narrower, less debatable legal issues fully dispose of the appeal before
the court.” Id. (quoting Cooper v. Commonwealth, 54 Va. App. 558, 566 (2009)); see also
Theologis v. Weiler, 76 Va. App. 596, 603, 605 n.5 (2023) (noting the “large number of issues
presented” in the appeal, finding that the best and narrowest ground on which to decide the case
was on the merits, and “express[ing] no opinion on the other issues” raised by the appellant,
including whether the issues “could be reached on demurrer”).
With these principles in mind, we find that the best and narrowest ground on which to
decide this appeal is that the plain language of the subcontract does not support Dexis’s claims, and
hold that IBTCI’s contractual obligation to allocate approximately 40% of the project workshare to
-4- Dexis extended only to the $70,000,000 in funding originally provided by USAID under the prime
contract.
“Basic contract interpretation principles dictate that ‘[w]hen the terms in a contract are
clear and unambiguous, the contract is construed according to its plain meaning.’” Orthopaedic
& Spine Ctr. v. Muller Martini Mfg. Corp., 61 Va. App. 482, 490 (2013) (alteration in original)
(quoting Env’t Staffing Acquisition Corp. v. B & R Constr. Mgmt., 283 Va. 787, 793 (2012)). “It
is a basic tenet of Virginia law that the courts, when interpreting a contract, ‘construe it as
written’ and do ‘not add terms the parties themselves did not include.’” PBM Nutritionals, LLC
v. Lexington Ins. Co., 283 Va. 624, 636 (2012) (quoting Landmark HHH, LLC v. Gi Hwa Park,
277 Va. 50, 57 (2009)). The “[w]ords that the parties used are normally given their usual,
ordinary, and popular meaning,” and “[n]o word or clause in the contract will be treated as
meaningless if a reasonable meaning can be given to it, and there is a presumption that the
parties have not used words needlessly.” Preferred Sys. Solutions, Inc. v. GP Consulting, LLC,
284 Va. 382, 392 (2012) (second alteration in original) (quoting D.C. McClain, Inc. v. Arlington
Cnty., 249 Va. 131, 135-36 (1995)). Appellate courts review issues of contract interpretation de
novo and have an “equal opportunity to consider the words of the contract within the four
corners of the instrument itself.” Eure v. Norfolk Shipbuilding & Drydock Corp., 263 Va. 624,
631 (2002); see also City of Chesapeake v. Dominion Securityplus Self Storage, LLC, 291 Va.
327, 334 (2016).
By its own description, the subcontract between Dexis and IBTCI is a “Cost-Plus-Fixed-Fee
. . . Completion type” contract. A “cost-plus-fixed-fee contract,” as defined in the Code of Federal
Regulations, “is a cost-reimbursement contract that provides for payment to the contractor of a
negotiated fee that is fixed at the inception of the contract.” 48 C.F.R. § 16.306(a) (emphasis
added). A “completion type” or “completion form” cost-plus-fixed-fee contract “describes a typical
-5- contract in which the scope of work is stated as a definite goal usually resulting in some end
product.” Fluor Enters., Inc. v. United States, 64 Fed. Cl. 461, 467 (2005); see also 48 C.F.R.
§ 16.306(d)(1). The subcontract sets a five-year term from October 15, 2019 to October 14, 2024
and provides that the “estimated cost for the performance of the work required under th[e]
subcontract, exclusive of fixed fee is $24,776,518.” The “fixed fee” to be earned by Dexis is
$1,238,826, for a total subcontract value of $26,015,344. The subcontract expressly states that the
“Total Subcontract Costs shall not exceed the total cost and fee listed above” and that the “total cost
stated above may not be adjusted without written modification signed by IBTCI.” As IBTCI
correctly argues, a “‘not to exceed’ value means just that—the amount disclosed is the maximum
amount to be paid to the subcontractor.” Thus, on its face, the subcontract entitles Dexis to
$26,015,344 (performance cost plus fixed fee) and does not obligate IBTCI to allocate to Dexis any
portion of additional work that it may receive from USAID.
Dexis sees things differently and relies mainly on two provisions in the statement of work,
which was incorporated by reference into the subcontract. In its view, the clause in the statement of
work that IBTCI would “make a good faith effort to achieve the agreed-upon workshare” obligates
IBTCI to “‘make a good faith effort’ to provide Dexis with a targeted workshare of 40% of the total
work under the USAID contract,” and not merely 40% of the initial allocation from USAID
contemplated when the parties entered into the subcontract. Dexis also argues that the provision in
the statement of work setting the workshare to be “a range of no less than 38.5% up to 41.5%, as
well as 100% of the total Direct costs associated with TDM for that labor over the life of the
contract” supports its claim to a 40% share of all the work USAID allocates to IBTCI over the
five-year life of the contract, including the additional $55,000,000. (Emphasis added).
We do not, however, read contract terms in isolation. See TM Delmarva Power, LLC v.
NCP of Va., LLC, 263 Va. 116, 119 (2001). Rather, “contracts must be considered as a whole
-6- ‘without giving emphasis to isolated terms.’” Id. (quoting American Spirit Ins. Co. v. Owens, 261
Va. 270, 275 (2001)). Considering the subcontract as a whole, Dexis’s arguments are unpersuasive.
The statement of work itself describes the $26,015,344 allocated to Dexis as the “subcontract
ceiling” and describes the 41.5% maximum workshare as the basis upon which this ceiling was
calculated.4 This provides the relevant lens under which we view the “good faith” and “life of the
contract” provisions in the statement of work. Viewing those provisions through that lens, they do
not support Dexis’s arguments that IBTCI was obliged to provide a portion of any additional work
that might be allocated by USAID beyond that envisioned at the outset of the subcontract.
Additionally, the subcontract includes an “Order of Precedence” provision stating that “[i]n
the event of an inconsistency or conflict between the documents” comprising the subcontract, “the
inconsistency shall be resolved by giving precedence” first to the subcontract, then to the statement
of work, and then to certain other documents in a specified order. By the straightforward terms of
the subcontract’s “Order of Precedence” clause, the statement of work must yield to the provisions
in the subcontract. And the subcontract explicitly states that the “Total Subcontract Costs shall not
exceed” $26,015,344 and that the “total cost stated above may not be adjusted without written
modification signed by IBTCI.”
Thus, when “construed as a whole” and “effect [is] given to every provision,” the plain,
unambiguous language of the subcontract sets the value of Dexis’s workshare at $26,015,344
(inclusive of its $1,238,826 fixed fee) as a ceiling which “may not be adjusted without [a] written
modification signed by IBTCI” and does not establish a contractual obligation for IBTCI to
allocate approximately 40% of the workshare of the additional $55,000,000 provided by USAID to
Dexis. Ames v. American Nat’l Bank of Portsmouth, 163 Va. 1, 38-39 (1934) (quoting Scott v.
Albemarle Horse Show Ass’n, 128 Va. 517, 526 (1920)).
See Subcontract Schedule A-1, “illustrat[ing] this workshare model” and using a 4
“41.5% workshare” “to determine the subcontract ceiling.” -7- CONCLUSION
For these reasons, we affirm the court’s judgment.
Affirmed.
-8-