Multiscaff Limited v. Aptim Federal Services, LLC

CourtDistrict Court, E.D. Virginia
DecidedJanuary 22, 2024
Docket1:23-cv-01369
StatusUnknown

This text of Multiscaff Limited v. Aptim Federal Services, LLC (Multiscaff Limited v. Aptim Federal Services, LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Multiscaff Limited v. Aptim Federal Services, LLC, (E.D. Va. 2024).

Opinion

IN IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF VIRGINIA Alexandria Division MULTISCAFF LIMITED, Plaintiff, v. Civil No. 1:23cv1369 (DIN) APTIM FEDERAL SERVICES, LLC, Defendant. MEMORANDUM OPINION

At issue in this breach of contract action is a simple question: who pays? Plaintiff Multiscaff Limited (“Multiscaff’) was hired by subcontractor Ferrous Protection Limited (“FPL”) to provide scaffolding and other materials for a construction project on the island of Diego Garcia. FPL was in turn retained by Defendant Aptim Federal Services, LLC (“APTIM”), the general contractor for the project. FPL’s performance fell flat, leading APTIM to terminate and replace FPL. Termination contractually entitled APTIM to retain all material then in use by FPL — including Multiscaff’s materials. Multiscaff believes that APTIM’s right of retention came with a corresponding commitment to compensate Multiscaff. But in APTIM’s view, FPL was the only party contractually obliged to pay. Multiscaff posits that APTIM wants to have its cake and eat it too, receiving all of the benefits that flowed from Multiscaff without assuming any of the liabilities. APTIM views this as a case of sour grapes. Multiscaff, in APTIM’s view, was content to be reimbursed by FPL until FPL became insolvent, at which time Multiscaff turned its gaze to the one party with the means to pay. There is no dispute that from December 2020 to the present, APTIM retained and used Multiscaff’s materials, and that Multiscaff was not

paid for this use. Nor is there any dispute that Multiscaff has a legal claim for reimbursement. The only question is who must pay — APTIM or FPL? Multiscaff sued APTIM for unjust enrichment, quantum meruit, conversion, and after amendment of the complaint, breach of contract. APTIM responded with a counterclaim for breach of contract. The parties have now filed cross motions for summary judgment. For the reasons that follow, the Court will GRANT IN PART and DENY IN PART APTIM’s motion for summary judgment (ECF. No. 61). In addition, the Court will DENY Multiscaff’s motion for partial summary judgment (ECF. No. 64). Specifically, APTIM is entitled to judgment as a matter of law on Multiscaff’s claim for quantum meruit. The motions are denied in all other respects. I. SUMMARY JUDGMENT EVIDENCE Summary judgment is appropriate “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). Once the movant has met its burden of showing that there is no material dispute, the nonmovant must then demonstrate with specific evidence that there exists a genuine disputed issue of material fact. Matsushita Elec. Indus. Co. Ltd. v. Zenith Radio Corp., 475 U.S. 574, 586-87 (1986). A fact is material if it “might affect the outcome of the suit under the governing law.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). All “justifiable inferences are to be drawn in the [nonmovant’s] favor.” Jd. at 255. However, the nonmovant “cannot create a genuine issue of material fact through mere speculation or the building of one inference upon another.” Beale v. Hardy, 769 F.2d 213, 214 (4th Cir. 1985). Because summary judgment requires an assessment of the undisputed facts, Local Civil Rule 56(b) directs a movant to include an enumerated list of material facts as to which the movant

contends that no genuine dispute exists. The nonmovant must then respond by stating whether the fact is disputed or admitted, and if disputed, to provide citations to evidence in the record supporting the claim of a factual dispute. The following undisputed facts are derived from the parties’ submissions and the factual record: e Multiscaff is a limited liability company incorporated in the United Kingdom with a principal place of business in Lancashire, England. (ECF No. 90 (“Am. Compl.”) § 2.) e APTIM is a Louisiana limited liability company headquartered in Baton Rouge, Louisiana. APTIM’s principal place of business was previously Alexandria, Virginia, but APTIM relocated to Baton Rouge in July 2020. APTIM’s sole member is Aptim Government Solutions, LLC, a Louisiana limited liability company. The sole member of Aptim Government Solutions is Aptim Corp., a Delaware corporation with its principal place of business in Louisiana. (ECF No. 10 (“Corporate Disclosure”)); (ECF No. 20-1 (“Aidan Delgado Decl.”) f 3, 5.) e On February 28, 2017, APTIM entered an indefinite delivery, indefinite quantity contract (the “IDIQ Contract”) (ECF No. 45-1) with the Air Force Civil Engineering Center (““AFCEC”).! Under the IDIQ Contract, AFCEC would issue individual task orders to APTIM. (ECF No. 75-1 (APTIM’s Response to Multiscaff’s Statement of Facts (hereinafter, “AR_SOF”) § 2)). e Pursuant to the IDIQ Contract, on July 25, 2018, AFCEC issued a task order to APTIM to repair storage tanks located at Naval Support Facility Diego Garcia, a military installation in the British Indian Ocean Territory (hereinafter, the “Project” and, as to the task order, the “Prime Contract”). AR_SOF 93; (ECF No. 39-1 (“Prime Contract”) at 1, 5). e On December 1, 2018, APTIM entered a subcontract with FPL (the “AF Contract”) (ECF No. 34-1), a U.K. corporation, under which FPL was to provide APTIM with material and equipment related to the Diego Garcia Project. In exchange, APTIM agreed to pay FPL a fixed lump sum of $4,486,560. The AF Contract was negotiated and executed in Dallas, Texas. AR_SOF 5-6; (ECF No. 79-1 (Multiscaff’s Response to APTIM’s Statement of Facts (hereinafter, SOF”) 2)); (ECF No. 49 (Mem. Op. on Mot. to Dismiss (the “MTD Op.”) at 4)); AF Contract at 2. e The AF Contract incorporated Standard Terms and Conditions (“T&Cs”), which required FPL to obtain the prior written approval of APTIM before FPL subcontracted An IDIQ contract “allows an indefinite quantity of services for a fixed time. This method is used when a contracting agency anticipates a recurring need but has not determined, above a specified minimum, the precise quantities of services that it will require during the contract period.” 23 C.F.R. § 635.602.

any part of FPL’s work. Any subcontractors to FPL were to be bound to the obligations of the AF Contract. FPL was responsible for payment to subcontractors, and APTIM was to be made a third-party beneficiary of any subcontracts. AF Contract T&Cs § 10. e Inthe event of a breach by FPL, APTIM was entitled to terminate the AF Contract and “to take possession of and use any of the materials, tools, equipment, supplies and other property then in use by [FPL] for such Subcontract Work or present on the Project site.” The cost of completing any of FPL’s outstanding work was to be charged to FPL. Additionally, upon termination, FPL was required to “[a]ssign to [APTIM] subcontracts . . . and any and all other agreements, as designed by [APTIM].” AF Contract T&Cs § 25. e The AF Contract is governed by Virginia law. MTD Op. at 8-11; AF Contract T&Cs § 30. e On January 29, 2019, FPL entered a subcontract with Multiscaff (the “FM Contract”), under which Multiscaff was to provide scaffolding, sheeting and support personnel for the Project. The FM Contract is “back to back” with the AF Contract.2 APTIM was not a party to the FM Contract. FM Contract at 1-2 (ECF No. 65-3); MR_SOF {7 4-5; AR_SOF 4 11. e The FM Contract was to begin when the last shipping container of Multiscaff’s material left Multiscaff’s depot and was to conclude when the last container was returned to the depot.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Great Western Telegraph Co. v. Burnham
162 U.S. 339 (Supreme Court, 1896)
Messenger v. Anderson
225 U.S. 436 (Supreme Court, 1912)
Klebe v. United States
263 U.S. 188 (Supreme Court, 1923)
Morissette v. United States
342 U.S. 246 (Supreme Court, 1952)
Archawski v. Hanioti
350 U.S. 532 (Supreme Court, 1956)
Leroy v. Great Western United Corp.
443 U.S. 173 (Supreme Court, 1979)
Arizona v. California
460 U.S. 605 (Supreme Court, 1983)
Arizona v. California
466 U.S. 144 (Supreme Court, 1984)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Christianson v. Colt Industries Operating Corp.
486 U.S. 800 (Supreme Court, 1988)
Hercules, Inc. v. United States
516 U.S. 417 (Supreme Court, 1996)
Great-West Life & Annuity Insurance v. Knudson
534 U.S. 204 (Supreme Court, 2002)
Lashawn A. v. Marion S. Barry, Jr.
87 F.3d 1389 (D.C. Circuit, 1996)
TFWS, Inc. v. Franchot
572 F.3d 186 (Fourth Circuit, 2009)
Abi-Najm v. Concord Condominium, LLC
699 S.E.2d 483 (Supreme Court of Virginia, 2010)
DUNN CONST. CO. v. Cloney
682 S.E.2d 943 (Supreme Court of Virginia, 2009)
Mongold v. Woods
677 S.E.2d 288 (Supreme Court of Virginia, 2009)
PMA Capital Ins. Co. v. US Airways, Inc.
626 S.E.2d 369 (Supreme Court of Virginia, 2006)
Filak v. George
594 S.E.2d 610 (Supreme Court of Virginia, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
Multiscaff Limited v. Aptim Federal Services, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/multiscaff-limited-v-aptim-federal-services-llc-vaed-2024.