Hercules, Inc. v. United States

516 U.S. 417, 116 S. Ct. 981, 134 L. Ed. 2d 47, 9 Fla. L. Weekly Fed. S 422, 40 Cont. Cas. Fed. 76,894, 96 Daily Journal DAR 2395, 64 U.S.L.W. 4117, 1996 U.S. LEXIS 1557, 96 Cal. Daily Op. Serv. 1403
CourtSupreme Court of the United States
DecidedMarch 4, 1996
Docket94-818
StatusPublished
Cited by518 cases

This text of 516 U.S. 417 (Hercules, Inc. v. United States) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hercules, Inc. v. United States, 516 U.S. 417, 116 S. Ct. 981, 134 L. Ed. 2d 47, 9 Fla. L. Weekly Fed. S 422, 40 Cont. Cas. Fed. 76,894, 96 Daily Journal DAR 2395, 64 U.S.L.W. 4117, 1996 U.S. LEXIS 1557, 96 Cal. Daily Op. Serv. 1403 (1996).

Opinions

Chief Justice Rehnquist

delivered the opinion of the Court.

Petitioners in this case incurred substantial costs defending, and then settling, third-party tort claims arising out of their performance of Government contracts. In this action under the Tucker Act, they sought to recover these costs from the Government on alternative theories of contractual indemnification or warranty of specifications provided by the Government. We hold that they may not do so.

When the United States had armed forces stationed in Southeast Asia in the 1960’s, it asked several chemical manufacturers, including petitioners Hercules Incorporated (Hercules) and Wm. T. Thompson Company (Thompson), to manufacture and sell it a specific phenoxy herbicide, code-named Agent Orange. The Department of Defense wanted to spray the defoliant in high concentrations on tree and plant life in order to both eliminate the enemy’s hiding places and destroy its food supplies. From 1964 to 1968, the Government, pursuant to the Defense Production Act of 1950 (DPA), 64 Stat. 798, as amended, 50 U. S. C. App. § 2061 et seq. (1988 ed. and Supp. V), entered into a series of fixed-price production contracts with petitioners. The military prescribed the formula and detailed specifications for manufacture. The contracts also instructed the suppliers to mark the drums containing the herbicide with a 3-inch orange band with “[n]o [420]*420further identification as to conten[t].” Lodging 30 (available in clerk’s office case file). Petitioners fully complied.

In the late 1970’s, Vietnam veterans and their families began filing lawsuits against nine manufacturers of Agent Orange, including petitioners. The plaintiffs alleged that the veterans’ exposure to dioxin, a toxic byproduct found in Agent Orange and believed by many to be hazardous, had caused various health problems. The lawsuits were consolidated in the Eastern District of New York and a class action was certified. In re “Agent Orange” Product Liability Litigation, 506 F. Supp. 762, 787-792 (1980).

District Judge Pratt awarded petitioners summary judgment on the basis of the Government contractor defense in May 1983. In re “Agent Orange” Product Liability Litigation, 565 F. Supp. 1263. Before the judgment was entered, however, the case was transferred to Chief Judge Weinstein, who withdrew Judge Pratt’s opinion, ruled that the viability of the Government contractor defense could not be determined before trial, and reinstated petitioners as defendants. See In re “Agent Orange” Product Liability Litigation, 597 F. Supp. 740, 753 (1984).

In May 1984, hours before the start of trial, the parties settled. The defendants agreed to create a $180 million settlement fund with each manufacturer contributing on a market-share basis. Hercules’ share was $18,772,568; Thompson’s was $3,096,597. Petitioners also incurred costs defending these suits exceeding $9 million combined.1

[421]*421Petitioners want the United States to reimburse them for the costs of defending and settling this litigation. They attempted to recover first in District Court under tort theories of contribution and noncontractual indemnification. Having failed there,2 they each sued the Government in the United States Claims Court, invoking jurisdiction under 28 U. S. C. § 1491, and raising various claims sounding in contract.3 On the Government’s motions, the Claims Court granted summary judgment against petitioners and dismissed both complaints. Hercules, Inc. v. United States, 25 Cl. Ct. 616 (1992); Wm. T. Thompson Co. v. United States, 26 Cl. Ct. 17 (1992).

The two cases were consolidated for appeal and a divided panel of the Court of Appeals for the Federal Circuit affirmed. 24 F. 3d 188 (1994). The court held that petitioners’ claim of implied warranty of specifications failed because petitioners could not prove causation between the alleged breach and the damages. The court explained that, had petitioners pursued the class-action litigation to completion, the Government contractor defense would have barred the imposition of tort liability against them. The Government contractor defense, which many courts recognized before the Agent Orange settlement, but which this Court did not con[422]*422sider until afterward, shields contractors from tort liability for products manufactured for the Government in accordance with Government specifications, if the contractor warned the United States about any hazards known to the contractor but not to the Government. Boyle v. United Technologies Corp., 487 U. S. 500, 512 (1988). Because the Court of Appeals believed petitioners could have availed themselves of this defense, the court held that, by settling, petitioners voluntarily assumed liability for which the Government was not responsible. It also rejected Thompson’s claim of contractual indemnification. Thompson had argued that the Government, pursuant to § 707 of the DPA, 50 U. S. C. App. § 2157 (1988 ed.), impliedly promised to indemnify Thompson for any liabilities incurred in performing under the DPA. Not persuaded, the court held that §707 did not create indemnification, but only provided a defense to a suit brought against the contractor by a disgruntled customer whose work order the DPA contract displaced. We granted certiorari, 514 U. S. 1049 (1995), and now affirm the judgment below but on different grounds.4

We begin by noting the limits of federal jurisdiction. “[T]he United States, as sovereign, ‘is immune from suit save as it consents to be sued . . . and the terms of its consent to be sued in any court define that court’s jurisdiction to entertain the suit.’ ” United States v. Testan, 424 U. S. 392, 399 (1976), quoting United States v. Sherwood, 312 U. S. 584, 586 [423]*423(1941). Congress created the Claims Court5 to permit “a special and limited class of cases” to proceed against the United States, Tennessee v. Sneed, 96 U. S. 69, 75 (1878), and the court “can take cognizance only of those [claims] which by the terms of some act of Congress are committed to it,” Thurston v. United States, 232 U. S. 469, 476 (1914); United States v. Sherwood, supra, at 586-589. The Tucker Act confers upon the court jurisdiction to hear and determine, inter alia, claims against the United States founded upon any “express or implied” contract with the United States. 28 U. S. C. § 1491(a).

We have repeatedly held that this jurisdiction extends only to contracts either express or implied in fact, and not to claims on contracts implied in law. Sutton v. United States, 256 U. S. 575, 581 (1921); Merritt v. United States,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
516 U.S. 417, 116 S. Ct. 981, 134 L. Ed. 2d 47, 9 Fla. L. Weekly Fed. S 422, 40 Cont. Cas. Fed. 76,894, 96 Daily Journal DAR 2395, 64 U.S.L.W. 4117, 1996 U.S. LEXIS 1557, 96 Cal. Daily Op. Serv. 1403, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hercules-inc-v-united-states-scotus-1996.