Siegfried Construct v. Gulf Insurance Co

CourtCourt of Appeals for the Fourth Circuit
DecidedFebruary 2, 2000
Docket98-2808
StatusUnpublished

This text of Siegfried Construct v. Gulf Insurance Co (Siegfried Construct v. Gulf Insurance Co) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Siegfried Construct v. Gulf Insurance Co, (4th Cir. 2000).

Opinion

UNPUBLISHED

UNITED STATES COURT OF APPEALS

FOR THE FOURTH CIRCUIT

SIEGFRIED CONSTRUCTION, INCORPORATED, Plaintiff-Appellant,

v.

GULF INSURANCE COMPANY, Defendant-Appellee,

and

No. 98-2808 JENNIFER BUILDERS, INCORPORATED, t/a Jennifer Drywall, Incorporated, Defendant.

ASSOCIATED BUILDERS AND CONTRACTORS OF VIRGINIA, INCORPORATED; THE SURETY ASSOCIATION OF AMERICA; AMERICAN INSURANCE ASSOCIATION, Amici Curiae.

Appeal from the United States District Court for the Eastern District of Virginia, at Alexandria. Albert V. Bryan, Jr., Senior District Judge. (CA-98-555-A)

Argued: October 28, 1999

Decided: February 2, 2000

Before WIDENER, WILKINS, and TRAXLER, Circuit Judges.

_________________________________________________________________

Reversed and remanded by unpublished per curiam opinion.

_________________________________________________________________ COUNSEL

ARGUED: Mark Peyser Friedlander, Jr., FRIEDLANDER & FRIEDLANDER, P.C., McLean, Virginia, for Appellant. Erica Swecker Beardsley, WATT, TIEDER, HOFFAR & FITZGERALD, L.L.P., McLean, Virginia, for Appellee. ON BRIEF: Maurice Baskin, David C. Mancini, Charles W. Durant, VENABLE, BAET- JER & HOWARD, L.L.P., McLean, Virginia, for Amicus Curiae Associated Builders. Martha L. Perkins, AMERICAN INSURANCE ASSOCIATION, Washington, D.C.; Edward G. Gallagher, WICK- WIRE GAVIN, P.C., Vienna, Virginia, for Amicus Curiae Surety Association.

_________________________________________________________________

Unpublished opinions are not binding precedent in this circuit. See Local Rule 36(c).

_________________________________________________________________

OPINION

PER CURIAM:

Siegfried Construction, Inc. ("Siegfried" or"SC") appeals from the district court's grant of judgment as a matter of law for Gulf Insur- ance Company ("Gulf"), the surety on behalf of Siegfried's subcon- tractor, Jennifer Builders, Inc. ("Jennifer"). The district court concluded that (1) Siegfried did not declare Jennifer to be in default, and (2) Siegfried did not provide Gulf with reasonable notice that Siegfried was arranging for the correction and completion of Jenni- fer's work. Based upon these findings, the district court determined as a matter of law that Siegfried had not met the requirements of the performance bond. We reverse and remand.

I.

Siegfried was the general contractor for the construction of a Sleep Inn Hotel in Rockville, Maryland. In this capacity, Siegfried hired numerous subcontractors to perform portions of the work. Siegfried

2 engaged Jennifer to install dry wall and door frames, hang valances, and complete some trim and finishing work. The subcontract required Jennifer to obtain a performance bond, which Gulf issued shortly after Jennifer began work on the hotel.1 _________________________________________________________________

1 The performance bond, which incorporated the subcontract by refer- ence, in pertinent part provides:

NOW, THEREFORE, THE CONDITION OF THIS OBLI- GATION is such that, if Principal shall promptly and faithfully perform said subcontract, then this obligation shall be null and void; otherwise to remain in full force and effect.

Whenever Principal shall be, and be declared by Obligee to be in default under the subcontract, the Obligee having performed Obligee's obligations thereunder:

1. Surety may promptly remedy the default subject to the provisions of paragraph 3 herein, or;

2. Obligee, after reasonable notice to Surety may, or Surety upon demand of Obligee may, arrange for the perfor- mance of Principals' obligation under the subcontract sub- ject to the provisions of paragraph 3 herein;

3. The balance of the subcontract price, as defined below, shall be credited against the reasonable cost of completing performance of the subcontract. If completed by the Obli- gee, and the reasonable cost exceeds the balance of the subcontract price, the Surety shall pay to the Obligee such excess, but in no event shall the aggregate liability of the Surety exceed the amount of this bond. If the Surety arranges completion or remedies the default, that portion of the balance of the subcontract price as may be required to complete the subcontract or remedy the default and to reimburse the Surety for its outlays shall be paid to the Surety at the times and in the manner as said sums would have been payable to Principal had there been no default under the subcontract. The term "balance of subcontract price," as used in this paragraph, shall mean the total amount payable by Obligee to Principal under the subcon- tract and amendments thereto, less the amounts heretofore properly paid by Obligee under the subcontract.

J.A. 17.

3 The Sleep Inn construction, however, did not proceed smoothly. The hotel was originally scheduled to be completed by August 9, 1997, but was not finished until September 19, 1997. In many cases the delays were caused by various subcontractors, including Jennifer. During the course of the construction, Siegfried repeatedly com- plained to Jennifer about the quality of work and the laborers pro- vided. Specifically, Siegfried remonstrated that the metal door frames installed by Jennifer were crooked, dry wall was hung in the wrong sequences causing delays, piece workers hanging drywall had no des- ignated foreman, only four to eight dry wall workers were on the job when more were needed to remain on schedule, dry wall was improp- erly fitted around electrical and plumbing boxes, and in many areas dry wall was improperly placed so that it bulged.

On July 14, 1997, Siegfried sent Jennifer a "Formal Notice of Ter- mination for Failure to Perform." J.A. 183. The letter, in accordance with the subcontract,2 gave Jennifer "three (3) days formal notifica- tion of [Siegfried's] intention to terminate your subcontract agreement _________________________________________________________________

2 Article X of the subcontract provided that:

If, in the opinion of SC, Subcontractor shall at any time (1) refuse or fail to provide sufficient properly skilled workmen or materials of the proper quality, (2) fail in any respect to prose- cute the work according to the current schedule, (3) cause, by any action or omission, the stoppage or delay of or interference with the work of SC or of any other builder or subcontractor, . . . or (8) by any other action, indicate an unwillingness or inability to perform, or continue performing, hereunder then, after serving three days' written notice, unless the condition(s) specified in such notice shall have been eliminated within such three days, SC may, at its option (i) without voiding the other provisions of this Subcontract and without notice to Subcontractor's sureties, if any, take such steps as are necessary in SC's reasonable dis- cretion, to overcome the condition(s), in which case the Subcon- tractor shall be liable to SC for the full cost thereof, (ii) terminate the Subcontract for default, or (iii) seek specific performance of Subcontractor's obligations hereunder, it being agreed by Sub- contractor that specific performance may be necessary to avoid irreparable harm to SC and/or Owner. . . .

J.A. 170.

4 for default, unless acceptable corrections are effected by July 17, 1997." J.A. 183. The letter then set forth a number of grievances regarding Jennifer's workers and demanded that Jennifer take correc- tive action. On July 15, Siegfried sent a corrected termination letter to Jennifer further detailing problems with Jennifer's work and demanding prompt correction. Jennifer responded by making some changes, but Siegfried soon found that the original problems reoccur- red.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Mullane v. Central Hanover Bank & Trust Co.
339 U.S. 306 (Supreme Court, 1950)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Paul Carter v. William L. Ball, III
33 F.3d 450 (Fourth Circuit, 1994)
Gordonsville Energy, L.P. v. Virginia Electric & Power Co.
512 S.E.2d 811 (Supreme Court of Virginia, 1999)
Horton v. Horton
487 S.E.2d 200 (Supreme Court of Virginia, 1997)
Clevert v. Jeff W. Soden, Inc.
400 S.E.2d 181 (Supreme Court of Virginia, 1991)
Century-21, Gail Boswell & Associates, Inc. v. Elder
391 S.E.2d 296 (Supreme Court of Virginia, 1990)
Southwood Builders, Inc. v. Peerless Insurance
366 S.E.2d 104 (Supreme Court of Virginia, 1988)
Chaves v. Johnson
335 S.E.2d 97 (Supreme Court of Virginia, 1985)
Phoenix Insurance Company v. Lester Brothers, Inc.
127 S.E.2d 432 (Supreme Court of Virginia, 1962)
D.C. McClain, Inc. v. Arlington County
452 S.E.2d 659 (Supreme Court of Virginia, 1995)
RW Power Partners, L.P. v. Virginia Electric & Power Co.
899 F. Supp. 1490 (E.D. Virginia, 1995)
Fidelity & Deposit Co. of Maryland v. Bailey
133 S.E. 797 (Supreme Court of Virginia, 1926)
C. S. Luck & Sons, Inc. v. Boatwright
162 S.E. 53 (Supreme Court of Virginia, 1932)
New Amsterdam Casualty Co. v. Moretrench Corp.
35 S.E.2d 74 (Supreme Court of Virginia, 1945)
American Surety Co. of New York v. Zoby
130 S.E.2d 587 (Supreme Court of Virginia, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
Siegfried Construct v. Gulf Insurance Co, Counsel Stack Legal Research, https://law.counselstack.com/opinion/siegfried-construct-v-gulf-insurance-co-ca4-2000.