Balfour Beatty Construction, Inc. v. Colonial Ornamental Iron Works, Inc.

986 F. Supp. 82, 1997 U.S. Dist. LEXIS 20941, 1997 WL 757549
CourtDistrict Court, D. Connecticut
DecidedOctober 1, 1997
DocketCivil 3:96CV00345 (AVC)
StatusPublished
Cited by21 cases

This text of 986 F. Supp. 82 (Balfour Beatty Construction, Inc. v. Colonial Ornamental Iron Works, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Balfour Beatty Construction, Inc. v. Colonial Ornamental Iron Works, Inc., 986 F. Supp. 82, 1997 U.S. Dist. LEXIS 20941, 1997 WL 757549 (D. Conn. 1997).

Opinion

RULING ON THE DEFENDANT, NATIONAL SURETY CORPORATION’S MOTION FOR SUMMARY JUDGMENT

COVELLO, District Judge.

This is an action for damages in which the plaintiff, Balfour Beatty, Inc., (Beatty), alleges that the defendants, Colonial Iron Works (Colonial) and Engineered Products, Inc. (EPI) are liable for breach of contract, negligent misrepresentation, fraudulent misrepresentation, and violations of the Connecticut Unfair Trade Practices Act (CUTPA), Conn. Gen.Stat. § 42-110b(a). The complaint also alleges that the defendant, National Surety Corporation (“NSC”), “is obligated under the performance bond to reimburse Balfour Beatty for the damages it has sustained.” The defendant, NSC, now moves for summary judgment, claiming there is no genuine issue as to any material fact, and that it is entitled to judgment as a matter of law.

The issue presented is whether the plaintiff provided sufficient notification of the principal’s default to the surety defendant in order to incur the defendant’s liability under the terms of the performance bond. For the following reasons, the court concludes that the plaintiff did not sufficiently notify the surety defendant of the principal’s default. Accordingly, the surety’s motion for summary judgment is granted.

FACTS

Examination of the complaint, exhibits, and the Rule 9 statements of material fact accompanying the motion for summary judgment, and the responses thereto, discloses the following undisputed material facts. In January 1993, the plaintiff, Balfour Beatty, as a general contractor, entered into a construction contract with Metro-North Commuter Railroad for the construction of the Peck Drawbridge and Bridgeport Viaduct in Bridgeport, Connecticut. In January 1994, the plaintiff entered into contract with Colonial Ornamental Iron Works, Inc. (“Colonial”), for the structural steel for the railway bridge.

The contract stated that, “[i]t is the intent of this Purchase Order to ensure that the Colonial Iron Work provides Balfour Beatty with an adequate, continuous and uninterrupted supply of materials according to the schedule furnished in advance by Balfour Beatty, with a delivery completion date of August 15, 1995.” The purchase order further stated that “this schedule is subject to revision as dictated by conditions on this project. Balfour Beatty will provide updated schedules as needed.” The purchase order also contained provisions with regard to modifications 1 and delivery. 2

*84 The defendant argues that “the plaintiff demanded that [Colonial] provide a Performance Bond in consideration for agreeing to [a] revised payment and performance schedule.” On August 10, 1995, the defendant, National Surety Corporation, posted the performance bond for Colonial, the principal, who had, at that time, only completed 65% of the contract. 3

The language of the performance bond specifically required that,

“whenever Principal [Colonial] shall be, and declared by Obligee to be in default under the subcontract, the Obligee having performed Obligee’s obligations thereunder:
1) Surety [NSC] may promptly remedy the default, subject to the provisions of paragraph 3 herein, or;
2) Obligee after reasonable notice to Surety may, or Surety upon demand of obligee may arrange for the performance of Principal’s obligation under the subcontract subject to the provisions of paragraph 3 herein;
3) The balance of the subcontract price, as defined below, shall be credited against the reasonable cost of completing performance of the subcontract____(emphasis added).

The plaintiff claims that two letters that it sent on August 17, 1995 4 and December 19, 1995, 5 gave NSC notice that it considered Colonial to be in default.

On February 29, 1996, the plaintiff filed the within complaint seeking, as to defendant NSC, payment under the bond NSC issued in behalf of Colonial.

STANDARD

Summary judgment is appropriately granted when the evidentiary record shows that there are no genuine issues of material fact and that the moving party is entitled to judgment as a matter of law. Fed.R.Civ.P. 56. In determining whether the record presents genuine issues for trial, the court must view all inferences and ambiguities in a light most favorable to the non-moving party. See Bryant v. Maffucci, 923 F.2d 979, 982 (2d Cir.1991), cert. denied, 502 U.S. 849, 112 S.Ct. 152, 116 L.Ed.2d 117 (1991). A plaintiff raises a genuine issue of material fact if “the jury could reasonably find for the plaintiff.” Anderson v. Liberty Lobby Inc., 477 U.S. 242, 252, 106 S.Ct. 2505, 2512, 91 L.Ed.2d 202 (1986). Rule 56 “provides that the mere existence of some alleged factual dispute between the parties will not defeat an other *85 ■wise properly supported motion for summary judgment; the requirement is that there be no genuine issue of material fact.” Liberty Lobby, 477 U.S. at 247-48, 106 S.Ct. at 2510 (emphasis in original). “One of the principal purposes of the summary judgment rule is to isolate and dispose of factually unsupported claims ... [and] it should be interpreted in a way that allows it to accomplish this purpose.” Celotex v. Catrett, 477 U.S. 317, 323-24, 106 S.Ct. 2548, 2553, 91 L.Ed.2d 265 (1986).

DISCUSSION

The defendant states that the bond, by its express terms, provided for notice of default to NSC and argues that “the plaintiff never declared Colonial in default, never provided notice of such declaration of default to NSC, never terminated the contract with Colonial, never requested that the Surety step in and complete performance, and never gave notice to NSC that the plaintiff intended to arrange for the performance of Colonial’s obligations.”

The plaintiff responds that: 1) “NSC had actual notice of Colonial’s default, because the delivery provision set forth in the purchase Order was already in breach at the time NSC issued the bond;” 2) the plaintiff “did provide notice of default to NSC in the form of letters, one dated August 17, 1995 and the other December 19, 1995;” and 3) “NSC was not entitled to notice of default, because the bond does not expressly provide for such notice .”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Flatiron-Lane v. Case Atlantic Co.
121 F. Supp. 3d 515 (M.D. North Carolina, 2015)
Stonington Water Street Assoc., LLC v. Hodess Building Co.
792 F. Supp. 2d 253 (D. Connecticut, 2011)
County of Brunswick v. Lexon Insurance
710 F. Supp. 2d 520 (E.D. North Carolina, 2010)
Raito, Inc. v. Cardi Corp.
Superior Court of Rhode Island, 2010
Raito, Inc. v. Cardi Corporation
Superior Court of Rhode Island, 2010
Hunt Construction Group, Inc. v. National Wrecking Corporation
542 F. Supp. 2d 87 (District of Columbia, 2008)
Colorado Structures, Inc. v. Insurance Co. of the West
161 Wash. 2d 577 (Washington Supreme Court, 2007)
Colorado Structures, Inc. v. Insurance Co. of the West
125 Wash. App. 907 (Court of Appeals of Washington, 2005)
Colo. Structures, Inc. v. INSURANCE CO. OF WEST
106 P.3d 815 (Court of Appeals of Washington, 2005)
School Board of Escambia County v. Tig Premier Insurance
110 F. Supp. 2d 1351 (N.D. Florida, 2000)
St. Paul Fire & Marine Insurance v. City of Green River
93 F. Supp. 2d 1170 (D. Wyoming, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
986 F. Supp. 82, 1997 U.S. Dist. LEXIS 20941, 1997 WL 757549, Counsel Stack Legal Research, https://law.counselstack.com/opinion/balfour-beatty-construction-inc-v-colonial-ornamental-iron-works-inc-ctd-1997.