United States Fidelity & Guaranty Co. v. Braspetro Oil Services Co.

219 F. Supp. 2d 403, 157 Oil & Gas Rep. 474, 2002 U.S. Dist. LEXIS 15518, 2002 WL 1900870
CourtDistrict Court, S.D. New York
DecidedJuly 25, 2002
Docket97 CIV.6124 JGK, 98 CIV.3099 JGK
StatusPublished
Cited by5 cases

This text of 219 F. Supp. 2d 403 (United States Fidelity & Guaranty Co. v. Braspetro Oil Services Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Fidelity & Guaranty Co. v. Braspetro Oil Services Co., 219 F. Supp. 2d 403, 157 Oil & Gas Rep. 474, 2002 U.S. Dist. LEXIS 15518, 2002 WL 1900870 (S.D.N.Y. 2002).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

KOELTL, District Judge.

TABLE OF CONTENTS

Introduction.409

FINDINGS OF FACT.410

The Parties.410

Brasoil Retained Petrobras to Manage the P-19 and P-31 Contracts.414

The P-19 International Bid Process.415

*408 The P-19 Consortium Underbid the P-19 Project...416

The Sureties’ Issuance of the P-19 Bond.418

Relevant Provisions of the P-19 Contract.419

Delays in the Commencement of the P-19 Project.422

The P-31 International Bid Process.424

The P-31 Consortium Underbid the P-31 Project.425

The Issuance of the P-31 Bond.425

Relevant Terms of the P-31 Contract.426

Initial Efforts to Address the Consortia’s Cash Flow Problems.428

Changes to the EAP and the Establishment of Blocked Accounts in the First Amendments.431

Comfort Letters and Direct Payments for Equipment.434

IVI and the Petrobras Defendants Kept the Sureties Fully Informed of the Developing Crisis.436

Critical Problems at the end of 1996 and the Beginning of 1997 .438

Discussions between Petrobras, the Sureties, and the Consortia Regarding the Financial Problems of the Consortia and the Sureties’ Obligations under the Bonds.442

Additional Funds to Continue Work on the Projects.447

Declarations of Default.449

Brasoil Did Not Fundamentally Change the P-19 Project, Interfere with Construction, Make Excessive Changes, Fail to Recognize Change Orders, Fail to Grant Extensions of Time or Otherwise Breach the P-19 Contract.456

Brasoil Did Not Fundamentally Change the P-31 Project, Interfere with Construction, Make Excessive Changes, Fail to Recognize Change Orders, Fail to Grant Extensions of Time or Otherwise Breach the P-31 Contract.462

Accounting Issues.464

Marubeni.467

Damages.470

CONCLUSIONS OF LAW.472

Jurisdiction.472

Choice of Law.474

The Sureties’ Liability under the Performance Bonds .476

Damages 484

*409 The Indemnification Action. .486

The Tortious Interference Claim. .488

CONCLUSION. .490

Introduction

These consolidated cases concern the obligations and liabilities of United States Fidelity & Guaranty Co. (“USF & G”) and American Home Assurance Co. (“AHAC”) (collectively the “Sureties”), pursuant to performance guaranty bonds that were issued by those companies in connection with two massive naval construction projects in Brazil known as the P-19 and P-31 Projects. The Sureties issued the P-19 Performance Bond in the amount of $110,512,660 on behalf of the construction consortium which was to perform the P-19 conversion, as principal, in favor of Braspetro Oil Services Co. (“Brasoil”), as the obligee. The Bank of Tokyo-Mitsubishi Ltd. (“Bank of Tokyo”) and the Long-Term Credit Bank of Japan, Ltd. (“LTCB”) (collectively the “Japanese Banks”), which had provided funding for the project, were additional obligees on the P-19 Performance Bond under a Dual Ob-ligee Rider to the Bond. The Sureties issued the P-31 Performance Bond in the amount of $163,000,000 on behalf of a similar construction consortium that was to perform the conversion of the P-31 Project, as principal, in favor of Brasoil as the obligee.

The P-19 Project involved the design and conversion of a platform formerly used for oil and natural gas exploration, known as the Treasure Stawinner 1 , into a semi-submersible oil and natural gas production platform. The conversion of the P-19 vessel, which is registered under Panamanian law, was the largest of its kind ever undertaken. The P-31 Project involved the design and conversion of an oil tanker (Very Large Crude Carrier, or “VLCC”), known as the Vidal de Negreiros, into a Floating Production, Storage, and Offloading vessel (“FPSO”).

Both the P-19 and the P-31 Projects were plagued by huge cost overruns. Bra-soil and its indirect parent, Petróleo Brasi-leiro S.A.Petrobras (“Petrobras”), claim that these overruns were caused by the construction consortia’s substantial underbids on both projects and by market conditions for which Brasoil and Petrobras were not responsible. Therefore, Brasoil and Petrobras claim, they justifiably declared the construction contracts to be in default and called on the Sureties to meet their obligations on the Bonds. When the Sureties failed to do so, Brasoil had the projects completed and now looks to the Sureties for the cost of the completion of the projects and costs of delay for the projects. In addition to many other arguments and theories, the Sureties claim that Petrobras, which was managing the projects for Bra-soil, substantially changed the nature of the projects by making numerous changes in the requirements of the contracts, without notice to the Sureties, and that it was these changes, for which the construction consortia had not been compensated, that vastly increased the costs of the projects. The Sureties claim that the construction consortia were not actually in default under the construction contracts and that, because of the substantial changes which changed the nature of the contracts, the Sureties were discharged from any requirement to pay any amounts under the Bonds.

In the Declaratory Judgment Action, No. 97 Civ. 6124, the Sureties seek a declaratory judgment against Brasoil and the *410 Japanese Banks that the Sureties have no obligations or liabilities under the Bonds. Brasoil, joined by the Japanese Banks with respect to the P-19 Bond, denies the Sureties’ allegations and counterclaim to require the Sureties to pay the amounts owed under the Bonds. In the Indemnity Action, No. 98 Civ. 3099, the Sureties sue Petrobras, the individual members of the construction consortia, and others, claiming, under numerous alternative theories, that the Sureties are entitled to indemnification for any costs they are required to pay under the Bonds. In the Indemnification action, the Sureties claim that by its domination and control of the construction consortia, as well as pursuant to theories of partnership, Petrobras is liable for the indemnification obligations of the construction consortia to the Sureties. The Sureties also claim that Petrobras tortiously interfered with the payment obligations of the construction consortium on the P-19 Project and Brasoil under.a payment bond issued to secure financing provided to the P-19 Project by Marubeni America Corp. (“MAC”). The Sureties have also sued the members of the construction consortia and others, but those claims have been severed pending resolution of the current claims among the Sureties, Brasoil, Petrobras, and the Japanese Banks.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stonington Water Street Assoc., LLC v. Hodess Building Co.
792 F. Supp. 2d 253 (D. Connecticut, 2011)
Mid-State Surety Corp. v. Thrasher Engineering, Inc.
575 F. Supp. 2d 731 (S.D. West Virginia, 2008)
Enterprise Capital, Inc. v. San-Gra Corp.
284 F. Supp. 2d 166 (D. Massachusetts, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
219 F. Supp. 2d 403, 157 Oil & Gas Rep. 474, 2002 U.S. Dist. LEXIS 15518, 2002 WL 1900870, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-fidelity-guaranty-co-v-braspetro-oil-services-co-nysd-2002.