United States Fidelity & Guaranty Co. v. Braspetro Oil Services Co.

219 F. Supp. 2d 403, 157 Oil & Gas Rep. 474, 2002 U.S. Dist. LEXIS 15518, 2002 WL 1900870
District Court, S.D. New York·Decided July 25, 2002·No. 97 CIV.6124 JGK, 98 CIV.3099 JGK·Published·Cited by 5 cases

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

KOELTL, District Judge.

TABLE OF CONTENTS

Introduction.409

FINDINGS OF FACT.410

The Parties.410

Brasoil Retained Petrobras to Manage the P-19 and P-31 Contracts.414

The P-19 International Bid Process.415

*408 The P-19 Consortium Underbid the P-19 Project...416

The Sureties’ Issuance of the P-19 Bond.418

Relevant Provisions of the P-19 Contract.419

Delays in the Commencement of the P-19 Project.422

The P-31 International Bid Process.424

The P-31 Consortium Underbid the P-31 Project.425

The Issuance of the P-31 Bond.425

Relevant Terms of the P-31 Contract.426

Initial Efforts to Address the Consortia’s Cash Flow Problems.428

Changes to the EAP and the Establishment of Blocked Accounts in the First Amendments.431

Comfort Letters and Direct Payments for Equipment.434

IVI and the Petrobras Defendants Kept the Sureties Fully Informed of the Developing Crisis.436

Critical Problems at the end of 1996 and the Beginning of 1997 .438

Discussions between Petrobras, the Sureties, and the Consortia Regarding the Financial Problems of the Consortia and the Sureties’ Obligations under the Bonds.442

Additional Funds to Continue Work on the Projects.447

Declarations of Default.449

Brasoil Did Not Fundamentally Change the P-19 Project, Interfere with Construction, Make Excessive Changes, Fail to Recognize Change Orders, Fail to Grant Extensions of Time or Otherwise Breach the P-19 Contract.456

Brasoil Did Not Fundamentally Change the P-31 Project, Interfere with Construction, Make Excessive Changes, Fail to Recognize Change Orders, Fail to Grant Extensions of Time or Otherwise Breach the P-31 Contract.462

Accounting Issues.464

Marubeni.467

Damages.470

CONCLUSIONS OF LAW.472

Jurisdiction.472

Choice of Law.474

The Sureties’ Liability under the Performance Bonds .476

Damages 484

*409 The Indemnification Action. .486

The Tortious Interference Claim. .488

CONCLUSION. .490

Introduction

These consolidated cases concern the obligations and liabilities of United States Fidelity & Guaranty Co. (“USF & G”) and American Home Assurance Co. (“AHAC”) (collectively the “Sureties”), pursuant to performance guaranty bonds that were issued by those companies in connection with two massive naval construction projects in Brazil known as the P-19 and P-31 Projects. The Sureties issued the P-19 Performance Bond in the amount of $110,512,660 on behalf of the construction consortium which was to perform the P-19 conversion, as principal, in favor of Braspetro Oil Services Co. (“Brasoil”), as the obligee. The Bank of Tokyo-Mitsubishi Ltd. (“Bank of Tokyo”) and the Long-Term Credit Bank of Japan, Ltd. (“LTCB”) (collectively the “Japanese Banks”), which had provided funding for the project, were additional obligees on the P-19 Performance Bond under a Dual Ob-ligee Rider to the Bond. The Sureties issued the P-31 Performance Bond in the amount of $163,000,000 on behalf of a similar construction consortium that was to perform the conversion of the P-31 Project, as principal, in favor of Brasoil as the obligee.

The P-19 Project involved the design and conversion of a platform formerly used for oil and natural gas exploration, known as the Treasure Stawinner 1 , into a semi-submersible oil and natural gas production platform. The conversion of the P-19 vessel, which is registered under Panamanian law, was the largest of its kind ever undertaken. The P-31 Project involved the design and conversion of an oil tanker (Very Large Crude Carrier, or “VLCC”), known as the Vidal de Negreiros, into a Floating Production, Storage, and Offloading vessel (“FPSO”).

Both the P-19 and the P-31 Projects were plagued by huge cost overruns. Bra-soil and its indirect parent, Petróleo Brasi-leiro S.A.Petrobras (“Petrobras”), claim that these overruns were caused by the construction consortia’s substantial underbids on both projects and by market conditions for which Brasoil and Petrobras were not responsible. Therefore, Brasoil and Petrobras claim, they justifiably declared the construction contracts to be in default and called on the Sureties to meet their obligations on the Bonds. When the Sureties failed to do so, Brasoil had the projects completed and now looks to the Sureties for the cost of the completion of the projects and costs of delay for the projects. In addition to many other arguments and theories, the Sureties claim that Petrobras, which was managing the projects for Bra-soil, substantially changed the nature of the projects by making numerous changes in the requirements of the contracts, without notice to the Sureties, and that it was these changes, for which the construction consortia had not been compensated, that vastly increased the costs of the projects. The Sureties claim that the construction consortia were not actually in default under the construction contracts and that, because of the substantial changes which changed the nature of the contracts, the Sureties were discharged from any requirement to pay any amounts under the Bonds.

Free access — add to your briefcase to read the full text and ask questions with AI

United States Fidelity & Guaranty Co. v. Braspetro Oil Services Co., 219 F. Supp. 2d 403, 157 Oil & Gas Rep. 474, 2002 U.S. Dist. LEXIS 15518, 2002 WL 1900870 (S.D.N.Y. 2002).

219 F. Supp. 2d 403 (United States Fidelity & Guaranty Co. v. Braspetro Oil Services Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Stonington Water Street Assoc., LLC v. Hodess Building Co.
792 F. Supp. 2d 253 (D. Connecticut, 2011)
Mid-State Surety Corp. v. Thrasher Engineering, Inc.
575 F. Supp. 2d 731 (S.D. West Virginia, 2008)
Enterprise Capital, Inc. v. San-Gra Corp.
284 F. Supp. 2d 166 (D. Massachusetts, 2003)