Argonaut Insurance Company v. Town of Cloverdale, Indiana

699 F.2d 417, 1983 U.S. App. LEXIS 30662
CourtCourt of Appeals for the Seventh Circuit
DecidedFebruary 9, 1983
Docket82-1268
StatusPublished
Cited by30 cases

This text of 699 F.2d 417 (Argonaut Insurance Company v. Town of Cloverdale, Indiana) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Argonaut Insurance Company v. Town of Cloverdale, Indiana, 699 F.2d 417, 1983 U.S. App. LEXIS 30662 (7th Cir. 1983).

Opinion

POSNER, Circuit Judge.

The appeal in this 'diversity case requires us to decide a question of suretyship under the common law of Indiana. The essential facts are undisputed. The Town of Clover-dale, Indiana hired a contractor, HESCO, to build sewers. HESCO gave the town a performance bond in the amount of $238,-000. The surety on the bond was Argonaut Insurance Company. Under its contract with HESCO, the town “agree[d] to pay the Contractor the sums herein specified in monthly installments as the work progresses upon estimates signed by the Engineer [an engineering firm the town had hired to supervise the project],” and the engineer was authorized, “at his discretion, [to] include in the aforesaid progress payments an estimate of the equipment and materials ... which has [sic] been delivered upon the site of the work, and for which receipted invoices have been delivered to the Engineers.” About halfway through the project HESCO defaulted and Argonaut stepped in and hired another contractor to complete the work. Argonaut later discovered that the engineering firm had included in its progress-payment estimates, and the town had paid HESCO, $17,000 for materials delivered to the construction site for which either receipted invoices had not been submitted or “retainage” had not been deducted (the contract provided that 10 percent of each progress payment was to be withheld “as part security for the faithful performance” of the contract).

Argonaut demanded that the town pay it $17,000 in addition to the $16,000 due as the last installment payment for completion of the project. (The town had to pay Argonaut to complete the project because the cost of the project exceeded the amount of the performance bond.) The town was willing to pay Argonaut the $16,000 final installment on condition that Argonaut abandon its claim to the additional $17,000, but Argonaut refused, and sued the town for $33,000. Trial was by jury. At the close of *419 the evidence Argonaut moved for a directed verdict. The judge took the motion under advisement and sent the case to the jury, which hung. Twenty-seven months later the judge granted Argonaut’s motion and entered judgment for $50,000 — $33,000 plus interest from the date of Argonaut’s demand for the $17,000 in unauthorized progress payments.

If a contract that a surety has guaranteed is altered without the surety’s consent, he is discharged, on the theory that he insured only the original contract. Indiana Telco Fed. Credit Union v. Young, 156 Ind. App. 483, 487, 297 N.E.2d 434, 436 (1973). As a corollary to this rule, he is discharged if the obligee under the suretyship contract (the Town of Cloverdale, in this case) makes advance payments to the principal (HES-CO) beyond those provided for in the contract (we postpone consideration of whether the discharge is total or partial in this situation). Detroit Fidel. & Sur. Co. v. Bushong, 96 Ind.App. 352, 175 N.E. 683 (1931); United States for Use & Benefit of H & S Industries, Inc. v. F.D. Rich Co., 525 F.2d 760, 771 (7th Cir.1975); Stearns, The Law of Suretyship 123 (5th ed., Elder, 1951). Whether this is a true corollary may be doubted, since the fact that a prepayment is unauthorized does not mean that it breaks or alters the contract. But the corollary has an independent rationale, and therefore need not be rested on deduction. The rationale is that unauthorized advances reduce the principal’s incentive to complete the contract, thereby increasing the risk to the surety, and increase the cost of the surety’s substitute performance (in this case the argument would be that if the Town of Cloverdale had retained the $17,000 it erroneously paid HESCO its loss on its dealings with HESCO would have been that much less). Both parts of this rationale, however, are questionable. Arant, Rationale of the Rule That an Obligee’s Premature Payment Discharges His Surety, 80 U.Pa.L.Rev. 842, 853 (1932). The principal’s default may be and usually is unrelated to any slackening off due to unauthorized advances and may indeed be retarded rather than accelerated by them. And whether the advances increase the surety’s risk depends on what the principal did with them; if he used them on the project the amount at risk to the surety may be unaffected.

Though the rule on unauthorized advances may well be just a vestige of an era when sureties were usually not compensated and therefore were treated with a judicial tenderness that they do not deserve today, see Stearns, supra, at 2, we have no evidence that Indiana is about to jettison the rule. But we are entitled, in light of its shaky foundations, to pay sympathetic attention to the exception that the town presses on us: a surety is not discharged by reason of an unauthorized payment made in good-faith reliance on an engineer’s or architect’s certificate of progress. See cases cited in Annot., Contractor’s Bond — Pay ment Releasing Surety, 127 A.L.R. 10, 77 (1940); Simpson, Handbook on the Law of Suretyship 394-95 n. 10 (1950). Although we have found no Indiana cases dealing with this exception there is no reason to think the Indiana courts would reject it. Argonaut points out that it is not seeking discharge in full but only the crediting of the unauthorized payments against its obligations under the suretyship contract. However, the modern rule — for which there is ancient authority in Indiana, see Weik v. Pugh, 92 Ind. 382, 386 (1884); Foster v. Gaston, 123 Ind. 96, 106-07, 23 N.E. 1092, 1096 (1890) — is that a discharge because of unauthorized payments to the principal operates only to the extent of the unauthorized payments. See, e.g., Central Towers Apts., Inc. v. Martin, 61 Tenn.App. 244, 453 S.W.2d 789, 796-97 (1969); National Union Indemnity Co. v. G.E. Bass & Co., 369 F.2d 75, 77 (5th Cir.1966). There is an exception for extreme cases. Bushong, which did not cite Weik or Foster and appears to have granted a full discharge (though the opinion in F.D. Rich, supra, 525 F.2d at 771, interprets it as a partial-discharge case), may have been an extreme case; this is not.

So the Town of Cloverdale seems to be within the exception. In addition, Indiana might join those states that not only do not *420 allow total discharge for unauthorized prepayments but do not allow even partial discharge unless the surety proves that the prepayments injured him, and that is hard to prove where — as was the case here, we shall see — the prepayments are not just pocketed by the contractor but go to buy materials that are used in the performance of the contract. Simpson, supra, at 399. However, there is such a paucity of Indiana authority on these questions — as a matter of fact we cannot find any recent case from any jurisdiction dealing with the effect of reliance on an engineer’s or architect’s certificate — that we shall also analyze this case as one of original contractual interpretation, unaided by the special rules of interpretation applied in suretyship cases.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

RLI Insurance v. Indian River School District
556 F. Supp. 2d 356 (D. Delaware, 2008)
Aetna Casualty And Surety Co. v. Aniero Concrete Co.
404 F.3d 566 (Second Circuit, 2005)
Aetna Casualty & Surety Co. v. Aniero Concrete Co.
404 F.3d 566 (Second Circuit, 2005)
National Surety Corporation v. United States
118 F.3d 1542 (Federal Circuit, 1997)
Brighton School District 27J v. Transamerica Premier Insurance Co.
923 P.2d 328 (Colorado Court of Appeals, 1996)
Mergentime Corp. v. Washington Metropolitan Area Transit Authority
775 F. Supp. 14 (District of Columbia, 1991)
Gravis v. Graves
574 N.E.2d 952 (Indiana Court of Appeals, 1991)
Banco Portugues Do Atlantico v. Asland, S.A.
745 F. Supp. 962 (S.D. New York, 1990)
Fireman's Fund Insurance Company v. The United States
909 F.2d 495 (Federal Circuit, 1990)
Rainbow Navigation, Inc. v. United States
742 F. Supp. 171 (D. New Jersey, 1990)
Fireman's Fund Insurance v. United States
34 Cont. Cas. Fed. 75,538 (Court of Claims, 1988)
Newman-Green, Inc. v. Alejandro Alfonzo-Larrain R.
832 F.2d 417 (Seventh Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
699 F.2d 417, 1983 U.S. App. LEXIS 30662, Counsel Stack Legal Research, https://law.counselstack.com/opinion/argonaut-insurance-company-v-town-of-cloverdale-indiana-ca7-1983.