National Surety Corporation v. United States

118 F.3d 1542, 41 Cont. Cas. Fed. 77,129, 1997 U.S. App. LEXIS 16455, 1997 WL 366019
CourtCourt of Appeals for the Federal Circuit
DecidedJuly 3, 1997
Docket94-5159
StatusPublished
Cited by49 cases

This text of 118 F.3d 1542 (National Surety Corporation v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Surety Corporation v. United States, 118 F.3d 1542, 41 Cont. Cas. Fed. 77,129, 1997 U.S. App. LEXIS 16455, 1997 WL 366019 (Fed. Cir. 1997).

Opinions

PAULINE NEWMAN, Circuit Judge.

The government appeals the decision of the United States Court of Federal Claims1 holding the government liable to the surety for the improper release of retainage for a construction contract upon which National Surety Corporation served as guarantor. The decision of liability is affirmed, albeit on a different ground than that selected by the Court of Federal Claims. We remand for redetermination of the amount of damages.

BACKGROUND

National Surety furnished performance and payment bonds in connection with a contract between Dugdale Construction Company and the Department of Veterans Affairs, for construction of a water distribution system at Fort Harrison, Montana. The construction contract provided that the government would retain ten percent of all progress payments until Dugdale submitted, and the contracting officer approved, a “complete project arrow diagram,” which is a detailed schedule of the critical path for performing the contract. The retainage provision was as follows:

Clause G-7(A). Payment to Contractor Clause 7 of the General Provisions (Contractor Contract) is supplemented to include the following:
Retainage: This contract shall have 10 percent retainage withheld on each progress voucher until the complete project arrow diagram has been approved. Once the schedule has been approved and the Contracting Officer has determined that the Contractor’s progress is satisfactory, the Contracting Officer may elect not to withhold any additional retainage. Previous retainage will not be reduced and future payments will be made in full. If during subsequent project updates the Contracting Officer determines that the Contractor’s progress is unsatisfactory, he may withhold 10 percent retainage on the current payment request and subsequent payments to protect the interests of the Government and until he again determines that the Contractor’s progress is satisfactory.

Dugdale did not provide the requisite project arrow diagram. Nonetheless, the government did not withhold the ten percent retain-[1544]*1544age from the progress payments, as the contract required.

Dugdale abandoned the project before its completion, and the government then terminated the contract for default. National Surety completed the construction in accordance "with its performance bond, and was paid the difference between the contract price and the payments that had been made to Dugdale, ie., $126,333, less liquidated damages for late completion. National Surety then filed a claim for the funds that were required to have been retained by the government from the progress payments to Dugdale. The contracting officer did not act on the claim within the statutory period, and National Surety brought suit in the Court of Federal Claims.

On cross motions for summary judgment, the Court of Federal Claims held that National Surety was a third party beneficiary of the contract between Dugdale and the government and that the government breached this obligation when it improperly paid the retainage to Dugdale, thereby incurring liability to National Surety. The court awarded as damages the amount that should have been retained ($97,742) plus statutory interest. This appeal followed.

DISCUSSION

In the Court of Federal Claims the parties offered alternative theories of their legal relationships and ensuing liabilities. Although we affirm the court’s conclusion as to liability, we do so on application of suretyship principles.

A

The view that the surety is a third party beneficiary of the contract whose performance it assures is not the usual premise of surety claims against an obligee, although, to be sure, the surety’s obligations are affected by that performance. See Arthur Adelbert Stearns, The Law of Suretyship § 1.1 (1951) (“Suretyship may be defined as a contractual relation whereby one person engages to be answerable for the debt or default of another”); Balboa Ins. Co. v. United States, 775 F.2d 1158, 1160 (Fed.Cir.1985) (“suretyship is the result of a three-party agreement”).

Suretyship law derives from a different legal premise than whether the bonded contract, or any provision thereof, was made for the surety’s direct benefit. The surety bond embodies the principle that any material change in the bonded contract, that increases the surety’s risk or obligation without the surety’s consent, affects the surety relationship. The principles are set forth in, e.g., Gritz Harvestore, Inc. v. A.O. Smith Harvestore Prods., Inc., 769 F.2d 1225, 1230 n. 7 (7th Cir.1985):

Where, without the surety’s consent, the principal and the creditor modify their contract otherwise than by extension of time for payment
(b) the compensated surety is
(i) discharged if the modification materially increases his risk, and
(ii) not discharged if the risk is not materially increased, but his obligation is reduced to the extent of loss due to the modification.

(citing Restatement, Security § 128 at 340-41 (1941)). These principles have been elaborated upon in the Third Restatement, including a synthesis of the circumstances under which the surety is entitled to relief against the obligee based on impairment of suretyship status. See Restatement (Third) of Suretyship & Guaranty § 37 (1996). Extensive precedent illustrates the discharge or pro tanto reduction of the surety’s obligation, varying in implementation based on the particular facts. The general rule with respect to retainage in construction contracts is the subject of the following example in the Third Restatement:

1. S has issued a performance bond with respect to P’s contract to construct a house for 0 for $100,000. Pursuant to the contract between O and P, O is to pay P monthly for the portion of the work completed that month minus a 15 percent “retainage.” After completing 60 percent of the project and receiving $51,000 ($60,000 minus the $9,000 retainage) from O, P defaults. S completes the project at a cost to S of $40,000. After S completes the [1545]*1545project, 0 pays the $9,000 retainage to P, who, despite this payment, is insolvent. Had 0 paid the retainage to P before S completed the project, S would have been discharged to the extent of $9,000 by application of § 38 (impairment of collateral). S has a claim against O for $9,000 because the payment to P would have discharged S from the secondary obligation to that extent.

Id. § 37, illus. 1. See, e.g., Home Indem. Co. v. United States, 180 Ct.Cl. 173, 376 F.2d 890, 895 (1967) (United States liable to surety despite the fact that the government had disbursed the retainages); Hochevar v. Maryland Cos. Co., 114 F.2d 948 (6th Cir.1940) (improper release of 15% retainage in construction contract released the surety pro tanto); Maryland Cos. Co. v. Board of Water Commissioners, 66 F.2d 730 (2d Cir.1933) (same).

The surety’s rights and obligations are not based on third-party beneficiary concepts, but on principles of suretyship law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barlovento, LLC v. AUI, Inc.
D. New Mexico, 2020
Colonial Surety Co. v. United States
108 Fed. Cl. 622 (Federal Claims, 2013)
Hartford Fire Insurance v. United States
108 Fed. Cl. 525 (Federal Claims, 2012)
Lumbermens Mutual Casualty Co. v. United States
654 F.3d 1305 (Federal Circuit, 2011)
United Surety & Indemnity Co. v. United States
90 Fed. Cl. 203 (Federal Claims, 2009)
Lumbermens Mutual Casualty v. United States
90 Fed. Cl. 558 (Federal Claims, 2009)
PCL Construction Services, Inc. v. United States
84 Fed. Cl. 601 (Federal Claims, 2008)
Great American Insurance v. Norwin School District
544 F.3d 229 (Third Circuit, 2008)
Nelson Construction Co. v. United States
79 Fed. Cl. 81 (Federal Claims, 2007)
Patton v. United States
74 Fed. Cl. 110 (Federal Claims, 2006)
Wagner v. United States
71 Fed. Cl. 355 (Federal Claims, 2006)
Capitol Indemnity Corp. v. United States
71 Fed. Cl. 98 (Federal Claims, 2006)
Commercial Casualty Insurance v. United States
71 Fed. Cl. 104 (Federal Claims, 2006)
Engineered Demolition, Inc. v. United States
70 Fed. Cl. 580 (Federal Claims, 2006)
Liberty Mutual Insurance v. United States
70 Fed. Cl. 37 (Federal Claims, 2006)
Nova Casualty Co. v. United States
69 Fed. Cl. 284 (Federal Claims, 2006)
In Re Jones Construction & Renovation, Inc.
337 B.R. 579 (E.D. Virginia, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
118 F.3d 1542, 41 Cont. Cas. Fed. 77,129, 1997 U.S. App. LEXIS 16455, 1997 WL 366019, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-surety-corporation-v-united-states-cafc-1997.