Commercial Casualty Insurance v. United States

71 Fed. Cl. 104, 2006 U.S. Claims LEXIS 134, 2006 WL 1517346
CourtUnited States Court of Federal Claims
DecidedMay 26, 2006
DocketNo. 03-2033C
StatusPublished
Cited by10 cases

This text of 71 Fed. Cl. 104 (Commercial Casualty Insurance v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commercial Casualty Insurance v. United States, 71 Fed. Cl. 104, 2006 U.S. Claims LEXIS 134, 2006 WL 1517346 (uscfc 2006).

Opinion

OPINION

FIRESTONE, Judge.

Pending before the court is a motion by the defendant, the United States (“government” or “United States”), to dismiss the complaint of the plaintiff, Commercial Casualty Insurance Company of Georgia (“plaintiff” or “Commercial Casualty”), for failure to state a claim upon which relief can be granted, pursuant to Rule 12(b)(6) of the Rules of the United States Court of Federal Claims (“RCFC”). The government contends that the plaintiff, a Miller Act, 40 U.S.C §§ 3131-3134 (2000 & Supp.2002), surety of a government contractor who provided payment and performance bonds on a government construction contract, may not state a claim against the United States pursuant to the doctrine of equitable subrogation. In general, that doctrine provides that a surety who provides a bond guaranteeing the performance of a contract and who performs its obligations under that bond following contractor default may step into the shoes of another and assert that person’s rights in seeking reimbursement of its costs. The government does not dispute that if the plaintiff had been called upon to take over and complete performance of the contract at issue pursuant to its performance bond obligations, then the plaintiff would be subrogat-ed to the rights of the prime contractor. As [106]*106a result, a performance bond surety would be able to step into the contractor’s privity of contract with the government, and therefore would be able to rely on the waiver of sovereign immunity contained in the Tucker Act, 28 U.S.C. § 1491 (2000), to sue the United States for payment.

Instead, the government contends that because the plaintiff fulfilled its payment bond obligations and paid only subcontractors, the plaintiff is only subrogated to the rights of those subcontractors, who are not in privity of contract with the government and who therefore cannot sue the United States under the Tucker Act for payment. Because the plaintiff is not in privity of contract with the government either, the government contends that the plaintiff may not sue the United States in this court for the contract funds the government continues to hold in connection with the completed contract. In the alternative, the government argues that it is entitled to summary judgment because the plaintiff has not fully paid all of the subcontractors’ claims, and therefore the plaintiff may not assert a claim based on the doctrine of equitable subrogation.

The plaintiff and the amicus curiae, the Surety Association of America (“amicus” or “SAA”), argue that a payment bond surety, like a performance bond surety who takes over performance of a government contract, is subrogated to the rights of not only the subcontractors whom it pays, but also to the rights of the government contractor whose debt it pays, who is in privity with the government and, therefore, is able to sue the United States for payment.

For the reasons that follow, the court agrees with the plaintiff and amicus that a payment bond surety is subrogated to both subcontractors and the prime contractor, and therefore a payment bond surety may rely upon the prime contractor’s privity of contract with the United States and may sue the United States under the Tucker Act, pursuant to the doctrine of equitable subrogation. The government’s motion to dismiss is therefore DENIED. Based on representations made by the parties at oral argument, the court conditionally DENIES the government’s motion for summary judgment as well.

BACKGROUND

The following facts are undisputed unless otherwise noted.1 On June 25, 2001, the United States Department of the Navy (“Navy”) awarded Contract No. N62467-01-C-3215 to F.A.S. Development Company, Inc. (“FAS” or “contractor”) to replace a 400Hz frequency converter at Naval Air Station Atlanta in Marietta, Georgia. On July 17, 2001, the plaintiff issued performance and payment bonds to FAS in the amount of $108,768. On January 10, 2002, the plaintiff notified the government of outstanding claims by “subcontractors and vendors on projects bonded by the surety” and requested that no payments be made to FAS. Def.’s App. 9.

On March 27, 2002, FAS and the Navy entered into bilateral modification P00001, which amended contract specifications, decreased the contract price from $108,768 to $52,625, and extended the contract completion date from October 9, 2001 to June 14, 2002. Subsequently, they entered into another modification, P00002, which extended the contract completion date from June 14, 2002 to July 24, 2002.

FAS requested that the contract balance be assigned to the plaintiff, but on July 31, 2002, the Navy informed FAS that its request for an assignment of the contract balance to the plaintiff was “unapproved.” Def.’s App. 13. The stated reason was that the assignment would violate the Assignment of Claims Act. On August 2, 2002, the plaintiff requested by letter that the Navy not release contract funds to FAS, but to instead pay the plaintiff as surety. In its letter, the plaintiff stated that it “[was] equitably subro-gated to the contract funds through its payment of claims on this and other projects.” Def.’s App. 17.

[107]*107On August 19, 2002, the Navy issued a unilateral modification, P00003, which among other things reduced the contract price to $48,425. On September 10, 2002, FAS submitted a final invoice. The Navy has not paid FAS and continues to hold the $48,425 in contract funds.

By letter dated September 16, 2002, the plaintiff notified the Navy that it had received claims for payment from FAS’s subcontractors upon the contract, FCX Systems, Inc. (“FCX”) and Rogers Electrical Contractors, Inc. (“Rogers Electric”), and demanded that the Navy make payment to the plaintiff. The total amount of the claims made under the bond for this project was $37,209.

On July 31, 2003, the plaintiff sent a payment to Hatmaker and Associates, a debt collection agency hired by FCX, in the amount of $25,644, for the labor and materials that FCX provided on the contract. This payment was made pursuant to the payment bond issued by the plaintiff. The plaintiff has not paid any money to Rogers Electric; the plaintiff denied Rogers Electric’s claim for payment based on untimeliness.

The plaintiff filed a complaint in this court on September 2, 2003. Oral argument on the government’s motion to dismiss or in the alternative for summary judgment was held on April 28, 2006.2

DISCUSSION

1. Motion to Dismiss

A. Standard for Decision

The government has filed a motion to dismiss for failure to state a claim, although it argues that this court does not have jurisdiction over the plaintiff’s claim. While the plaintiff’s complaint states a type of claim over which this court generally has jurisdiction, the government argues that this court does not have jurisdiction over the plaintiff’s particular claim under the facts alleged here, and thus seeks dismissal for failure to state a claim. See Fisher v. United States, 402 F.3d 1167, 1172-73 (Fed.Cir.2005).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Colonial Surety Co. v. United States
108 Fed. Cl. 622 (Federal Claims, 2013)
Haddon Housing Associates, LLC v. United States
99 Fed. Cl. 311 (Federal Claims, 2011)
Insurance Co. of West v. United States
83 Fed. Cl. 535 (Federal Claims, 2008)
Nelson Construction Co. v. United States
79 Fed. Cl. 81 (Federal Claims, 2007)
United States Fire Insurance v. United States
78 Fed. Cl. 308 (Federal Claims, 2007)
National American Insurance v. United States
72 Fed. Cl. 451 (Federal Claims, 2006)
Travelers Indemnity Co. v. United States
72 Fed. Cl. 56 (Federal Claims, 2006)
Wagner v. United States
71 Fed. Cl. 355 (Federal Claims, 2006)
Capitol Indemnity Corp. v. United States
71 Fed. Cl. 98 (Federal Claims, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
71 Fed. Cl. 104, 2006 U.S. Claims LEXIS 134, 2006 WL 1517346, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commercial-casualty-insurance-v-united-states-uscfc-2006.