Capitol Indemnity Corp. v. United States

71 Fed. Cl. 98, 2006 U.S. Claims LEXIS 133, 2006 WL 1517335
CourtUnited States Court of Federal Claims
DecidedMay 26, 2006
DocketNo. 04-1478C
StatusPublished
Cited by11 cases

This text of 71 Fed. Cl. 98 (Capitol Indemnity Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Capitol Indemnity Corp. v. United States, 71 Fed. Cl. 98, 2006 U.S. Claims LEXIS 133, 2006 WL 1517335 (uscfc 2006).

Opinion

OPINION

FIRESTONE, Judge.

Pending before the court is a motion by the defendant, the United States (“government” or “United States”), to dismiss the complaint of the plaintiff, Capitol Indemnity Corporation (“plaintiff' or “Capitol Indemnity”) for failure to state a claim upon which relief can be granted, pursuant to Rule 12(b)(6) of the Rules of the United States Court of Federal Claims (“RCFC”). The government contends that the plaintiff, a Miller Act, 40 U.S.C. §§ 3131-3134 (2000 & Supp.2002), surety of a government contractor who fulfilled its obligations only under a payment bond on a government construction contract, may not state a claim against the United States pursuant to the doctrine of equitable subrogation.1 Because the plaintiff only paid subcontractors pursuant to its payment bond obligations, the government argues that the plaintiffs claim for reimbursement of its costs through the doctrine of equitable subrogation must be dismissed.2 In the alternative, the government argues that even if the plaintiff may maintain a claim for equitable subrogation, the plaintiffs failure to notify the government of the prime contractor’s default on its obligations to its subcontractors is fatal to its equitable subro-gation claim as a matter of law. For the reasons that follow, the court finds that a payment bond surety may maintain a claim for equitable subrogation, but that the plaintiffs equitable subrogation claim must be dismissed on the merits. The government’s motion to dismiss this claim is therefore GRANTED.

BACKGROUND

The following facts are taken from the plaintiffs complaint and are presumed to be true for purposes of the government’s motion to dismiss. On or about September 26, 2002, the Department of Veterans Affairs (“VA”) awarded Contract Number V69DC-506-8a to replace ARF chillers at the VA Medical Center in Milwaukee, Wisconsin, to R & T Mechanical Contractors, Inc. (“R & T”) for $579,257. R & T was required by the Miller Act, 40 U.S.C. §§ 3131-3134, to obtain performance and payment bonds from a surety in order to secure R & T’s performance of the contract. On November 22, 2002, the plaintiff, as surety for R & T, issued performance and payment bonds which contained the following condition: “All contract funds relating to this project are to be sent to Northern Escrow, Inc. for distribution.” Compl. ¶ 6. The plaintiff had hired Northern [100]*100Escrow, Inc. (“Northern”) to administer the contract by receiving progress payments from the United States and distributing the funds in accordance with the contract. The plaintiff, with R & T’s assent, included this payment provision in the bonds due to its concerns about R & T’s ability to satisfy its obligations to its subcontractors, suppliers, and materialmen. The bonds were accepted by the United States.

On December 5, 2002, the United States received R & T’s first progress report and progress payment application. The progress report stated that R & T had completed only 5% of the work required by the contract, although scheduled completion was 24%. Notwithstanding this discrepancy, the United States authorized a progress payment of $28,460 and paid this amount directly to R & T, rather than to Northern. The United States did not obtain the plaintiffs consent to pay R & T directly.

On December 24, 2002, the United States received R & T’s second progress report and progress payment application. The progress report stated that 12% of the contract was complete, while the payment application stated that 52% of the contract was complete. Scheduled completion was 35%. Notwithstanding this additional discrepancy, the United States again authorized a payment, this time in the amount of $274,674, and again sent this payment directly to R & T, rather than to Northern, without the plaintiffs consent.

On February 5, 2003, the United States received R & T’s third progress report and progress payment application. This time both the progress report and the payment application indicated that the contract was only 19% complete, although scheduled completion was 58%. The United States again authorized payment, in the amount of $38, 942.00, and sent this payment directly to R & T, rather than Northern, without the plaintiffs consent.

The first three progress payments totaled $342,166.00, representing 60% of the contract price. Following these three payments, the United States sent the remaining five progress payments to Northern, rather than to R & T.3 However, R & T failed to properly pay its subcontractors, suppliers, and material-men, and therefore defaulted on the contract with the United States. The subcontractors, suppliers, and materialmen filed claims against the bonds, and thus far the plaintiff has been required to pay $113,556.00 to these parties. The plaintiff demanded that the United States reimburse it in the amount of $113,556.00, discharge the plaintiff from any further bond obligations totally or pro tanto, and hold the plaintiff harmless from any pending unpaid claims. The United States rejected the demand.

On September 20, 2004, the plaintiff filed its complaint in this court seeking reimbursement of the $113,556.00 it has paid to subcontractors, pro tanto discharge, to be held harmless from any pending unpaid claims, attorney’s fees, interest, and costs. One of the plaintiffs arguments is that it is entitled to reimbursement from the United States pursuant to the doctrine of equitable subro-gation. Under this doctrine, the plaintiff argues that, as a surety, it is entitled to be subrogated to the rights of R & T and any subcontractors it paid in any contract funds held as security by the United States. The plaintiff argues that the United States abused its discretion by disbursing those contract funds directly to R & T rather than to Northern for the first three progress payments, and that therefore it is entitled to reimbursement from the United States for the amounts it has paid to subcontractors.

On June 3, 2005, the government moved to dismiss the plaintiffs complaint for failure to [101]*101state a claim upon which relief can be granted. The government argues that because the plaintiff only fulfilled the obligations of its payment bond, the plaintiff is only subro-gated to the rights of the subcontractors whom it paid. Because subcontractors do not have standing to bring claims against the United States, the government argues that the plaintiff may not bring its claim against the United States here. The government also argues that the plaintiff is not entitled to be reimbursed based on allegedly wrongful disbursements of progress payments because the plaintiff does not allege that it notified the government of R & T’s default before the government made the first three progress payments. On July 29, 2005, the SAA filed its amicus brief arguing that a payment bond surety is subrogated to the rights of both subcontractors and the prime contractor. Oral argument was held on April 28, 2006.4

DISCUSSION

A. Standard for Decision

The government has filed a motion to dismiss for failure to state a claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hanover Insurance Company (The) v. United States
133 Fed. Cl. 633 (Federal Claims, 2017)
Hartford Fire Ins. Co. v. Columbia State Bank
Court of Appeals of Washington, 2014
Hartford Fire Insurance v. Columbia State Bank
334 P.3d 87 (Court of Appeals of Washington, 2014)
Hartford Fire Insurance v. United States
108 Fed. Cl. 525 (Federal Claims, 2012)
Insurance Co. of West v. United States
83 Fed. Cl. 535 (Federal Claims, 2008)
Nova Casualty Co. v. United States
72 Fed. Cl. 755 (Federal Claims, 2006)
National American Insurance v. United States
72 Fed. Cl. 451 (Federal Claims, 2006)
Wagner v. United States
71 Fed. Cl. 355 (Federal Claims, 2006)
Cincinnati Insurance v. United States
71 Fed. Cl. 544 (Federal Claims, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
71 Fed. Cl. 98, 2006 U.S. Claims LEXIS 133, 2006 WL 1517335, Counsel Stack Legal Research, https://law.counselstack.com/opinion/capitol-indemnity-corp-v-united-states-uscfc-2006.