Hanover Insurance Company (The) v. United States

133 Fed. Cl. 633, 2017 WL 3634475
CourtUnited States Court of Federal Claims
DecidedAugust 24, 2017
Docket16-999C
StatusPublished
Cited by1 cases

This text of 133 Fed. Cl. 633 (Hanover Insurance Company (The) v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hanover Insurance Company (The) v. United States, 133 Fed. Cl. 633, 2017 WL 3634475 (uscfc 2017).

Opinion

OPINION

Bruggink, Judge.

In its amended complaint, plaintiff, Hanover Insurance Company (“Hanover”), seeks *634 to recover $440,000 from the United States on a theory of equitable subrogation. Hanover executed payment and performance bonds on behalf of its principal, B & J Multi Service Corporation (“B & J”), in connection with a contract between B & J and the Department of Veterans Affairs (“VA”) to repair the steam system at a VA facility in West Haven, Connecticut. Plaintiff contends that it notified the VA of a default by B & J, triggering its right to be equitably subrogat-ed to B & J’s right to the contract balance. Defendant moved to dismiss pursuant to Rule 12(b)(6) of the Rules of the United States Court of Federal Claims (“RCFC”), arguing that Hanover’s complaint is deficient as a matter of law because it does not allege that plaintiff put the VA on notice of B & J’s default until after the contract balance had been paid to B & J. Oral argument was held on May 2, 2017. As part of the briefing on defendant’s motion, both parties submitted materials outside of the complaint. The court therefore converted defendant’s motion to dismiss to one for summary judgment pursuant to RCFC 66 and afforded the parties an opportunity to submit supplemental materials to further support their positions. Supplemental briefing is now complete. Because defendant has not established that Hanover failed to give notice of default, defendant’s motion must be denied.

FACTUAL BACKGROUND

The following facts are undisputed. On August 4, 2009, B & J and the VA entered into Contract No. VA241-C-1241 (‘West Haven Contract”), pursuant to which B & J was to provide tools, labor, materials and equipment to repair the steam system at a VA facility in West Haven, Connecticut. As required by the West Haven Contract, B & J separately contracted with Hanover on August 20, 2009, to provide performance and payment bonds in support of B & J in the amount of $2,505,000.

Shortly thereafter, B & J commenced work but was suspended by the VA on February 17, 2010, for walking off the site, not paying subcontractors, and incorrectly certifying that subcontractors were being paid. During the course of the West Haven Contract, a number of B & J’s subcontractors and suppliers made claims against Hanover’s payment bonds.

On December 22, 2010, Hanover forwarded to the VA a fully executed assignment and direction of the contract funds from B & J to Hanover, but with respect to a contract not at issue here:

... B & J Multi Service Corp.... does hereby assign, transfer and set over to Hanover Insurance Group ... all of the Principal’s right, title, and interest in and to any and all payments ... and retainage ... any other money now due or hereafter to become due, arising out of [the contract]
[[Image here]]

Pi’s. Suppl. Br., Ex. A. That assignment was acknowledged by John Zizik of the VA, who noted that, “I am in receipt of your Notice of Assignment. I’ll be working this week on determining payment and change order requests.”

On February 2, 2011, Hanover informed the VA by email that it had been “writing large checks” to “ensure that the work for your project (West Haven Contract) is being performed without disruption.” Pi’s. Resp. to Mot. for Summ. J., Ex. A. In an email exchange on May 9, 2011, between Ms. Ruggie-ro, a contracting officer for the VA, and Mr. McDevitt, counsel for Hanover, Ms. Ruggiero stated that she had a “basis for termination fok default” of the West Haven Contract. Pi’s. Supp. Br., Ex. D. On August 3, 2011, Mr. Zizik, another contracting officer for the VA, sent an email to a subcontractor on the West Haven project, NG Environmental Contractors, directing it to address payment issues with Hanover. On August 11, 2011, another subcontractor, EnviroMed, emailed Hanover’s Mi'. McDevitt to assert a claim against the surety, on which Mr. Zizik was copied. On March 7, 2012, the VA terminated the West Haven Contract for convenience.

On February 23, 2013, the VA copied Hanover on an email containing its response to B & J’s settlement proposal for termination for convenience costs. Hanover responded on February 25, 2013, instructing the VA that “[n]o monies are to be paid to B & J. If this matter is resolved, all payments will be to Hanover.” Pi’s. Resp. to Mot. for Summ. J., Ex. B. On May 7, 2013, the VA agreed with *635 B & J to pay it $440,000 to settle all of B & J’s claims under the West Haven Contract.

On June 4, 2013, Ms. Ruggiero emailed Hanover’s counsel, Eric Loeffler, notifying Hanover of the settlement with B & J and inquiring whether payment was to go directly to the surety. Mr. Loeffler replied to the email saying that he is “doubtful of the authority of B & J to enter into such agreement, given Hanover’s equitable and contractual rights as surety” and again requested that funds not be released to B & J without Hanover’s written consent. Pi’s. Resp. to Mot. for Summ. J., Ex. C. Ms. Ruggiero then emailed B & J employees on June 6, 2013, stating that she still had “an issue to resolve with the bonding company requesting payment directly to them.” Id. Ex. D. Several weeks later, after learning of further communications between B & J and the VA, Hanover reminded the VA by letter, dated June 25, 2013, of its subrogation claim. The relevant portion of the June 25 letter is set out below:

This firm represents Hanover Insurance Group which issued the above referenced bond, as surety, on behalf of [B & J], principal .... Hanover was recently contacted by B & J about the status of the final negotiated payment due under the contract, and I understand you may have been in communication with B & J about the documents required to close-out the contract such that the final negotiated payment can be processed. For the reasons set forth below, it is important that Hanover be involved in that process. Please give me a call at your earliest convenience to discuss.
Also, I wish to reiterate Hanover’s demand that no further contract funds, either earned, unearned or retained, or settlement proceeds, be released to B & J or any other person or entity without the express written consent and direction of Hanover. Hanover has received claims and incurred losses against the ... bond, as well as other bonds issued by Hanover on behalf of B & J. Pursuant to Hanover’s common law rights of equitable subrogation, its perfected security interest, along with Hanover’s express assignment and trust fund rights as set forth in a written Agreement of Indemnity between Hanover and B & J, Hanover owns and/or otherwise has a priority interest to the funds.

Am. Compl., Ex. 3.

Despite Hanover’s communications with the VA, the agency paid B & J $440,000 on September 10, 2013. Defs. Mot. for Summ. J., Ex. 1. On September 17, 2013, counsel for Hanover sent a certified letter to the CO demanding payment of the $440,000, stating that “B & J is in default of the Bonds.” Am. Compl., Ex. 4. Having already made the final payment on the West Haven Contract, the VA refused.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
133 Fed. Cl. 633, 2017 WL 3634475, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hanover-insurance-company-the-v-united-states-uscfc-2017.