Lumbermens Mutual Casualty Co. v. United States

654 F.3d 1305, 2011 U.S. App. LEXIS 15903, 2011 WL 3319722
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 3, 2011
Docket2010-5086, 2010-5087
StatusPublished
Cited by52 cases

This text of 654 F.3d 1305 (Lumbermens Mutual Casualty Co. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lumbermens Mutual Casualty Co. v. United States, 654 F.3d 1305, 2011 U.S. App. LEXIS 15903, 2011 WL 3319722 (Fed. Cir. 2011).

Opinion

DYK, Circuit Judge.

This case requires us to decide three issues concerning the jurisdiction of the United States Court of Federal Claims (“Claims Court”) in actions brought by Miller Act sureties against the United States. See 40 U.S.C. § 3131(b) (2006) (formerly 40 U.S.C. § 270a).

In Insurance Company of the West v. United States, 243 F.3d 1367, 1375 (Fed.Cir.2001) [hereinafter ICW], we held that the Claims Court has jurisdiction under the Tucker Act, 28 U.S.C. § 1491, over sureties’ claims against the government that are based upon the theory of equitable subrogation. The first issue presented in this appeal is whether the surety’s claim against the United States seeking to recover allegedly improper progress payments made to the contractor is an equitable subrogation claim and is therefore within Tucker Act jurisdiction under ICW. We conclude that the surety’s claim is not an equitable subrogation claim because the United States made the payments in question before it received notice of the contractor’s default.

The second issue is whether the Claims Court has Tucker Act jurisdiction over impairment of suretyship claims against the government apart from the theory of equitable subrogation. We hold that the United States’ waiver of sovereign immunity under the Tucker Act does not extend to such claims.

The final question is whether the administrative requirements of the Contract Disputes Act (“CDA”), 41 U.S.C. § 601 et seq., apply to a surety’s claim against the United States arising from a takeover agreement which the government and surety have entered into for the completion of a bonded contract following the principal ob-ligor’s default. We hold that such claims fall within the scope of the CDA and that, as such, the Claims Court lacks jurisdic *1308 tion over a surety’s takeover agreement claim where the surety has failed to satisfy the CDA’s jurisdictional prerequisites.

Baokground

I

On April 11, 2000, Landmark Construction Company (“Landmark”) and the United States Navy (“Navy”) entered into a contract under which Landmark agreed to repair and renovate 160 military family housing units for the price of $9,878,026. The contract required construction to be completed by October 23, 2002, and it provided for liquidated damages of $75 per unit, per day past that date. In accordance with the Miller Act, 40 U.S.C. § 3131(b) (2006) (formerly 40 U.S.C. § 270a), the contract required Landmark to furnish performance and payment bonds.

To fulfill the construction contract’s bond requirement, Landmark entered into two suretyship agreements with Lumber-mens Mutual Casualty Company (“Lum-bermens”) on April 20, 2000, under which Lumbermens issued a payment bond (for $2.5 million) and a performance bond (for the $9,878,026 contract price). The United States was not a party to either suretyship agreement, but both contracts expressly identified the United States as the intended third-party beneficiary of the bond in the event Landmark breached its obligations.

On February 27, 2001, Landmark and the Navy agreed to add 21 housing units to the construction contract (for a total of 181 units) in exchange for increasing the contract price by $1,884,174. The modification did not extend the contract’s completion date, which remained October 23, 2002. Lumbermens did not provide payment or performance bonds for the additional units.

On July 20, 2001, Landmark informed the Navy that it was unable to complete the construction contract due to financial problems, and it abandoned the construction site soon thereafter. The Navy terminated Landmark for default on August 2, 2001. At that time, Landmark had completed only 22 (about 12%) of the 181 housing units, but the Navy had already given Landmark payments equal to $4,793,633 — approximately 40% of the modified contract price. In making these payments, the government allegedly ignored multiple Federal Acquisition Regulation (“FAR”) provisions incorporated into the contract that were purportedly aimed at ensuring progress payments would correspond to the amount of work actually completed. For example, under the FAR payment provisions, progress payments were not to be issued until Landmark provided a Schedule of Prices (an itemization of the contract price detailing how all funds would be spent), a Network Analysis Schedule (a chart breaking down the contractor’s work schedule into a series of tasks and dates), and, for each invoice, a Certification of Completion (a document certifying that the invoice submitted by the contractor only requests payment for services within the contract). Lumbermens contends that the government did not enforce these FAR provisions; that the provisions were intended to benefit the surety as well as the government; and that Lumbermens was injured as a result of the government’s lax enforcement.

Following Landmark’s default, the United States exercised its rights as an intended third-party beneficiary of the performance bond and demanded that Lumbermens complete the construction contract. Lumbermens accepted its obligation and hired Atherton Construction (“Atherton”) to complete the job. The three parties — Lumbermens, Atherton, and the United States — entered into a “takeover agreement” on November 20, *1309 2001, under which Lumbermens agreed that, “in accordance with [its] obligations under [the] Performance Bond,” “it [would] undertake the completion of the work and [would] contract with [Ather-ton] for completing the work remaining under the contract.” J.A. 314. Atherton agreed to complete the entire modified contract, including the 21 additional units that were not part of the original contract bonded by Lumbermens, and it contracted with another surety to bond the additional units. Lumbermens and Atherton also entered into a separate “completion” contract under which they agreed that Lumbermens would be responsible for all liquidated damages assessed by the government between October 23, 2002, and June 22, 2003, and Atherton would be liable for assessments thereafter.

In January 2002, after beginning construction, Atherton discovered safety code violations in the electrical work completed by Landmark. The Navy had previously been notified of the faulty wiring issue by Landmark during a design review meeting on August 24, 2000. Though the electrical issue delayed Atherton’s work by 46 days, the Navy denied Atherton’s requests for an extension.

Atherton completed the construction project on June 6, 2003.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sanchez v. United States
Federal Claims, 2026
HALL v. United States
Federal Claims, 2024
The Portland Mint v. United States
102 F.4th 1371 (Federal Circuit, 2024)
May v. United States
Federal Claims, 2022
Perry v. United States
Federal Circuit, 2021
Barlovento, LLC v. AUI, Inc.
D. New Mexico, 2020
Perry v. United States
Federal Claims, 2020
Ellis v. United States
Federal Claims, 2020
Guarantee Company of North v. Ikhana, LLC
941 F.3d 1140 (Federal Circuit, 2019)
Baha v. United States
Federal Claims, 2019
Thomas v. United States
Federal Claims, 2018
Phila. Indem. Ins. Co. v. Ohana Control Sys., Inc.
289 F. Supp. 3d 1141 (D. Hawaii, 2018)
Nottage v. United States
Federal Claims, 2017
Interdigital Communications v. Zte Corporation
711 F. App'x 998 (Federal Circuit, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
654 F.3d 1305, 2011 U.S. App. LEXIS 15903, 2011 WL 3319722, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lumbermens-mutual-casualty-co-v-united-states-cafc-2011.