Wolf Creek Railroad LLC v. United States

CourtCourt of Appeals for the Federal Circuit
DecidedNovember 25, 2025
Docket24-1873
StatusUnpublished

This text of Wolf Creek Railroad LLC v. United States (Wolf Creek Railroad LLC v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wolf Creek Railroad LLC v. United States, (Fed. Cir. 2025).

Opinion

Case: 24-1873 Document: 47 Page: 1 Filed: 11/25/2025

NOTE: This disposition is nonprecedential.

United States Court of Appeals for the Federal Circuit ______________________

WOLF CREEK RAILROAD LLC, Plaintiff-Appellant

v.

UNITED STATES, Defendant-Appellee ______________________

2024-1873 ______________________

Appeal from the United States Court of Federal Claims in No. 1:23-cv-01684-CNL, Judge Carolyn N. Lerner. ______________________

Decided: November 25, 2025 ______________________

LEWIS P. RHODES, Reston Law Group LLP, Reston, VA, argued for plaintiff-appellant. Also represented by THOMAS DAVID.

SEAN KELLY GRIFFIN, Commercial Litigation Branch, Civil Division, United States Department of Justice, Wash- ington, DC, argued for defendant-appellee. Also repre- sented by BRIAN M. BOYNTON, ERIC P. BRUSKIN, PATRICIA M. MCCARTHY. ______________________ Case: 24-1873 Document: 47 Page: 2 Filed: 11/25/2025

Before DYK, TARANTO, and CHEN, Circuit Judges. TARANTO, Circuit Judge. In 2023, Wolf Creek Railroad LLC sued the United States Army Joint Munitions Command (the Army) in the United States Court of Federal Claims (Claims Court) for compensation for alleged breach of a contract with the Army, including breach of an implied covenant of good faith and fair dealing. Wolf Creek brought its action under the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101(7), 7104(b)(1), invoking the Claims Court’s jurisdiction under 28 U.S.C. § 1491(a)(1)–(2). As relevant here, the Claims Court dismissed the complaint for lack of subject matter jurisdiction because the Army contract alleged was not one to which Wolf Creek was a party or under which the Army owed Wolf Creek a contractual duty. Wolf Creek Railroad, LLC v. United States, No. 23-1684, 2024 WL 1270189 (Fed. Cl. Mar. 26, 2024) (CFC Decision). We affirm. I A In 2008, the Army executed Contract No. W52P1J-09- E-0001 (Facility Contract) with American Ordnance, LLC, effective October 2, 2008, whereby American Ordnance agreed to perform operations and maintenance services at the Milan Army Ammunition Plant (Plant) in Milan, Ten- nessee. J.A. 40, 49. The Army and American Ordnance also executed Contract No. W52P1J-09-G-0001 (Basic Or- dering Agreement), effective the same day, providing for the Army to obtain operation and maintenance services from American Ordnance beyond those explicitly identified in the Facility Contract. J.A. 219–303. Within the Basic Ordering Agreement was a statement of work, in further- ance of the Armament Retooling and Manufacturing Sup- port (ARMS) Initiative, stating that the Army could authorize American Ordnance to put Army facilities to Case: 24-1873 Document: 47 Page: 3 Filed: 11/25/2025

WOLF CREEK RAILROAD LLC v. US 3

commercial use by, among other things, entering into “ten- ant use agreements” with third parties. J.A. 233. The statement of work (SOW) provided: The Government may authorize the Contractor [i.e., American Ordnance] to use facilities in sup- port of . . . tenant use agreements under this facil- ity contract during the term hereof. . . . Approval for such use shall not be construed as an extension of the facility contract. The approval for each use shall stand as separate agreements entered into under the authority of the facility contract, allow- ing use of those facilities specifically identified in the agreement for the specified period. Execution of each use and/or extension/option is dependent upon receipt of written authorization from the [Fa- cility Contract] Contracting Officer. J.A. 233 (SOW § 2.1.1). The SOW also clarified that, when American Ordnance entered into a tenant use agreement with the Army’s authorization, [t]he [Army] is not a party to the Tenant Use Agree- ments and does not deal directly with the tenants; all consideration/revenue is considered due from [American Ordnance]. J.A. 235 (SOW § 3.3.7). And the SOW addressed termina- tion and ensuing settlement costs: The FAR [(Federal Acquisition Regulation)] Part . . . 49 . . . sets forth the terms for establishing ap- propriate termination settlement costs associated with any . . . tenant use agreements. . . . Settle- ment consideration costs must be found allowable, allocable, and reasonable in accordance with the FAR requirements. Settlement consideration will include the contractors/subcontractors/tenant use contractor’s financial investment and contractual commitment for each individual . . . tenant use Case: 24-1873 Document: 47 Page: 4 Filed: 11/25/2025

agreement impacted. Tenant use contractors will negotiate all settlement agreements with [Ameri- can Ordnance]. J.A. 234 (SOW § 2.2.4). A decade later, in April 2018, American Ordnance re- quested authorization from the Army’s contracting officer to “subcontract” with Wolf Creek for Wolf Creek to operate a railway system at the Plant. J.A. 304–05. Two months later, the contracting officer issued a memorandum ap- proving the request if certain conditions were met. J.A. 306–09. As relevant here, the Army (1) required the agree- ment between American Ordnance and Wolf Creek to be a tenant use agreement in accordance with the SOW; (2) re- quired a copy of the executed agreement to be sent to the Army; (3) reserved the right to cancel an approved use at no cost to itself if the Plant was closed, sold, and/or trans- ferred to an entity outside the Department of the Army; and (4) required the agreement to stipulate that the Army “shall not be held liable in the event that [Wolf Creek] is forced to cease operations and thereby vacate the facility as a result of any change in [the Plant’s] status.” J.A. 306– 08. The Army’s authorization letter further explained that “[i]ndemnification is not included as part of this approval.” J.A. 308. In June 2018, American Ordnance and Wolf Creek ex- ecuted Tenant Use Contract AO 18-0002 (2018 TUA), which had a twenty-five-year duration with potential for renewal. J.A. 310–338. The Army did not review the 2018 TUA before it was executed by American Ordnance and Wolf Creek. See Complaint, Wolf Creek Railroad LLC v. United States, No. 24-1873 (Fed. Cl. Sept. 29, 2023), ECF No. 1 ¶ 15 (Complaint). In the 2018 TUA, Wolf Creek agreed to perform tasks such as railcar maintenance and repair, including maintenance of and certain repairs for government-owned locomotives, among other operational duties. J.A. 313–15. American Ordnance charged Wolf Case: 24-1873 Document: 47 Page: 5 Filed: 11/25/2025

WOLF CREEK RAILROAD LLC v. US 5

Creek fixed monthly fees for its use of the Plant and col- lected a percentage of Wolf Creek’s revenue from its opera- tions at the Plant. J.A. 304, 314. The 2018 TUA also addressed termination procedures, using the word “Owner” to refer to the landowner, i.e., the Army: (a) Convenience – The Owner’s representative [i.e., American Ordnance] may terminate this Agree- ment or portions thereof at any time by giving thirty (30) days written notice to the Tenant [i.e., Wolf Creek] . . . (iii) in the event the Government determines that termination of this Agreement or portions thereof is in the best interests of the Gov- ernment or (iv) the Owner’s representative’s inabil- ity to perform any of its obligations, including, but not limited, its ability to authorize use of the Facil- ities to the Tenant. In the event of termination un- der this provision, the termination will be at no cost to the Owner’s representative and the Owner’s rep- resentative shall be held harmless for any damages as a result of the termination. . . . (d) This Article 13 shall be administered according to FAR Part 49, as it relates to fixed price contracts. J.A. 323 (2018 TUA §§ 13(a), (d)). In 2019, Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Merritt v. United States
267 U.S. 338 (Supreme Court, 1925)
Kern-Limerick, Inc. v. Scurlock
347 U.S. 110 (Supreme Court, 1954)
Winter v. FloorPro, Inc.
570 F.3d 1367 (Federal Circuit, 2009)
Biltmore Forest Broadcasting Fm, Inc. v. United States
555 F.3d 1375 (Federal Circuit, 2009)
Lumbermens Mutual Casualty Co. v. United States
654 F.3d 1305 (Federal Circuit, 2011)
The United States v. Johnson Controls, Inc.
713 F.2d 1541 (Federal Circuit, 1983)
Cgi Federal Inc. v. United States
779 F.3d 1346 (Federal Circuit, 2015)
Rasmuson v. United States
807 F.3d 1343 (Federal Circuit, 2015)
Pacific Gas and Electric Co. v. United States
838 F.3d 1341 (Federal Circuit, 2016)
Frankel v. United States
842 F.3d 1246 (Federal Circuit, 2016)
Stephens v. United States
884 F.3d 1151 (Federal Circuit, 2018)
Nova group/tutor-saliba v. United States
87 F.4th 1375 (Federal Circuit, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
Wolf Creek Railroad LLC v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wolf-creek-railroad-llc-v-united-states-cafc-2025.