Cgi Federal Inc. v. United States

779 F.3d 1346, 2015 U.S. App. LEXIS 3685, 2015 WL 1015678
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 10, 2015
Docket2014-5143
StatusPublished
Cited by70 cases

This text of 779 F.3d 1346 (Cgi Federal Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cgi Federal Inc. v. United States, 779 F.3d 1346, 2015 U.S. App. LEXIS 3685, 2015 WL 1015678 (Fed. Cir. 2015).

Opinion

MOORE,. Circuit Judge.

In this pre-award bid protest appeal, CGI Federal Inc. challenges the payment terms of requests for quotes (“RFQs”) issued by the United States Department of Health and Human Service’s Centers for Medicare and Medicaid Services (“CMS”). CGI argues that the payment terms violate certain statutory and regulatory provisions. The government responds, as it did below, that CGI did not have standing to bring its bid protest because it did not qualify as an “interested party” within the meaning of 28 U.S.C. § 1491(b)(1). Because the Court of Federal Claims correctly held that CGI qualified as an interested party at the time it filed its bid protest, but erred in holding that the payment terms do not violate the applicable regulations, we reverse and remand.

*1348 Background

In the contracts at issue, CMS uses contractors, such as CGI, to determine if Medicare claims were correctly paid. If the contractor identifies an overpayment, CMS sends a demand letter to the provider seeking repayment and pays the contractor a contingency fee. Pursuant to the original contracts from 2008, the contractors invoiced CMS for the contingency fee when the overpayment was collected from the provider, typically 41 days after the demand letter. In 2014, CMS issued new RFQs for these recovery services. The 2014 RFQs included additional payment terms requiring the contractors to wait to invoice CMS until a provider’s challenge to the repayment request passed the second level of a five-level appeal process, which typically occurs somewhere between 120 and 420 days after the demand letter.

Five different contractors bid on the 2014 RFQs, but CGI did not. Instead, before bidding closed, CGI filed a timely pre-award protest at the Government Accountability Office (“GAO”) challenging the revised payment terms. While the GAO protest was pending, the bidding period closed. The GAO subsequently denied the protest. Three business days later, CGI filed a protest in the United States Court of Federal Claims. CGI and the government then filed cross-motions for judgment on the administrative record, and the government moved to dismiss for lack of standing. The Court of Federal Claims denied the government’s motion to dismiss but granted its motion for judgment on the administrative record, holding that the modified payment terms do not violate statutory or regulatory provisions. CGI Fed. Inc. v. United States, No. 14-cv-00355-MCW, slip op. at 9-10, 18-21 (Fed. Cl. Aug. 15, 2014) (“Opinion and Order ”). It also held that the payment terms do not unduly restrict competition. Id. at 22. CGI appeals. We have jurisdiction under 28 U.S.C. § 1295(a)(3).

Discussion

I. Standing

Whether a party has standing is an issue of law that we review de novo. Am. Fed’n of Gov’t Emps. v. United States, 258 F.3d 1294, 1298 (Fed.Cir.2001) (“AFGE”). To have standing to bring a bid protest in the Court of Federal Claims, a plaintiff must be an “interested party.” 28 U.S.C. § 1491(b)(1). While § 1491(b)(1) does not define “interested party,” we have construed the term in accordance with the definition provided in the Competition in Contracting Act (“CICA”), 31 U.S.C. §§ 3551-56, “an actual or prospective bidder or offeror whose direct economic interest would be affected by the award of the contract or by failure to award the contract.” AFGE, 258 F.3d at 1299 (quoting 31 U.S.C. § 3551(2)). Thus, to demonstrate that it has standing, CGI must show that it is (1) an actual or prospective bidder, and (2) that it has a direct economic interest. Digitalis Educ. Solutions, Inc. v. United States, 664 F.3d 1380, 1384 (Fed.Cir.2012).

A. Prospective Bidder

CGI never submitted a bid in response to the 2014 RFQs and thus is not an actual bidder. CGI must therefore show that it was a prospective bidder at the time it filed its protest in the Court of Federal Claims. We hold that it has made such a showing.

The parties primarily debate the implications of four cases in which we have opined on the meaning of “prospective bidder.” A brief description of each case is helpful. In MCI Telecommunications Corp. v. United States, we considered the meaning of “prospective bidder” within the now-defunct Brooks Act, 40 U.S.C. *1349 § 759(f)(9)(B), which included a definition of “interested party” identical to the definition in CICA. 878 F.2d 362 (Fed.Cir. 1989). There, we held that MCI was not a prospective bidder because it did not participate in the bidding process and did not file the protest at issue until after the contract had been awarded. Id. at 364-65. We noted that MCI could not “achieve prospective bidderhood” via its post-award protest because “the opportunity to qualify either as an actual or prospective bidder ends when the proposal period ends.” Id. at 365.

One year later in Federal Data Corp. v. United States, we held that Federal Data was not a “prospective bidder” within the meaning of the Brooks Act because it withdrew from the bidding process prior to filing a protest. 911 F.2d 699, 702-05 (Fed.Cir.1990). “Federal Data knowingly took itself out of the bidding prior to filing its amended protest,” and therefore “relinquished any chance of receiving the contract by that action.” Id. at 703-04. We noted that Federal Data “could have continued to compete for the contract award ... and could have utilized the protest procedures available to an interested party to correct any deficiencies it perceived in the procurement process,” but did not. Id. at 705. We stated that a “prospective bidder” “does not include one who only intends to bid in the event of a reprocurement.” Id. at 704.

We considered the meaning of “prospective bidder” in the context of an interested party under § 1491 in Rex Service Corp. v. United States, 448 F.3d 1305 (Fed.Cir. 2006). Rex initially filed a pre-award protest with the agency. Id. at 1307. The agency denied its protest, and Rex, having not submitted a bid, did not pursue the matter further. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
779 F.3d 1346, 2015 U.S. App. LEXIS 3685, 2015 WL 1015678, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cgi-federal-inc-v-united-states-cafc-2015.