Konecranes Nuclear Equipment & Services, LLC

CourtArmed Services Board of Contract Appeals
DecidedMay 7, 2024
Docket62797, 62827
StatusPublished

This text of Konecranes Nuclear Equipment & Services, LLC (Konecranes Nuclear Equipment & Services, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Konecranes Nuclear Equipment & Services, LLC, (asbca 2024).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) Konecranes Nuclear Equipment & ) ASBCA Nos. 62797, 62827 Services, LLC ) ) Under Contract No. N62470-16-D-2013 )

APPEARANCES FOR THE APPELLANT: Suzanne Sumner, Esq. Taft Stettinius & Hollister LLP Dayton, OH

William Wagner, Esq. Taft Stettinius & Hollister LLP Indianapolis, IN

APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq. Navy Chief Trial Attorney Susannah M. Mitchell, Esq. Antonio T. Robinson, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE HERZFELD

Konecranes Nuclear Equipment Services, LLC (Konecranes) appeals the Department of the Navy’s (Navy) contracting officer’s final decisions denying Konecranes’ claims to interpret the contract and for delay damages. Konecranes sought to deliver four portal cranes to the Navy, but the Navy refused to accept delivery after an initial test of one of the cranes revealed some damage to the luffing drum. Konecranes quickly identified the root cause of the damaged drum and fixed the problem. However, the Navy would not accept Konecranes’ solution and its unsuccessful demand for an unnecessary alternative solution caused further delay and increased Konecranes’ costs. We conducted a six-day hearing on entitlement and quantum and conclude that Konecranes’ four cranes met the contractual requirements and were ready for delivery. The Navy’s decision to delay delivery based on a requested change to contractual requirements was not justified. Therefore, we sustain Konecranes’ appeals and award $4,862,696.31 plus any Contract Disputes Act (CDA) interest from the time it submitted its monetary claim. FINDINGS OF FACT

I. The Navy Approves of Konecranes’ Design for Four Level-Luffing Cranes

A. The Navy Purchases Four Level-Luffing Cranes

On March 3, 2016, the Navy awarded Konecranes contract No. N62470-16-D- 2013 (the Contract), an indefinite delivery/indefinite quantity contract to design, fabricate, assemble, and deliver up to four, 25-ton general purpose portal cranes for use at the Navy’s Puget Sound Naval Shipyard, Naval Base Kitsap, Bremerton and Bangor, Washington (R4, tab 1, at 27; tab 128 at 795). 1 The cranes will be used to load food, maintenance, parts, and other supplies into the Navy’s nuclear submarines at the naval shipyard, but will not handle any nuclear materials (tr. 1/39-40, 43). The Navy ordered two cranes for Bangor (cranes 53-54) and two cranes for Bremerton (cranes 51-52) for a total of $62,241,720 (R4, tab 15; exs. A-15 to -17).

The Navy Crane Center (the Navy agency that typically handles crane procurements involving cranes above 10 tons) conducted the procurement and awarded the Contract (tr. 6/8). The Navy has an inventory of between 4,000 and 5,000 cranes (tr. 6/10). The Navy procured the cranes from Konecranes as commercial items, but the Navy Crane Center had never previously used a commercial items procurement to purchase a crane (tr. 1/43, 6/78-79, 6/101).

Konecranes and its predecessors – Pawling & Harnischfeger and Morris Material Handling – have built over 600 cranes for the Navy, including recently delivering a 140-ton portal crane for lifting nuclear materials, and constructing three, 175-ton portal cranes (tr. 1/41-43). Also, Konecranes is a subsidiary of Finland-based Konecranes, Plc (Konecranes-Finland), which has built tens of thousands of cranes (including hundreds of commercial portal cranes) (tr. 1/41, 57).

1 The Rule 4 file submitted by the Navy consisted of Tabs 1-98. Konecranes supplemented the Rule 4 file with Tabs 99-164. At the request of the parties, we admitted all Rule 4 file documents as evidence in our April 13, 2022 Order (see also tr. 1/9-10). Because the tabs are sequential, we reference all these documents as “R4.” The parties also requested and we admitted Konecranes Exhibits A-1 through A-19 as evidence in our April 13, 2022 Order (see also tr. 1/10). We admitted Exhibits A-20 and G-1 during the hearing (tr. 3/67, 5/27-29). As represented to the Board on the first day of the hearing, the parties stipulated to the admission of deposition transcripts for seven witnesses so the parties could cite relevant parts in their post-hearing briefs (tr. 1/8-9). For page citation to the Rule 4 documents, we refer only to the page number and exclude pre-fixes (“GOVRule4,” “KNESRule4Sup4,” or “GOVPROD”) and leading zeroes before the page numbers. 2 Konecranes proposed using level-luffing portal cranes to meet the requirements of the Contract (tr. 1/60, 69; R4, tab 99). Konecranes-Finland’s ports group had showed the Navy’s Bremerton personnel a level-luffing crane used in nearby Victoria Island before contract award and Bremerton’s personnel were interested in that design (tr. 3/155, 171). Below is a diagram of the proposed level-luffing crane, which we have annotated based on the testimony at the hearing:

(R4, tab 99 (diagram); tr. 1/45, 47 (boom at 285 feet when raised, structure slews/rotates); R4, tab 128 at 796 (30 foot rails at Bangor, 20 foot rails at Bremerton)).

When the boom is raised and lowered it is known as “luffing” (tr. 1/51). To “luff” (or raise or lower) the boom, the crane uses two steel ropes wrapped around a

3 steel luffing drum (powered by a motor) (tr. 1/64, 118). As the steel ropes unwind, the boom gets lowered, usually to a 35-degree angle when loading submarines or fully horizontal when the crane is subject to quarterly maintenance (tr. 1/65-66). As the steel ropes wind back around the steel drum, the boom gets raised (tr. 1/64, 118, 2/20, 67).

Konecranes proposed using a level-luffing crane (as opposed to a non-level luffing crane, also known as a reeving crane), because the hook holding the payload stays at the same height when the boom is raised and lowered (R4, tab 99; tr. 1/61-62). Konecranes deemed using a level-luffing crane “a little safer” when loading materials because it would result in faster and more efficient loading that would avoid “hitting” the periscopes, antennas, and the submarine sail (the large black tube that sticks up from the submarine) (tr. 1/39-40, 66-67, 70). The level-luffing crane also required less use and, thus, less stress on the luffing drum – sometimes only used for several minutes to move the boom into a steady angle before rotating (or “slewing”) a load from the dock to over a submarine (tr. 2/19-21, 3/215-16). Instead of using the luffing mechanism to move the boom up and down to load supplies, the level-luffing crane relies more heavily on a separate main hoist and whip hoist (or auxiliary hoist) with a separate hoist steel drum and ropes to raise and lower the hook to place loads into the submarine (R4, tab 128 at 796-97; tr. 3/215-17).

Prior to the Contract with Konecranes, the Navy had never purchased a level-luffing crane (tr. 5/82, 6/81).

B. Navy and Konecranes’ Design Changes, Design Drawings Approved

Given the requirement for a commercial item crane, the Contract’s specifications stated, “The crane design is intended to be a manufacturer’s standard design incorporating the additional features required by the specification” (R4, tab 128 at 795). Konecranes submitted the crane design for Navy approval (tr. 1/71). Konecranes submitted its proposed design drawings in September 2018 (tr. 1/74; but see R4, tab 38 at 359 (stating September 18, 2017)). During the Navy’s review of Konecranes’ design, the Navy requested and Konecranes agreed to modify the Contract to add a steel walkway along the boom to be used during maintenance of the crane (R4, tab 17 at 1; tr. 1/97-98). The addition of the steel walkway added more than 5,000 pounds to the boom weight (tr. 1/98-99, 234).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hercules, Inc. v. United States
516 U.S. 417 (Supreme Court, 1996)
States Roofing Corporation v. Winter
587 F.3d 1364 (Federal Circuit, 2009)
Yankee Atomic Electric Co. v. United States
536 F.3d 1268 (Federal Circuit, 2008)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
G. L. Christian and Associates v. The United States
312 F.2d 418 (Court of Claims, 1963)
Gardner Displays Company v. The United States
346 F.2d 585 (Court of Claims, 1965)
Tecom, Inc. v. The United States
732 F.2d 935 (Federal Circuit, 1984)
Cheyenne River Sioux Tribe v. United States
806 F.2d 1046 (Federal Circuit, 1986)
C. Sanchez and Son, Incorporated v. United States
6 F.3d 1539 (Federal Circuit, 1993)
Hercules Incorporated v. United States
292 F.3d 1378 (Federal Circuit, 2002)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)
Indiana Michigan Power Company v. United States
422 F.3d 1369 (Federal Circuit, 2005)
Scott Timber Co. v. United States
692 F.3d 1365 (Federal Circuit, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Konecranes Nuclear Equipment & Services, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/konecranes-nuclear-equipment-services-llc-asbca-2024.