States Roofing Corporation v. Winter

587 F.3d 1364, 2009 U.S. App. LEXIS 26569, 2009 WL 4546850
CourtCourt of Appeals for the Federal Circuit
DecidedDecember 7, 2009
Docket2009-1067
StatusPublished
Cited by44 cases

This text of 587 F.3d 1364 (States Roofing Corporation v. Winter) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
States Roofing Corporation v. Winter, 587 F.3d 1364, 2009 U.S. App. LEXIS 26569, 2009 WL 4546850 (Fed. Cir. 2009).

Opinions

NEWMAN, Circuit Judge.

States Roofing Corporation appeals the decision of the Armed Services Board of Contract Appeals (“the Board”), denying States Roofing’s claim for additional costs incurred in connection with its contract to perform roofing work at a Naval facility in Norfolk, Virginia.1 The claim is brought in accordance with the Contract Disputes Act of 1978, 41 U.S.C. § 601 et seq., and turns on whether States Roofing reasonably interpreted certain aspects of the contract, such that the Navy’s divergent interpretation is appropriately viewed as a constructive change and warrants compensation. The Board allowed the claim as applied to work in some areas of the roof, and denied the claim as to the same work in other areas of the roof. States Roofing appeals the denial, and disputes the meas[1367]*1367ure of the compensation awarded for the allowed portion of the claim.

BACKGROUND

States Roofing and the Navy entered into Contract No. N62470-97-C-8319 for “Building W-143 Roof Replacement, Wall Repair & Painting,” at a fixed price of $2,370,000. Building W-143 is a large structure, and in the contract the roof is divided into eleven “cells,” labeled A through K. These cells include penthouses located on the main roof, and both the main roof itself and the penthouses have vertical elements called parapet walls. This appeal relates to the contract’s requirements for waterproofing of the parapet walls.

Pursuant to Federal Acquisition Regulation (“FAR”) 52.236-3 (“Site Investigation and Conditions Affecting the Work”), States Roofing’s President, Hugh DeLauney, had inspected the roof of Building W-143 before bidding. Mr. DeLauney observed the roofing work that had previously been performed in cells A and B by a different contractor, RayCo Roofing. RayCo had used waterproofing paint on the parapet walls in these cells; States Roofing formulated its bid accordingly. The Board found that the use of paint to waterproof parapet walls is not uncommon, and that States Roofing had used this method of waterproofing in other government contracts. The Board found that “[a]t the time of the bid, SRC intended to paint the parapet walls after cleaning them; it did not intend to apply any type of wall flashing to them.” Board Opinion at 9.

After States Roofing had been awarded the contract and had begun work on the project, the Navy objected to the use of waterproofing paint on the parapet walls. Lt. Darren R. Hale, the Assistant Resident Officer in Charge of Construction, disagreed with States Roofing’s understanding of the contract, and required use of three-ply felt flashing material to waterproof the parapet walls. It was eventually agreed that States Roofing would apply a one-ply waterproofing flashing material having the brand name “DynaClad,” but only because the commercially available three-ply flashing material was found not suitable for this application and DynaClad was deemed a comparable substitute. States Roofing complied with the Navy’s instructions and applied the DynaClad to the parapet walls, and requested an equitable adjustment for the additional cost of using DynaClad flashing material instead of paint on the parapet walls. The Navy’s contracting officer held that the use of DynaClad was a no-cost change, reasoning that the contract required three-ply flashing material, not paint.

The roofing work continued to completion. States Roofing’s accountant performed an audit, including all adjustments and settled claims, and concluded that the company had incurred costs totaling $3,329,317.51 in performing the contract, excluding profit. The government’s corresponding audit concluded that total costs of $3,336,636 were incurred, excluding profit. States Roofing was paid a total of $2,934,346.07, placing it in an overall loss position.

On appeal to the Board, States Roofing argued that it had reasonably interpreted the contract as permitting use of waterproofing paint for the parapet walls, and that if the contract were unclear or ambiguous, reasonable doubt should be resolved in favor of the contractor under the rules of interpretation of federal procurement contracts. The Board found that for the parapet walls of the penthouses of roof cells A and B, only waterproofing paint was required, but that for parapet walls in cells C through J, three-ply flashing mate[1368]*1368rial was required. The Board found that States Roofing erroneously assumed that the acceptability of paint for cells A and B also applied to cells C through J, and that States Roofing failed to take account of certain detail appearing on drawing A38, which was one of the 48 sheets of drawings included with the contract. The Board found that there was “no specification for the parapet wall waterproofing membrane,” for the Navy stated that it had “inadvertently” omitted this specification. Board Opinion at 7. However, the Board held that drawing A38 provided sufficient indication that felt flashing material was required on the parapet walls, to render States Roofing’s interpretation “not within the zone of reasonableness.” Id. at 20.

The Board also stated, as an alternative ground for denying relief for the roof cells other than cells A and B, that “[a]t a minimum, there was a patent ambiguity in the specifications and drawings arising out of the references to ‘coats,’ ‘layers’ and ‘plies’ about which [States Roofing] was obligated to inquire.” Id.

DISCUSSION

Contract interpretation under the Contract Disputes Act is a question of law, requiring plenary determination on appeal to this court, with “no deference owing to the interpretation adopted by either the agency or the Board.” Lockheed Martin IR Imaging Systems, Inc. v. West, 108 F.3d 319, 322 (Fed.Cir.1997); see 41 U.S.C. § 609(b) (“the decision of the agency board on any question of law shall not be final or conclusive”); Textron Def. Systems v. Widnall, 143 F.3d 1465, 1468 (Fed.Cir.1998) (“Contract interpretation is a question of law over which we exercise complete and independent review.”). In addition, “[c]onstruetion of the language of the contract to determine whether there is an ambiguity is a question of law which we review without deference.” Gardiner, Kamya & Assocs., P.C. v. Jackson, 467 F.3d 1348, 1353 (Fed.Cir.2006). “[Whether ambiguities are latent or patent and whether the contractor’s interpretation thereof is reasonable are also questions of law subject to de novo review.” Interwest Constr. v. Brown, 29 F.3d 611, 614 (Fed. Cir.1994). However, the Board’s factual findings “shall be final and conclusive and shall not be set aside unless the decision is fraudulent, or arbitrary, or capricious, or so grossly erroneous as to necessarily imply bad faith, or if such decision is not supported by substantial evidence.” 41 U.S.C. §

Related

Govwave, LLC v. United States
Federal Claims, 2025
Direct Steel, LLC
Armed Services Board of Contract Appeals, 2024
Konecranes Nuclear Equipment & Services, LLC
Armed Services Board of Contract Appeals, 2024
Anderson Contracting, LLC
Armed Services Board of Contract Appeals, 2024
IMC Construction Group
Armed Services Board of Contract Appeals, 2023
Richardson v. United States
Federal Claims, 2021
JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2021
L3 Technologies, Inc.
Armed Services Board of Contract Appeals, 2021
Granite Construction Company
Armed Services Board of Contract Appeals, 2020
Kiewit Infrastructure West Co. v. United States
972 F.3d 1322 (Federal Circuit, 2020)
Fluor Federal Solutions, LLC
Armed Services Board of Contract Appeals, 2019
Manhattan Hunt A Joint Venture
Armed Services Board of Contract Appeals, 2019
KiewitPhelps
Armed Services Board of Contract Appeals, 2019
L&M Technologies, Inc.
Armed Services Board of Contract Appeals, 2018
Parsons Evergreene, LLC
Armed Services Board of Contract Appeals, 2018

Cite This Page — Counsel Stack

Bluebook (online)
587 F.3d 1364, 2009 U.S. App. LEXIS 26569, 2009 WL 4546850, Counsel Stack Legal Research, https://law.counselstack.com/opinion/states-roofing-corporation-v-winter-cafc-2009.