KiewitPhelps

CourtArmed Services Board of Contract Appeals
DecidedApril 24, 2019
DocketASBCA No. 61197
StatusPublished

This text of KiewitPhelps (KiewitPhelps) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
KiewitPhelps, (asbca 2019).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of-- ) ) KiewitPhelps ) ASBCA No. 61197 ) Under Contract No. W9128F-12-C-0023 )

APPEARANCES FOR THE APPELLANT: Vivian Katsantonis, Esq. Christopher M. Harris, Esq. Watt, Tieder, Hoffar & Fitzgerald, L.L.P. McLean, VA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Thomas J. Ingram, Esq. Engineer Trial Attorney U.S. Army Engineer District, Omaha

OPINION BY ADMINISTRATIVE JUDGE CLARKE

This appeal arises from the contract to construct a five-level, one millio.n square foot facility to replace the U.S. Strategic Command (STRATCOM) complex at Offutt Air Force Base (OAFB) near Omaha, Nebraska. Specifically, this appeal deals with a dispute over wallboard (gypsum board) finishing requirements throughout the buildings. We have jurisdiction pursuant to the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7101-7109. We sustain the appeal.

FINDINGS OF FACT

Finishing vs. Finishes

1. Mr. Douglass is an operations manager for Hensel Phelps, one of the joint venture partners Kiewit and Hensel Phelps making up KiewitPhelps (KP). He had overall responsibility for this project. (Tr. 1/51-53) Mr. Douglass explained that drywall finishing is "used synonymously with the terminology of how you apply joint tape and drywall compound to the drywall to prepare it for decoration." He distinguished "drywall finishing" from "finishes" that are typically paint, wall covering or anything that would architecturally treat the wall surface. (Tr. 1/63) Mr. Douglass explained there are six levels of drywall finishing starting with zero which is blank drywall, Level 1 which is "fire-taping" up to Level 5 which is the highest level with the most applications of joint compound. Each successive level builds on the previous level of joint taping and the application of joint compound. There are seven levels of "finishes" for different kinds of paint, wall coverings,· wood panels, etc. (Tr. 1/64-65, 69) This similar terminology for different products can cause confusion as can be seen in the bidder inquiry discussed below.

Pre-Award Bidder Inquiry

2. Bidder Inquiry No. 4179969 was submitted on September 14, 2011, and read "Spec section 09 29 00 identifies various drywall finish levels (Level 1-7). Please identify where each finish level is to be applied." The government response was:

Provide Level 4 throughout facility unless noted otherwise. Provide Level 5 at the following locations: Primary Corridors (adjacent to: elevators, restrooms, break areas, atrium, auditorium, directorate areas), Walls with wood trim and/or panels, Walls and/or ceilings with direct sunlight [o]n surface. Walls with applied solid surfaces. These areas will be clarified in an upcoming amendment.

(Supp. R4, tab 3; app. supp. R4, tab 34 at 2-3) Mr. Hailey is an architect working for architectural firm HOR on the STRATCOM replacement facility project since 2008 (tr. 2/204). Mr. Hailey wrote the government response to Bidder Inquiry No. 4179969 (tr. 2/222-24). Mr. Hailey explained that Levels 1-7 are paint levels not drywall finish levels and the inquiry cited the wrong specification "should be 0990, not 0929" (tr. 2/225-26, 271). His response told the bidders where to put the paint in terms of drywall finish (tr. 2/271, 273-74).

3. In her final decision, contracting officer (CO) Young stated, "The contract provisions dealing with drywall finishes, though atypical, are clear and unambiguous, and generated no bidder inquiries" (R4, disc I, tab 1 at 11 ).

KP 's Drywall Subcontractor Bids & Trade Practice

4. KP's drywall subcontractor, Cleveland Construction, Inc. (CCI), did not bid finishing to Level 4 above ceilings and below floors (tr. 1/223; app. supp. R4, tab 19 at 1). In addition to CCI, three other drywall subcontractors submitted bids to KP for drywall work. Each bidder interpreted the drywall specifications the same as CCI that Level 4/5 finish was required for exposed walls and fire-taping or Level 1 finishing was required above ceilings (tr. 1/79-82). Allied Construction Services, Inc., wrote "Exposed drywall finished to G.A. level 4" and "Rated drywall above the ceiling finished to G.A. level 1" (app. supp. R4, tab 23 at 2). Midwest Drywall Co., Inc., wrote "Level 4 and 5 finishes at exposed drywall, fire-tape above ceilings" (app. supp. R4, tab 24 at 2). Stowell Co., Inc., wrote "Level 4 finish, typical on all exposed walls

lt I and ceilings, level 1 above ceiling on rated walls. Level 5 finish per Addendum." (App. supp. R4, tab 25 at 1)

5. Mr. Stayer has been employed by CCI for 38 years and is now CCI's vice president of the interior division (tr. 1/256). He testified that the industry standard practice is to apply Level 1 (fire-taping) finish above ceilings and below floors and Level 4 or 5 where decoration is to be applied (tr. 1/256-57).

Contract Award

6. On August 16, 2012, the United States Army Corps of Engineers (USACE) awarded KP Contract No. W9128F-12-C-0023 for $524,445,324 to construct the STRATCOM replacement facility at OAFB (R4, disc 1, tab 3b). Part of the contract involved finishing gypsum wallboard (drywall). The drywall work was subcontracted to CCI for approximately $16 million. (Tr. 1/79, 218-19)

Sensitive Compartmented Information Facility (SCIF) - DCID 6/9

7. HDR Architecture (HDR) was the designer of the project. HDR prepared the drawings and produced the contract specifications. (Tr. 2/159-60, 204) The STRATCOM facility included SCIF space. Mr. Hailey and HDR utilized DCID 6/9 to satisfy the SCIF requirements and that included requiring only Levels 4 and 5 drywall finish (tr. 2/210). Mr. Hailey placed Note 10 on Architectural Drawing A-702A, Interior Wall Type Details, that read, "SCIF- IAW DIRECTOR OF CENTRAL INTELLIGENCE DIRECTIVE NO. 6/9, NOV. 2002" (DCID 6/9) (R4, disc 3, tab 2c, vol. 3 at 379). Concerning drywall construction DCID 6/9 provides:

4.2 SCIF Criteria For Permanent Dry Wall Construction

Walls, floor and ceiling will be permanently constructed and attached to each other. To provide visual evidence of attempted entry, all construction, to include above the false ceiling and below a raised floor, must be done in such a manner as to provide visual evidence of unauthorized penetration.

(App. supp. R4, tab 71 at 15) DCID 6/9 does not specify how the contractor should achieve the finish to "provide visual evidence of unauthorized penetration" (tr. 2/230-31). Mr. Hailey testified that Mr. DeRuiter was STRATCOM's security manager (tr. 2/206). Mr. DeRuiter wanted painted walls to be painted true floor to true ceiling (tr. 2/245). Mr. Hailey testified that he relied on Mr. DeRuiter's interpretation of what DCID 6/9 required on SCIF walls (tr. 2/245, 247).

3 8. Mr. Flere was the contracting officer's representative (COR) and quality assurance lead for the supervisory civil engineer on the STRATCOM project. He has been on the project since its inception. (Tr. 3/5-6; app. supp. R4, tab 76) COR Flere testified that DeID 6/9 did not require higher finish levels above ceilings and below floors (tr. 3/45). He has never seen Level 4 finish required above ceilings and below floors (tr. 3/46).

Sensitive Compartmented Information Facility (SCJF) -!CD 705 & JCS 705-1

9. The contract specifications included section 01 32 52. 02 24, Special Security.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

States Roofing Corporation v. Winter
587 F.3d 1364 (Federal Circuit, 2009)
LAI Services, Inc. v. Gates
573 F.3d 1306 (Federal Circuit, 2009)
Teg-Paradigm Environmental, Inc. v. United States
465 F.3d 1329 (Federal Circuit, 2006)
Lear Siegler Services v. Rumsfeld, Secretary of Defense
457 F.3d 1262 (Federal Circuit, 2006)
Fruin-Colnon Corporation v. The United States
912 F.2d 1426 (Federal Circuit, 1990)
Coast Federal Bank, Fsb v. United States
323 F.3d 1035 (Federal Circuit, 2003)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)
H & M Moving, Inc. v. United States
499 F.2d 660 (Court of Claims, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
KiewitPhelps, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kiewitphelps-asbca-2019.