Teg-Paradigm Environmental, Inc. v. United States

465 F.3d 1329, 2006 U.S. App. LEXIS 24520, 2006 WL 2788413
CourtCourt of Appeals for the Federal Circuit
DecidedSeptember 29, 2006
Docket2006-5007
StatusPublished
Cited by140 cases

This text of 465 F.3d 1329 (Teg-Paradigm Environmental, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Teg-Paradigm Environmental, Inc. v. United States, 465 F.3d 1329, 2006 U.S. App. LEXIS 24520, 2006 WL 2788413 (Fed. Cir. 2006).

Opinion

SCHALL, Circuit Judge.

TEG-Paradigm Environmental, Inc. (“TEG”) entered into a contract with the United States Department of Housing and Urban Development (“HUD”). Pursuant to the contract, TEG agreed to perform asbestos abatement work at the Geneva Towers, an apartment complex, in San Francisco. After the contract work was completed, TEG submitted a claim to the contracting officer in which it sought an equitable adjustment in the contract price. In support of its claim, TEG asserted that it had been required to perform excessive cleaning and that it had been required to remove excessive quantities of asbestos. After the contracting officer denied the claim, TEG filed suit in the United States Court of Federal Claims under the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (2000).

TEG’s complaint in the Court of Federal Claims contained three counts. In Count One, TEG alleged breach of contract based upon HUD not permitting TEG to perform the contract work in accordance with its original work plan. In Count Two, TEG alleged that HUD breached the contract by requiring what it characterized as extraordinary and unnecessary cleaning of the surfaces of the buildings; Finally, in Count Three, TEG alleged that it was entitled to additional compensation under the contract based upon its removal of excessive quantities of asbestos. TEG sought a combined breach of contract and equitable adjustment recovery in the amount of approximately $4 million.

In due course, the parties filed cross-motions for summary judgment. The *1332 court granted summary judgment for the government on Counts One and Two of the complaint and for TEG on Count Three of the complaint. Teg-Paradigm Envtl., Inc. v. United States, No. 00-507C, slip op. at 26 (Fed.Cl. Aug. 30, 2002). TEG now appeals from the court’s decision granting the government’s motion for summary judgment on its two claims of breach of contract. Finding no error in the Court of Federal Claims’s decision, we affirm. 1

BACKGROUND

I.

The Geneva Towers were two high-rise apartment buildings in San Francisco. HUD acquired the buildings in 1991 and decided to implode them to make way for new development. Id., slip op. at 2. However, the buildings contained asbestos, which had to be removed before implosion. Id. HUD solicited bids on a contract for asbestos abatement and TEG was awarded the contract on May 8, 1997, for a fixed price of $5,153,625.00. The contract required that the abatement be complete on or by December 31, 1997, and provided for liquidated damages of $5,000 per day of delay. After several extensions, the deadline for finishing the abatement was changed to February 15, 1998. Id., slip op. at 7. However, TEG did not finish the abatement work until March 31, 1998, causing HUD to assess $220,000 in liquidated damages against it. Id., slip op. at 8. This delay was purportedly caused at least in part by disagreements between TEG and HUD over contract requirements. Specifically, the parties disagreed as to (i) whether the contract required TEG to abate asbestos in the pores and cracks of the Geneva Towers’ surfaces and (ii) whether TEG was required to comply with the contract specifications rather than TEG’s work plan.

A.

We begin with the facts relevant to the first point of contention between the parties, which concerns the level of asbestos abatement required by the contract (Count Two of the complaint).

The original contract specifications provided two separate abatement standards, one for friable and one for non-friable asbestos-containing materials. Friable materials are capable, when dry, of being crumbled, pulverized, or reduced to powder by hand pressure. Id., slip op. at 2. The original asbestos abatement standard was set forth at Section 2080, 4.3C of the contract, which provided as follows:

Friable materials applied to concrete, masonry, wood and nonporous surfaces, including but not limited to, steel structural members (decks, beams and columns), pipes and tanks, shall be cleaned to a degree that no traces of debris or residue are visible. Nonfriable materials applied to concrete, masonry, [or] wood shall be cleaned until no residue is visible other than that which is embedded in the pores, cracks, or other small voids below the surface of the material.

Thus, the original specifications established a stringent visibility standard for friable materials and a less stringent standard, one which allowed the contractor to leave asbestos in the pores and cracks, for non-friable materials. The original Section 2080, 4.3C likely provided the stringent visibility standard for friable asbestos-containing materials because they are more likely to become airborne and thus pose a health risk.

*1333 In the course of the bidding process, prospective bidders, including TEG, raised questions about which standard applied to the concrete on the exterior of the buildings. During a conference call concerning the prospective contract, TEG’s representative noted, “It’s a significant difference, because on one it has to be clean to a degree there’s no trace; on the other, it’s clean to a degree that material can still be embedded in pores, cracks and voids.”

In response to the questions raised during the bidding process about the original asbestos abatement standard, the government modified the standard. The revised section 2080, 4.8C set forth a single standard for all asbestos-containing materials and provided as follows:

Asbestos-containing materials applied to concrete, masonry, wood and nonporous surfaces, including, but not limited to, steel structural members (decks, beams and columns), pipes and tanks, shall be cleaned to a degree that no traces of debris or residue are visible by the Observation Services Contractor.

Thus, the revised Section 2080, 4.3C abolished the old standard applicable for non-friable materials that stated that it was acceptable to leave asbestos-containing materials in pores and cracks. Instead, a standard requiring that there be no visible asbestos, similar to the original standard for friable asbestos-containing materials, was adopted for all asbestos-containing materials. 2

As noted by the Court of Federal Claims, trade practice and custom in the asbestos abatement field includes presuming that any “debris and residue” contains asbestos. Id., slip op. at 13. The court based its finding on the American Society for Testing Material (“ASTM”) standard for asbestos abatement, which provides, “Any residue, dust, or debris found during the inspections is assumed to contain asbestos ....” Id.

B.

The parties’ second disagreement concerns whether the contract’s specifications or TEG’s work plan controlled the terms of TEG’s performance (Count One of the complaint).

Section C of the contract specifications states that the contractor will provide a work plan for approval, The relevant portion of Section C provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Direct Steel, LLC
Armed Services Board of Contract Appeals, 2024
GEMS Environmental Management Services
Armed Services Board of Contract Appeals, 2024
IMC Construction Group
Armed Services Board of Contract Appeals, 2023
Assad v. United States
Federal Claims, 2023
Jemison & Partners, Inc.
Armed Services Board of Contract Appeals, 2022
H2L1-CSC, JV
Armed Services Board of Contract Appeals, 2021
Barlovento, LLC v. AUI, Inc.
D. New Mexico, 2021
Doe v. United States
Federal Claims, 2021
Devine v. United States
Federal Claims, 2021
Granite Construction Company
Armed Services Board of Contract Appeals, 2020
Trade West Construction, Inc.
Armed Services Board of Contract Appeals, 2020
DynCorp International LLC
Armed Services Board of Contract Appeals, 2020
South Carolina Public Service Authority
Armed Services Board of Contract Appeals, 2020
Aero Tech Services Associates, Inc.
Armed Services Board of Contract Appeals, 2020
Watts Constructors, LLC
Armed Services Board of Contract Appeals, 2020
Langkamp v. United States
943 F.3d 1346 (Federal Circuit, 2019)
Fluor Federal Solutions, LLC
Armed Services Board of Contract Appeals, 2019
Manhattan Hunt A Joint Venture
Armed Services Board of Contract Appeals, 2019

Cite This Page — Counsel Stack

Bluebook (online)
465 F.3d 1329, 2006 U.S. App. LEXIS 24520, 2006 WL 2788413, Counsel Stack Legal Research, https://law.counselstack.com/opinion/teg-paradigm-environmental-inc-v-united-states-cafc-2006.