Trade West Construction, Inc.

CourtArmed Services Board of Contract Appeals
DecidedOctober 5, 2022
DocketASBCA No. 61068
StatusPublished

This text of Trade West Construction, Inc. (Trade West Construction, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trade West Construction, Inc., (asbca 2022).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Trade West Construction, Inc. ) ASBCA No. 61068 ) Under Contract No. W912PM-15-C-0024 )

APPEARANCES FOR THE APPELLANT: Karl Dix, Jr., Esq. Lochlin B. Samples, Esq. Smith, Currie & Hancock LLP Atlanta, GA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney David C. Brasfield, Jr., Esq. Carl E. Pruitt, Jr., Esq. Engineer Trial Attorney U.S. Army Engineer District, Mobile

OPINION BY ADMINISTRATIVE JUDGE STINSON

Appellant Trade West Construction, Inc., (Trade West or TWC), appeals a contracting officer’s denial of its October 21, 2016, claim, in the amount of $304,062, for shaping armor stone prior to placing it on top of an existing jetty. Trade West argues that the government wrongfully rejected the armor stone it wished to use, thereby forcing it to spend time and money shaping armor stone to make it acceptable to the government (R4, tab 3). 1 We have jurisdiction pursuant to the Contract Disputes Act of 1978, 41 U.S.C. §§ 7101-7109. We previously denied the parties’ cross-motions for summary judgment, finding triable issues of fact which could not be resolved on summary judgment. Trade West Construction, Inc., ASBCA No. 61068, 20-1 BCA ¶ 37,713 at 183,076 (Trade West I). The parties agreed to submit this appeal on the record, pursuant to Board Rule 11, for a decision on entitlement only. Each party submitted initial and responsive briefs. For the reasons set forth below, we deny the appeal.

FINDINGS OF FACT

1. On September 25, 2015, the United States Army Corps of Engineers (USACE), South Atlantic Division, Wilmington District (SAW) awarded Trade West Contract No. W912PM-15-C-0024 (the Contract), in the amount of $3,294,362, for

1 The government’s initial Board Rule 4 file was submitted in paper form and included tabs marked 1 through 5.10. The government’s joint supplemental Rule 4 file was submitted electronically and included tabs marked 006 through 090. South Jetty repairs to the Masonboro Inlet located in New Hanover County, North Carolina (R4, tab 4.1 at 126, 132-133; Joint Statement of Stipulated Facts (JSSF) 1). 2 The Contract required placement of armor stone, each weighing from 14 to 22 tons, onto an existing jetty, insuring that the armor stone “form a compact mass and interlock with each other and the existing stones” (R4, tab 4.1 at 134, 298; JSSF 1).

Contract Specifications

2. The Contract included specifications for “Exterior Improvements,” Section 32 05 00.38, entitled “Stone.” Contained within that section was Part 1, “General,” Part 2, “Products,” and Part 3, “Execution.” (R4, tab 4.1 at 293; JSSF 2)

3. Part 1.1, entitled “Scope,” provided, “[t]he work under this section shall include all plant, labor, materials, work surface, and equipment required for the furnishing, transportation, storage, and placing of stone as shown on the drawings” (R4, tab 4.1 at 294; JSSF 3).

4. Part 2.1, entitled “Materials,” included Part 2.1.1, “Granite/Gneiss,” which provided, in part, “stone shall be furnished in random sizes ranging in weight as indicated in the subparagraph ‘Stone Size and Gradations’” (R4, tab 4.1 at 296).

5. Part 2.1.2, entitled “Armor Stone,” provided, in part:

Stone shall consist of fresh, sound, hard, dense, durable, crystalline igneous or metamorphic rock which shall be separated from bedrock by quarrying. The stone shall be of such quality that the individual stone integrity and permanence within the jetty is assured under all conditions to which it is subjected.

....

The stone shall be free from open or incipient cracks, joints, seams, fissures and structural planes of weakness which might contribute to spalling or breakdown from; handling and placing, freeze-thaw cycles, wet-dry cycles, or from wave action. The stone shall be furnished in blocky and angular shapes. Flat stones, tabular stones, slabs, boulders and parts of boulders will be rejected. No stone will be

2 The parties’ JSSF in large part mirrors the Statement of Facts set forth in our previous decision. Trade West I at 183,067-75. 2 permitted which has a longest dimension that is three times (3X) or greater, than its least dimension.

(R4, tab 4.1 at 296; JSSF 4)

6. Part 2.1.3, entitled “Stone Size and Gradations,” provided “[f]or the granite/granite gneiss armor stone, the specified weight range shall be 14.0 tons to 22.0 tons with 75% weighing more than 18.0 tons” (R4, tab 4.1 at 297; JSSF 5).

7. Part 2.1.4, entitled “Stone Sources,” provided:

The source(s) from which the Contractor proposes to obtain stone materials as required for these specifications shall be selected and identified to the Contracting Officer or his/her designated representative within 15 days of receipt of Notice to Proceed. This source(s) shall be inspected by a Corps of Engineers Geologist. The stone source(s) shall provide test results of ASTM D5312/D5312M and ASTM D5313/D5313M and records of successful use on similar projects. . . . The tests shall include; bulk specific gravity, saturated surface dry (SSD) unit weight, absorption (all three tests as per ASTM C127), abrasion, wetting and drying (ASTM D5313/D5313M), and freeze-thaw (ASTM D5312/D5312M). The results of the testing shall be submitted to the Contracting Officer or his/her designated representative for review and approval at least 30 days prior to being shipped to the construction site.

(R4, tab 4.1 at 297; JSSF 6) 3

8. Part 2.1.5, entitled “Stone Not Meeting The Specifications,” provided, in part:

If, during the progress of the work, it is found that the stone being furnished and/or placed by the Contractor does not meet all the requirements of the specifications, the Contractor shall furnish other stone of a quality acceptable

3 ASTM (American Society for Testing and Materials), now known as ASTM International, is a “standards organization that develops and publishes voluntary consensus technical standards for a wide range of materials, products, systems, and services.” Harry Pepper and Assoc., Inc., ASBCA No. 62038, et al., 21-1 BCA ¶ 37,760 at 183,306 n.2. 3 to the Contracting Officer or his/her designated representative. Any stone rejected at the site of work as not meeting the requirements of these specifications for quality, condition, size, or otherwise, shall be removed from the site by and at the expense of the Contractor.

(R4, tab 4.1 at 297; JSSF 7)

9. Part 3.2, entitled “Placement of Stone,” included Part 3.2.1, “General,” which provided:

Care shall be taken to place the stone so that they will form a compact mass, and form as nearly as practicable a cross-section of the height, width, and slopes as shown on the contract drawings. All stones shall be carefully placed so as to form a compact mass and to minimize the voids between them. Special care shall be taken during placement of stone to avoid damaging the existing sheetpile wall.

(R4, tab 4.1 at 298; JSSF 8)

10. Part 3.2.4, entitled “Armor Stone Placement,” provided:

Armor stone shall be placed in a single layer to achieve the design cross sections and top elevation, as shown on the drawings. Begin placement of the stone at the toe of the placement limits and work upslope to reduce the risk of stone rolling and launching. Dropping of stones onto the structure is strictly prohibited. Each armor stone shall be lowered to rest before being released and shall be placed to the satisfaction of the Contracting Officer or his/her representative. All stones shall be carefully placed so as to minimize the size of voids between them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Teg-Paradigm Environmental, Inc. v. United States
465 F.3d 1329 (Federal Circuit, 2006)
Hometown Financial, Inc. v. United States
409 F.3d 1360 (Federal Circuit, 2005)
Application of Lucien Victor Gewiss
435 F.2d 904 (Customs and Patent Appeals, 1971)
Newell Clothing Co. v. United States
818 F.2d 876 (Federal Circuit, 1987)
The Hunt Construction Group, Inc. v. United States
281 F.3d 1369 (Federal Circuit, 2002)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
McCormick-Selph v. United States
588 F.2d 808 (Court of Claims, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
Trade West Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/trade-west-construction-inc-asbca-2022.