Mega Construction Co. v. United States

39 Cont. Cas. Fed. 76,564, 29 Fed. Cl. 396, 1993 U.S. Claims LEXIS 137, 1993 WL 331439
CourtUnited States Court of Federal Claims
DecidedAugust 27, 1993
DocketNo. 645-87C
StatusPublished
Cited by107 cases

This text of 39 Cont. Cas. Fed. 76,564 (Mega Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mega Construction Co. v. United States, 39 Cont. Cas. Fed. 76,564, 29 Fed. Cl. 396, 1993 U.S. Claims LEXIS 137, 1993 WL 331439 (uscfc 1993).

Opinion

OPINION

MOODY R. TIDWELL, III, Judge:

On April 17, 1992, the court issued its initial opinion in this case, reported at 25 Cl.Ct. 735 (1992), concluding that plaintiff had failed to prove it had been improperly terminated for default. On April 29, 1992, plaintiff moved to amend or modify the opinion, or for reconsideration and/or a new trial. The motion was premised on arguments that the court had not found the facts or law to be to the liking of plaintiff; the court had failed to make separate findings of liability on each of plaintiff’s numerous claims; a case relied upon by the court, Al Johnson Constr. Co. v. United States, 854 F.2d 467 (Fed.Cir.1988), as applied was unconstitutional or at least distinguishable from the instant case in some unidentified way; and that the court’s conclusion that the termination for default was proper was not supported “by any substantial evidence” or was completely unsupported by any evidence.

The law governing motions for reconsideration is ably set out in Bishop v. United States:

It is well recognized that “[a] motion for reconsideration is addressed to the discretion of the trial court.” Triax Co. v. United States, 20 Cl.Ct. 507, 509 (1990) (citing Eyre v. McDonough Power Equip., 755 F.2d 416, 420 (5th Cir.1985) (construing FRCP 59)); see Yuba Natural Resources, Inc. v. United States, 904 F.2d 1577, 1583 (Fed.Cir.1990); Gelco Builders & Burjay Constr. Corp. v. United States, [177 Ct.Cl. 1025, 369 F.2d 992, 1000 n. 7 (1966) ]. Post-opinion motions to reconsider are not favored[.] General Elec. Co. v. United States, [189 Ct.Cl. 116, 416 F.2d 1320, 1321 (1969)]. It is well-settled that “[t]he court has a right to know before it decides [the controversy at hand] whether the parties have anything further to present.” [Id., 416 F.2d] at 1322.
Generally, “[a] motion under RUSCC 59 must be based upon manifest error of law, or mistake of fact, and is not intended to give an unhappy litigant an addi[405]*405tional chance to sway the court.” Circle K Corp. v. United States, 23 Cl.Ct. 659, 664-65 (1991). The movant must show either that an intervening change in the controlling law has occurred, evidence not previously available has become available, or that the motion is necessary to prevent manifest injustice. Weyer-haeuser Corp. v. Koppers Co., 771 F.Supp. 1406, 1419 (D.Md.1991). “Litigants should not, on a motion for reconsideration, be permitted to attempt an extensive retrial based on evidence which was manifestly available at [the] time of the hearing.” Gelco, [369 F.2d at 1000 n. 7], The litigation process rests on the assumption that both parties present their case once, to their best advantage.

Bishop v. United States, 26 Cl.Ct. 281, 285-86 (1992).

Plaintiff has not argued or presented any credible argument or evidence that any of the conditions cited in Weyerhaeuser Corp. are present here. However, to provide the parties with a basis upon which to determine quantum, the court will reissue its opinion to give a detailed discourse on the reasons why the termination for default was proper, and to fully address the delay and non-delay claims. Plaintiff provided no support for its contention that Al Johnson was unconstitutional or distinguishable, and the court can imagine of none: That argument need not be addressed. Plaintiff’s motion to amend or modify is granted; plaintiff’s motion for reconsideration and/or for a new trial is denied. The opinion of the court reported at 25 Cl.Ct. 735 (1992) is vacated. The modified opinion follows.

I. INTRODUCTION

On August 20, 1985, plaintiff, Mega Construction Company, Inc., entered into a fixed-price construction contract with defendant, through the United States Postal Service (U.S.P.S. or Postal Service), for the construction of the Main Post Office at Canoga Park, California. The contract price, as amended was $2,316,609.68. On September 9, 1985, defendant issued its Notice To Proceed, and on either September 17 or 23, 1985, plaintiff commenced work on the project.1 The contract originally contemplated completion of the project on October 20, 1986, but defendant administratively allowed several of plaintiff’s requested extensions of the completion date, adding a total of 118 days to the performance period. The amended completion date was February 15, 1987. In December 1986, after the discovery of cracks in the concrete floor of the main workroom of the postal service building, the contracting officer determined that the concrete floor slab failed to conform to contract specifications. The contracting officer directed plaintiff on several occasions to submit a plan to remove and replace the slab. Plaintiff refused to comply with the contracting officer’s directives, and on July 22, 1987 defendant terminated the contract for default based on plaintiff’s failure to comply with directives of the contracting officer, lack of job action, and abandonment. Both parties alleged incompetence and mismanagement of the project on the part of the opposing party. Plaintiff also alleged bad faith and malice on the part of defendant and several of its contracting officials. The case will not turn on a finding that one party or the other acted with the least malice or incompetence. Each party must prove its claims and the case will be disposed of in favor of the party who has provided the requisite degree of credible evidence. All facts are disputed.

II. PROCEDURAL HISTORY

Following the termination for default, plaintiff filed suit in this court on October 14, 1987, requesting a conversion of the termination for default to a termination for convenience of defendant. The complaint [406]*406was arguably defective at the time because it did not contain a monetary claim. On December 14, 1987, defendant filed a motion to dismiss the complaint on the grounds that the court lacked subject matter jurisdiction over the suit because (1) plaintiff filed suit before submitting a monetary claim to the contracting officer, and (2) the complaint did not seek monetary damages. However, on December 9, 1987 the contracting officer issued a final decision that assessed partial reprocurement costs. The sole issue before the court in December 1987 was the propriety of the termination for default and assessment of reprocurement costs. Oral argument on the motion to dismiss was heard February 19, 1988. The court held that a bare termination for default, unaccompanied by a monetary claim did not — at that time — constitute a basis for a claim cognizable before this court, Mega Constr. Co. v. United States, 14 Cl.Ct. 555, 557 (1988) (Mega I), but that once defendant made its monetary counterclaim, jurisdiction was perfected, bringing this case within the jurisdiction of the court. Id. at 557-58. The court held that it lacked jurisdiction at the time the complaint was filed.

In the interest of substantial justice this court concludes that plaintiffs earlier pleadings in response to defendant’s motion to dismiss brought the issues properly before this court. [RUSCC] 8(f). This is not a case in which the complaint would be statutorily time-barred or otherwise dismissed as untimely.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GSC Construction, Inc.
Armed Services Board of Contract Appeals, 2020
Harvey v. United States
Federal Claims, 2020
City Of Puyallup v. Conway Construction Company
Court of Appeals of Washington, 2020
Matcon Diamond, Inc.
Armed Services Board of Contract Appeals, 2020
Rustler Construction, Inc. v. District of Columbia
211 A.3d 187 (District of Columbia Court of Appeals, 2019)
Baker DC, LLC v. Baggette Constr., Inc.
378 F. Supp. 3d 399 (D. Maryland, 2019)
Solaria Corporation v. United States
123 Fed. Cl. 105 (Federal Claims, 2015)
Trust Title Company v. United States
118 Fed. Cl. 99 (Federal Claims, 2014)
Seven Resorts, Inc. v. United States
112 Fed. Cl. 745 (Federal Claims, 2013)
TRG Construction Inc. v. District of Columbia Water & Sewer Authority
70 A.3d 1164 (District of Columbia Court of Appeals, 2013)
K-Con Building Systems, Inc. v. United States
107 Fed. Cl. 571 (Federal Claims, 2012)
M.E.S., Inc. v. United States
104 Fed. Cl. 620 (Federal Claims, 2012)
Armour of America v. United States
96 Fed. Cl. 726 (Federal Claims, 2011)
ADP Marshall, Inc. v. NORESCO, LLC
710 F. Supp. 2d 197 (D. Rhode Island, 2010)
Wayne Knorr, Inc. v. Department of Transportation
973 A.2d 1061 (Commonwealth Court of Pennsylvania, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
39 Cont. Cas. Fed. 76,564, 29 Fed. Cl. 396, 1993 U.S. Claims LEXIS 137, 1993 WL 331439, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mega-construction-co-v-united-states-uscfc-1993.