City Of Puyallup v. Conway Construction Company

Court of Appeals of Washington·Decided May 4, 2020·No. 80649-1·Published

Opinion

IN THE COURT OF APPEALS FOR THE STATE OF WASHINGTON

CONWAY CONSTRUCTION No. 80649-1-I COMPANY, DIVISION ONE

Respondent,

PUBLISHED OPINION

v.

CITY OF PUYALLUP, Appellant.

LEACH, J. — In this public works contract case, the City of Puyallup (the City)

appeals a trial court decision finding that it improperly terminated Conway Construction Company’s (Conway) contract for road improvements and awarding Conway damages plus attorney fees and costs. Substantial evidence supports the trial court’s findings of fact and they support its legal conclusions. But, Conway was not entitled to recover attorney fees because it did not submit an offer of settlement as required by statute. So, we affirm the trial court’s judgment for damages but reverse its award of attorney fees to Conway.

FACTS

The City and Conway contracted for road improvements (the project). The public works contract included a “Public Works Contract” form and incorporated by reference several voluminous documents, including the Washington State Department of Transportation Standard Specifications for Road, Bridge, and Municipal Construction.

Citations and pincites are based on the Westlaw online version of the cited material.

During construction, the City became concerned about the quality of pavement concrete, defects in utilities, and other construction defects, and issued notices to Conway describing these concerns. The City also observed unsafe work conditions, such as lack of trench shoring, and reported those concerns to the Washington State Department of Labor & Industries (L&I).

On March 9, 2016, the City gave Conway a notice of suspension and breach of contract.1 This notice identified nine items that it deemed contract breaches. These included defective and uncorrected work and safety concerns. It advised Conway that it had 15 days to remedy the listed issues. Conway denied any wrongdoing.

On March 21, 2016, the City informed Conway that it still needed to remedy the same nine items and that it had received further reports of safety violations. Conway again denied the safety violation allegations.

On March 25, 2016, the City issued a notice of termination for default to Conway.

The City also withheld payments due to Conway.

On April 23, 2016, L&I issued a citation to Conway for a “serious” safety violation endangering Conway workers.

Conway sued the City asking the court to declare termination for default improper and deemed it to be for public convenience. Conway later amended its request to include breach of contract and unjust enrichment claims. After a bench trial, the court found the City breached the contract when it terminated Conway. It awarded Conway damages,

1 This exhibit is dated March 9, 2015. This is an obvious scrivener’s error because it references a Non-Conformance Report dated March 3,2016 and the parties had not yet entered their contract on March 9, 2015. Exhibits 53, 58, and 59 contain similar dating errors.

attorney fees, and costs. The City appeals.

STANDARD OF REVIEW

We review a party’s challenge to a trial court’s decision when the trial court has evaluated the evidence to determine whether substantial evidence supports the trial court’s findings of fact and whether those findings support the court’s conclusions of law. 2 Substantial evidence is evidence sufficient to persuade a fair-minded person of its truth. 3 Evidence may be substantial even if there are other reasonable interpretations of the evidence.4 We defer to the trial court’s determinations about persuasiveness of the evidence, witness credibility, and conflicting testimony. 5 We will not disturb a trial court’s ruling if substantial, though conflicting, evidence supports its findings of fact.6 ANALYSIS

The City raises three issues on appeal. First, it claims the trial court used the wrong test to determine if the City properly terminated the project contract for default. Next, it claims the contract entitles it to an offset for Conway’s defective work. Finally, it contends Conway is not entitled to recover attorney fees because it did not make a statutorily required offer of settlement. We agree that Conway is not entitled to recover attorney fees, but we reject the City’s other claims.

2 Standing Rock Homeowners Ass’n v. Misich, 106 Wn. App. 231, 242-43, 23 P.3d 520 (2001). 3 Hegwine v. Longview Fibre Co., Inc., 132 Wn. App. 546, 555-56, 132 P.3d 789 (2006). 4 Sherrell v. Selfors, 73 Wn. App. 596, 600-01, 871 P.2d 168 (1994). 5 Snyder v. Haynes, 152 Wn. App. 774, 779, 217 P.3d 787 (2009). 6 Merriman v. Cokeley, 168 Wn.2d 627, 631, 230 P.3d 162 (2010).

Contract Termination – Breach of Contract Standard for Termination We first address the City’s claim that the trial court did not use the correct test to decide whether the City properly terminated Conway for default. The City contends the trial court should have used the following two part test (1) was Conway in default, and (2) was the City satisfied with Conway’s efforts to remedy the breach. Conway claims the City had to satisfy a different two part test (1) was Conway in default, and (2) did Conway neglect or refuse to correct rejected work. Conway also asserts that any error the trial court made in applying the correct test was harmless.

The City correctly notes the parties’ contract form contains two termination provisions. First, paragraph 22 of the contract provides that violation of a statute or regulation is “good cause” for terminating the contract:

22. Termination. The City shall be entitled to terminate this Contract for good cause. “Good cause” shall include, but shall not be limited to, any one or more of the following events:

d. Contractor’s failure to comply with Federal, state or local laws, rules or regulations

Second, the contract incorporates the Washington State Department of Transportation (“WSDOT”) Standard Specifications for Road, Bridge, and Municipal Construction (2014), which provided the general terms of the contract. Section 1-08.10(1) of these specifications contains terms relating to termination of the contract and allows the contracting agency to terminate the contract upon the occurrence of any one or more of the following events:

1. If the Contractor fails to supply sufficient skilled workers or suitable materials or equipment;

2. [Inapplicable]
3. [Inapplicable]

4. If the Contractor disregards laws, ordinances, rules, codes, regulations, orders or similar requirements of any public entity having jurisdiction;

5. If the Contractor disregards the authority of the Contracting Agency;

6. If the Contractor performs Work which deviates from the Contract, and neglects or refuses to correct the rejected Work; or

7. If the Contractor otherwise violates in any material way any provisions or requirements of the Contract.

Once the Contracting Agency determines that sufficient cause exists to terminate the Contract, written notice shall be given to the Contractor and its Surety indicating that the Contractor is in breach of the Contract and that the Contractor is to remedy the breach within 15 calendar days after the notice is sent.... If the remedy does not take place to the satisfaction of the Contracting Agency, the Engineer may, by serving written notice to the Contractor and Surety either:

1. Transfer the performance of the Work from the Contractor to the Surety;

or

Free access — add to your briefcase to read the full text and ask questions with AI

City Of Puyallup v. Conway Construction Company, (Wash. Ct. App. 2020).

City Of Puyallup v. Conway Construction Company (City Of Puyallup v. Conway Construction Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)
Hertz v. Riebe
936 P.2d 24 (Court of Appeals of Washington, 1997)
Sherrell v. Selfors
871 P.2d 168 (Court of Appeals of Washington, 1994)
Ducolon Mechanical, Inc. v. Shinstine/Forness, Inc.
893 P.2d 1127 (Court of Appeals of Washington, 1995)
Hearst Communications v. Seattle Times Co.
115 P.3d 262 (Washington Supreme Court, 2005)
Ethridge v. Hwang
20 P.3d 958 (Court of Appeals of Washington, 2001)
Merriman v. Cokeley
230 P.3d 162 (Washington Supreme Court, 2010)
Hegwine v. Longview Fibre Co., Inc.
132 P.3d 789 (Court of Appeals of Washington, 2006)
Snyder v. Haynes
217 P.3d 787 (Court of Appeals of Washington, 2009)
Terry Martin v. Stanley Smith
368 P.3d 227 (Court of Appeals of Washington, 2016)
Bryan Kelley And Dorre Don Llc v. Beverly L. Tonda
393 P.3d 824 (Court of Appeals of Washington, 2017)
Hearst Communications, Inc. v. Seattle Times Co.
154 Wash. 2d 493 (Washington Supreme Court, 2005)
Merriman v. Cokeley
168 Wash. 2d 627 (Washington Supreme Court, 2010)
Ethridge v. Hwang
20 P.3d 958 (Court of Appeals of Washington, 2001)
Standing Rock Homeowners Ass'n v. Misich
23 P.3d 520 (Court of Appeals of Washington, 2001)
Hegwine v. Longview Fibre Co.
132 Wash. App. 546 (Court of Appeals of Washington, 2006)
Snyder v. Haynes
152 Wash. App. 774 (Court of Appeals of Washington, 2009)
Filipino American League v. Carino
332 P.3d 1150 (Court of Appeals of Washington, 2014)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Shelter Products, Inc. v. Steelwood Construction, Inc.
307 P.3d 449 (Court of Appeals of Oregon, 2013)