Ducolon Mechanical, Inc. v. Shinstine/Forness, Inc.

893 P.2d 1127, 77 Wash. App. 707
CourtCourt of Appeals of Washington
DecidedMay 1, 1995
Docket16335-7-II
StatusPublished
Cited by12 cases

This text of 893 P.2d 1127 (Ducolon Mechanical, Inc. v. Shinstine/Forness, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ducolon Mechanical, Inc. v. Shinstine/Forness, Inc., 893 P.2d 1127, 77 Wash. App. 707 (Wash. Ct. App. 1995).

Opinion

Bridgewater, J.

Ducolon Mechanical, Inc. (Ducolon), a subcontractor, appeals the trial court’s order awarding it $3,136.66 as a result of the wrongful termination of a construction subcontract by Shinstine/Forness, Inc. (Shin-stine), a general contractor. Ducolon also appeals the trial court’s finding that it exercised bad faith in the performance of the subcontract. Ducolon admits, however, that it breached the subcontract. Shinstine cross-appeals the trial court’s order denying it actual attorney’s fees incurred after it submitted a CR 68 offer of judgment. We affirm.

In 1988, the Corporation of the Presiding Bishop, the Church of Jesus Christ of Latter Day Saints (LDS) awarded a contract to Shinstine for the construction of a church facility in Puyallup, Washington. Construction was to commence on January 16,1989, and be completed by October 23, 1989.

Ducolon bid for the plumbing and the heating, ventilating and air conditioning (HVAC) portions of the project. Shin-stine advised Ducolon that it may have made a mistake in *709 the calculation of its bid because its bid of $119,245 was substantially lower than all others. Ducolon reviewed its bid and informed Shinstine that its bid was correct. Shin-stine advised Ducolon for a second time that its bid was substantially lower than all other bids. Without reviewing its bid calculation, Ducolon increased it by approximately 10 percent. Shinstine accepted Ducolon’s bid after Shin-stine obtained a performance bond for Ducolon. The subcontract provided for attorney’s fees and costs to the prevailing party in the event of litigation.

Ducolon commenced work at the site in March 1989. By December 1989, Ducolon was well behind schedule. Shin-stine extended Ducolon’s completion deadline. Shinstine terminated the subcontract after inspecting the project and finding that Ducolon’s work was both defective and behind schedule. Shinstine replaced Ducolon with Air Systems Engineering. Air Systems completed Ducolon’s work for $16,268. Half of that amount was attributable to completion of Ducolon’s work and the other half to correcting Ducolon’s work. The building was substantially completed 30 days behind schedule.

Ducolon filed a materialmen’s lien foreclosure action pursuant to RCW 60.04 and a suit for wrongful termination of its subcontract against Shinstine and LDS. Shinstine and LDS counterclaimed, alleging breach of contract. Shinstine and LDS made a CR 68 offer of judgment for $17,500 that was not responded to by Ducolon. The case proceeded to a bench trial in Pierce County.

Shinstine argued that Ducolon could not recover an amount in excess of the original contract price of $127,377. Ducolon argued that it was entitled to recover its actual cost of performance (alleged to be $180,073) less progress payments of $89,746 made by Shinstine. Ducolon attributed the difference between the original contract price and its actual costs to a $50,000 bid error. During trial, Ducolon stated that it had not recognized the bid error when Shinstine brought the possibility of a bid error to its attention during the bid process.

*710 In support of its argument, Ducolon offered a "Claim Breakdown” sheet prepared by its accountant, showing actual costs (direct, overhead, and profit) of $180,073. The accountant who prepared the form and a Ducolon consultant testified that Ducolon actually incurred $180,073 in costs. The only testimony as to the value of the work to the owner or Shinstine was that of Douglas Shinstine. He testified that the value of the work was equal to the contract price. The trial court entered no finding of fact as to actual costs incurred by Ducolon.

The trial court found that Shinstine wrongfully terminated the subcontract because its notice of termination was defective. It also found that Ducolon materially breached the contract by delaying the completion of the project by about 30 days. Further, it found that Ducolon failed to exercise good faith in performing the contract and by bidding the project too low, despite having been advised by Shinstine that its bid was low.

The trial court calculated Ducolon’s award on the basis of Restatement (Second) of Contracts § 374(1) (1981). Section 374(1) states that "the party in breach is entitled to restitution for any benefit that he has conferred by way of part performance or reliance in excess of the loss that he has caused by his own breach”. Thus, the trial court subtracted progress payments and the cost to complete and repair Du-colon’s work from the original subcontract price of $127,377, arriving at $3,136.66 instead of the $90,326 requested by Du-colon. No award of actual attorney’s fees and costs was made, the court ruling that neither party had prevailed. However, the court awarded Shinstine statutory costs of $197 and statutory attorney’s fees of $125 under RCW 4.84.080 because Ducolon did not improve its position by going to trial. Shinstine paid $3,136.66 and the court also dissolved Ducolon’s lien, finding the lien had been satisfied. Following entry of judgment, Ducolon commenced this appeal and Shinstine and LDS cross-appealed.

I

Ducolon argues that the trial court erred in measuring its award. In particular, Ducolon argues that if it could avail *711 itself of equitable relief in the form of restitution, it would be entitled to recover the actual amount of money it spent in partially performing the contract.

The trial court awarded Ducolon restitution on the basis of Restatement (Second) of Contracts § 374(1) (1981). Although Washington courts generally characterize restitution and quantum meruit as "equitable form[s] of recovery”, CKP, Inc. v. GRS Constr. Co. 63 Wn. App. 601, 615, 821 P.2d 63 (1991), review denied, 120 Wn.2d 1010 (1992), quantum meruit and restitution under Restatement § 374 are legal remedies. See 5 Arthur L. Corbin, Contracts § 1102 (1964); 1 Dan B. Dobbs, Remedies § 4.1(2) (2d ed. 1993). 1

In this case, the legal remedy is adequate because Restatement § 374(1) permits Ducolon to recover an amount equal to its alleged actual costs if its actual costs are equal to the benefit it conferred to Shinstine. 2 Therefore, the only issue related to the measure of Ducolon’s award we need address is whether the trial court erred in finding that Ducolon was entitled to recover the reasonable value of its services to Shinstine, as measured by the original contract price less Shinstine’s cost to complete and repair. We find no error.

A

In Washington, a defaulting subcontractor is entitled to restitution of its part performance measured by the reasonable value of its services to the general contractor. See Fuller v. Rosinski, 79 Wn.2d 719, 723, 488 P.2d 1061

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conway Constr. Co. v. City of Puyallup
490 P.3d 221 (Washington Supreme Court, 2021)
City Of Puyallup v. Conway Construction Company
Court of Appeals of Washington, 2020
Robert Repin v. State of Washington and Washington State University
392 P.3d 1174 (Court of Appeals of Washington, 2017)
Eker Bros. Inc. v. Rehders
2011 NMCA 092 (New Mexico Court of Appeals, 2011)
RWR Management, Inc. v. Citizens Realty Co.
135 P.3d 955 (Court of Appeals of Washington, 2006)
Bort v. Parker
42 P.3d 980 (Court of Appeals of Washington, 2002)
Eagle Point Condominium Owners Ass'n v. Coy
9 P.3d 898 (Court of Appeals of Washington, 2000)
Auburn Mechanical, Inc. v. Lydig Construction, Inc.
951 P.2d 311 (Court of Appeals of Washington, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
893 P.2d 1127, 77 Wash. App. 707, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ducolon-mechanical-inc-v-shinstineforness-inc-washctapp-1995.