Burton v. Ascol

715 P.2d 110, 105 Wash. 2d 344, 1986 Wash. LEXIS 1074
CourtWashington Supreme Court
DecidedMarch 6, 1986
Docket51818-1
StatusPublished
Cited by23 cases

This text of 715 P.2d 110 (Burton v. Ascol) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burton v. Ascol, 715 P.2d 110, 105 Wash. 2d 344, 1986 Wash. LEXIS 1074 (Wash. 1986).

Opinion

Durham, J.

Marion D. Burton, a general contractor, brought a lien foreclosure action against Richard B. Ascol for work performed by Burton. Ascol counterclaimed against Burton, alleging negligent workmanship, breach of contract, and violations of the Consumer Protection Act, RCW 19.86. Ascol also filed a claim against Allied Fidelity Insurance Company, Burton's surety. The trial court entered a judgment for Ascol. In this appeal, Burton and Allied Fidelity contend the trial court erred by applying the Consumer Protection Act and awarding Ascol costs and attorney fees pursuant to the mechanics' and materialmen's lien foreclosure statute, RCW 60.04. Burton and Allied Fidelity also raise a number of issues concerning the trial court's award of damages and attorney fees pursuant to the Consumer Protection Act. Allied Fidelity further contends that the trial court lacked jurisdiction because Allied Fidelity never consented to have the case heard by a judge pro tempore pursuant to RCW 2.08.180 and the state constitution, article 4, section 7, and that the judgment against it is void for lack of notice. We hold that the trial court erred in applying the Consumer Protection Act and in awarding Ascol costs and fees pursuant to RCW 60.04. We also hold that the trial court did have jurisdiction and the judgment *346 against Allied Fidelity is not void for lack of notice. Because we conclude that the Consumer Protection Act does not apply, we need not address the issues concerning damages and fee awards under the act.

On November 5, 1982, Burton and Ascol entered into a contract for the purpose of constructing an addition to a building owned by Ascol. The contract provided that Ascol would pay Burton $31,976 to build the addition. Burton impliedly warranted that the addition would be constructed in a good and workmanlike manner. Burton and Ascol discussed the fact that the building would be constructed according to code. Burton began construction before the engineering plans were approved or certified by the Building Department. He completed the project on approximately January 10, 1983, and was paid the $31,976 provided for in the contract. Three days later, Ascol received a bill for extras from Burton in the amount of $4,872. On February 2, 1983, Burton filed a lien against Ascol for the extras.

In March 1983, Burton brought an action to foreclose the lien in Spokane County Superior Court. Ascol denied that he owed the amount claimed for extras and filed a counterclaim alleging damages for negligent workmanship, breach of contract for failure to construct the building in a workmanlike manner, and violations of the Consumer Protection Act. Ascol also brought a claim against Allied Fidelity, which had issued Burton a bond in the amount of $4,000, to recover the amount of that bond.

The cause of action came to trial on December 13, 1983, before the Honorable B. J. McLean, sitting as judge pro tempore. That day, the attorneys for Burton and Ascol signed a stipulation consenting to the judge pro tempore. At the beginning of the trial, Allied Fidelity's attorney, Patrick Downey, appeared in court and stated that he saw no reason to participate in the trial himself because Burton was actively defending the counterclaim. Downey asked the court if he could simply read into the record the dates of the contractor's bond. Counsel for Ascol requested that a *347 copy of the bond be admitted and the other counsel and the court agreed. The bond was stipulated into the record and Downey then asked the court to excuse him from the proceedings. Counsel for Burton and Ascol stated they had no objection to this and the court excused Downey for the remainder of the trial.

Testimony was then heard about the items of work for which Burton charged Ascol as extras. Both Burton and Ascol testified as to which work was covered by the contract and how the work charged as extras was performed. Ascol also testified that defects arose after the job was done and final payment was made. Specific problems about which he testified included damage to the roof and the interior of his existing building, leaks in the roof drain and rain gutters, improper installation of a door and a conduit, missing air vents, loosening outside walls, and defects in an extension to a loading ramp.

Ascol presented Robert Sackmaster as a witness. Sack-master testified about agreements into which he had entered with Burton in 1981 and 1982. Burton agreed to perform a number of remodeling projects in Sackmaster's home and to build him a garage. Sackmaster testified that the quality of the materials and workmanship in the remodeling projects was defective. He stated that bookshelves had warped, cabinet doors had shrunk, electrical wiring was not new, and areas were not properly stained. Regarding the garage, Sackmaster testified that support beams were not mounted as agreed, electrical outlets were left uncovered, pegboard was patched and warped, the floor was poured so that water could not drain from the driveway, and rain gutters leaked. Sackmaster also testified that Burton had stated that the work and materials would be of a good quality, that the job would be finished in a workmanlike manner, and that Burton's work did not conform to plans Sackmaster had made.

In its findings of fact, the trial court listed specific aspects of the project which it found were defective, missing, or negligently performed. It also stated which items of *348 work were extras and determined the reasonable charges for the extras. It also found that the quality of Burton's work was "questionable". It found that a number of Burton's acts and practices were "subject to repetition" and had the "capacity to deceive a substantial portion of the purchasing public." These included the failure to perform work in a workmanlike manner, defective workmanship, negligent workmanship, representing to Ascol that the structure was built in conformance with engineering plans, failing to pay for materials as purchased, and using a person not licensed as an electrician to do electrical work.

The court found that Ascol sustained actual damages resulting from Burton's defective workmanship, breach of contract and misrepresentation in the amount of $5,000. It then assessed treble damages for violation of the Consumer Protection Act, bringing Ascol's total damages to $15,000. The court offset from this total the $4,680.95 which it found Burton should receive for extras. This resulted in a judgment for Ascol of $10,319.05. In addition, the court found that Ascol was entitled to attorney fees of $9,092.27 and costs of $282.15 pursuant to the Consumer Protection Act, and in the alternative found Ascol could recover attorney fees and costs pursuant to RCW 60.04.210(7) for Burton's unjust lien or as the prevailing party pursuant to RCW 60.04.130.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eight Is Enough, Llc, V. Cynthia Ohlig
Court of Appeals of Washington, 2024
Stephen Kerr Eugster v. Paula C. Littlewood
Court of Appeals of Washington, 2020
In re the Guardianship of: Judith Diane Holcomb
Court of Appeals of Washington, 2018
Donald R. Earl v. XYZPrinting, Inc.
Court of Appeals of Washington, 2016
In Re The Parentage Of H.a.a., A.k.a. And B.m.a.
Court of Appeals of Washington, 2014
Jeffrey Chen v. City Of Medina
Court of Appeals of Washington, 2014
McNeil v. Powers
97 P.3d 760 (Court of Appeals of Washington, 2004)
Ducolon Mechanical, Inc. v. Shinstine/Forness, Inc.
893 P.2d 1127 (Court of Appeals of Washington, 1995)
Zachman v. Whirlpool Financial Corp.
869 P.2d 1078 (Washington Supreme Court, 1994)
State v. Robinson
825 P.2d 738 (Court of Appeals of Washington, 1992)
State v. Belgarde
815 P.2d 812 (Court of Appeals of Washington, 1991)
Mitchell v. Kitsap County
797 P.2d 516 (Court of Appeals of Washington, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
715 P.2d 110, 105 Wash. 2d 344, 1986 Wash. LEXIS 1074, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burton-v-ascol-wash-1986.