Eastlake Construction Co. v. Hess

686 P.2d 465, 102 Wash. 2d 30
CourtWashington Supreme Court
DecidedJune 21, 1984
Docket49191-7
StatusPublished
Cited by93 cases

This text of 686 P.2d 465 (Eastlake Construction Co. v. Hess) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eastlake Construction Co. v. Hess, 686 P.2d 465, 102 Wash. 2d 30 (Wash. 1984).

Opinions

Pearson, J.

Both parties to a construction contract appeal the Court of Appeals decision which increased the trial court's award of damages and affirmed the dismissal of an action under the Consumer Protection Act.

Two substantial issues are presented in this appeal. The first requires us to determine the proper measure of the owners' damages for breach of a construction contract resulting in both remediable and irremediable defects in the structure. We hold that the appropriate formulation of damages is that set forth in Restatement (Second) of Contracts § 348 (1981). Accordingly, we affirm several items of damages awarded, but remand for the trial court to apply section 348 to certain other claimed items of damages which were not allowed at trial.

The second issue is whether the trial court and Court of Appeals were correct in ruling that the inducement element of the "public interest" requirement of the Consumer Protection Act, RCW 19.86, was not met in this case. We reverse on this issue and remand for a determination of whether the "inducement" and "potential for repetition" [33]*33elements of the public interest requirement were satisfied. The remaining issues raised by Eastlake are patently without merit and will not be addressed in this opinion.

Plaintiff Eastlake Construction Company (Eastlake) brought this action in King County Superior Court to recover $13,719 allegedly owing on a construction contract. Eastlake had entered the contract with defendants LeRoy and Jean Hess to erect a 5-unit condominium building in Issaquah. Defendants counterclaimed, alleging damages for breach of the contract and violations of the Consumer Protection Act. The trial court awarded defendants damages for breach of contract, less the amount owing to Eastlake under the contract, and dismissed the Consumer Protection Act action.

Defendants are the parents of a mentally retarded 25-year-old woman. They agreed with the parents of other retarded children to build a small condominium to provide a permanent home for their children. Mr. Hess assumed responsibility for the project and located a suitable piece of property at 245 Northwest Juniper in Issaquah. The property was owned by William Carey, a social friend of defendants and a principal in Eastlake Construction Company. Carey agreed to sell the land to defendants on condition that Eastlake was awarded the contract to construct the condominiums. Plans and specifications were drawn up by Mr. J. C. Smith, an architect hired by Hess, and East-lake submitted a price of $118,600 to construct the building in accordance with these plans and specifications. On June 27, 1977, a "Lump Sum Construction Contract" incorporating these terms was signed by defendants as owners and by Mr. Kenneth Kemp on behalf of Eastlake. The contract provided that work was to begin within 10 days and the condominium to be substantially completed within 90 working days from the start. It provided further that East-lake was to be paid as work progressed, with 10 percent of the contract price to be withheld until 30 days after acceptance of the construction by the owner.

Construction began in June and progressed smoothly [34]*34until October. Progress payments were made to Eastlake on August 9, 1977 ($25,000); September 9, 1977 ($34,300); and October 10, 1977 ($28,880). After the October payment had been made, work ceased for 3 weeks, putting the project behind schedule. Hess subsequently determined that East-lake had been overpaid for the work completed up to that point, and decided to withhold the November progress payment of $16,380. Eastlake refused to do any further work on the project until it received the additional progress payment, and construction ceased completely.

The dispute continued until January, when, according to Hess's testimony, Carey informed him that the project was completed and that Eastlake intended to sue if not paid the balance owing on the contract. On January 14, 1978, at Hess's request, the architect, Smith, inspected the project and issued a written report. The report detailed work still to be completed, work to be corrected, and work not in compliance with the specifications. On January 25, 1978, Hess met with the principals of Eastlake. At this meeting, according to Hess, Eastlake agreed to complete construction by February 8, 1978, and Hess agreed as a sign of good faith to pay Eastlake a further $16,781 on the contract price. Subsequently, Hess paid Eastlake the agreed sum and Eastlake performed some further construction work. By the end of February, however, construction had not been completed to Hess's satisfaction.

Accordingly, Hess undertook to complete the construction himself, assisted by two carpenters. His itemized costs for completing the project total $7,979.80. A certificate of occupancy for the condominiums was issued by the City of Issaquah on May 31, 1978.

On July 14, 1978, Eastlake filed suit seeking $13,719 allegedly owing on the construction contract. Defendants counterclaimed, alleging that Eastlake had breached the contract and had violated the Consumer Protection Act.

The nonjury trial began on June 9, 1980. It was not disputed at trial that Eastlake had not been paid $13,719 of the contract price of $118,600. The principal factual dispute [35]*35centered around the nature and extent of Eastlake's breaches of the contract and the measure of damages for those breaches. The trial court heard considerable testimony that Eastlake had delayed completion of the project, had failed to complete the work contracted for, and had performed work and used materials not in accordance with the contract specifications. The trial court found that East-lake had breached the construction contract in a number of respects. These findings, and the damages allowed by the trial court, may be summarized as follows.

A. Breaches for which the trial court allowed damages.

1. Eastlake wrongfully abandoned the project in February 1978, and defendants were allowed the reasonable cost of completing construction to make the condominiums habitable, $7,979.80.

2. Defendants were allowed the reasonable rental value of the condominiums from the time construction should have been completed until the actual completion date, $4,262.50.

3. Defendants were allowed damages for the reasonable cost of work specified in the plans, but not completed by Eastlake: insulating waste pipes, $807.44; installing recirculating fans, $1,031.10.

4. Defendants were allowed damages for the reasonable cost of repairing and replacing work performed by Eastlake which did not conform to the specifications: repairing the roof, $4,414.01; replacing balcony guardrails, $1,580.76; repairing and replacing washer and dryer closets, $751.84; replacing nonvented kitchen hood fans, $926.53; and replacing interior doors, $787.22.

5. Defendants were also allowed $75 for installation of cable television and $200 for light fixture underrun.

6. Defendants were also allowed damages for the installation of kitchen cabinets not in accordance with contract specifications.

The court declined to award the cost of replacement of these cabinets because this would constitute unreasonable economic waste. Instead, the measure of damages was the difference between the value of the specified cabinets [36]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Richard Eggleston & Shannon Eggleston v. Asotin County
Court of Appeals of Washington, 2025
Russell v. WADOT Capital Inc
W.D. Washington, 2024
Patrick Pulido, V. Gregory Eaton
Court of Appeals of Washington, 2024
Marianne Montler v. Belfor USA Group, Inc.
Court of Appeals of Washington, 2023
Robert Akhtar And Gulnoor Akhtar, V. TTG, LLC
Court of Appeals of Washington, 2023
Robert Repin v. State of Washington and Washington State University
392 P.3d 1174 (Court of Appeals of Washington, 2017)
Microsoft Corporation v. Motorola Mobility
795 F.3d 1024 (Ninth Circuit, 2015)
Day Island Yacht Harbor, V General Construction Co
Court of Appeals of Washington, 2014
Nw Product, / X-res. v. Homax Products Inc., / X-app.
Court of Appeals of Washington, 2013
224 Westlake, LLC v. Engstrom Properties, LLC
281 P.3d 693 (Court of Appeals of Washington, 2012)
COLUMBIA PARK GOLF v. City of Kennewick
248 P.3d 1067 (Court of Appeals of Washington, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
686 P.2d 465, 102 Wash. 2d 30, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eastlake-construction-co-v-hess-wash-1984.