White v. Mitchell

213 P. 10, 123 Wash. 630, 1923 Wash. LEXIS 812
CourtWashington Supreme Court
DecidedFebruary 21, 1923
DocketNo. 17536
StatusPublished
Cited by38 cases

This text of 213 P. 10 (White v. Mitchell) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
White v. Mitchell, 213 P. 10, 123 Wash. 630, 1923 Wash. LEXIS 812 (Wash. 1923).

Opinion

Bridges, J.

The plaintiffs, who are sisters, owned a small tract of land near the town of Sumner, in this state, on which they desired to construct a dwelling. The defendants are experienced housebuilders, residing in the city of Tacoma. About the 1st of September, 1920, the plaintiffs entered into a contract with the defendants for the construction of such dwelling. This contract was partly in writing and partly oral. There were some drawings and some written specifications. The house was to be a two-story building, of a certain size and of a certain class of material, and the finishing of the building was to be of a designated kind, and, in general, the construction and finishing work were to be of the same general character as those in a certain dwelling in the city of Tacoma with which all the parties were acquainted. The house was to rest on a concrete foundation, allowing for a large basement. The contract price was somewhat less than $4,000, and payments were to be made in installments as the work progressed. About the last of the year 1920, the defendants considered the building completed and offered to turn it over to the plaintiffs. At that time all of the contract price had been paid [632]*632except some $400 or $500. The plaintiffs, believing that the house had not been constructed according to agreement, not only refused to pay the balance of the contract price, but brought suit for damages in the sum of $2,500. The court, who tried the case without a jury, allowed plaintiffs damages in the sum of $250, and gave judgment to the defendants for the balance of the contract price. The plaintiffs have appealed.

A reading of the testimony shows quite conclusively that the materials used in the construction of the house were such as the contract provided for, but it also shows that, when the respondents offered to turn the house over as completed, it had at least four material defects: First, there was some poor work which resulted in some of the windows and doors not being properly constructed, the septic tank not being in accordance with the agreement, and other minor defects, all of which, for a reasonably small sum, could be remedied; second, the southwest corner of the house was some three or four inches lower than the other portions; third, the lower floor of the house was generally uneven and materially out of level. This last condition was caused by the following circumstances: girders bearing a large portion of the weight of the house ran from each side thereof to the center and rested upon a post, the lower end of which rested upon a concrete slab placed in the bottom of the basement. During construction this slab broke, and thus let the girders sag. In an attempt to remedy this condition, the respondents jacked up the house as best they could, and built a new concrete block to replace the broken one. It was impossible, however, to remedy the matter entirely and make the flooring level, because at that time the roof was on the house, partitions had been built, and the plastering had been [633]*633done. Fourth; the hardwood floors and interior finish had become soft, raised, uneven and colored to a material extent.

It satisfactorily appears that, when the concrete was poured, the foundation walls were level, and that the sinking at the southwest corner was the result of soft, mushy soil at that point, caused, in at least some part, by the accumulation of water in the basement, and respondents contend they should not be held responsible for the sagging condition of the foundation. It also appears with reasonable satisfaction that, throughout the process of building, from six to sixteen inches of water stood in the basement, and that this condition so softened the earth as to cause the concrete block' upon which the girders rested to break and thus cause the floor to sag, and that respondents remedied this defect as best they could by jacking up the house and making a new concrete block. Respondents contend that they cannot be held responsible for the present condition caused by water in the basement, making the ground soft and mushy. .They also contend that the damage done to the finishing materials was solely because of dampness resulting from the great quantity of water constantly in the basement, and that they ought not to be held responsible for that condition.

On the contrary, the appellants contend that the respondents contracted to construct and turn over the house in a proper condition, and that, if the defects mentioned were caused by soft ground, or by the presence of water in the basement, such would not be any excuse.

From the findings made by the trial court, it is somewhat difficult to determine upon what theory he made the plaintiffs an allowance of $250. He finds that, [634]*634while the construction was going on, “certain waters impeded the work and there was then no way known of successfully taking the water from the basement; that they completed the structure, generally speaking, according to the plans and specifications, taking into consideration the obstacles encountered.” We can account for the judgment of the lower court only upon the theory that he concluded that the respondents were not, under the circumstances, responsible for any defects in the house except those.which could easily be repaired at small cost. The testimony makes it clear that the $250 allowed by the trial court would not, by any means, make the floor of the house level and repair the damage done to the interior finish because of the water standing in the basement.

There is nothing in the testimony to show that the soil was of such character as that it was impossible to put down a concrete wall which would not sink, nor is there anything to show that it was impossible to building the house without the presence of great quantities of water constantly standing in the basement. Undoubtedly, by their contract, the respondents impliedly, if not expressly, agreed to construct the house in a reasonably good and workmanlike manner. The mere fact that the ground was soft would not excuse them from the performance of their contract in a proper manner, unless it was of such character it would be impossible to construct a foundation upon it. For all that appears, a wider footing for the concrete basement would have prevented the foundation from sinking. The general rule is that a builder must substantially perform his contract according to its terms, and in the absence of contract governing the matter, he will be excused only by acts of God, impossibility of performance, or acts of the [635]*635other party to the contract preventing performance: If he wish to protect himself against the hazards of the soil, the weather, labor or other uncertain contingencies, he must do so by his contract.

In the case of Superintendent etc. of Public Schools of Trenton v. Bennett, 27 N. J. L. 513, 72 Am. Dec. 373, the court said:

“No rule of law is more firmly established by a long train of decisions than this: that where a party, by his own contract, creates a duty or charge upon himself, he is bound to make it good if he may, notwithstanding any accident by inevitable necessity, because he might have provided ag-ainst it by his contract, . . . . If a party, for sufficient consideration, agrees to erect and complete a building upon a particular spot, and find all the materials and do all the labor, he must erect and complete it, because he has agreed so to do. No matter what the expense, he must provide such a substruction as will sustained the building upon that spot until it is complete and delivered to the owner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lake Hills Invs., LLC v. Rushforth Constr. Co., Inc.
494 P.3d 410 (Washington Supreme Court, 2021)
Perception Construction Management, Inc. v. Bell
254 P.3d 1246 (Idaho Supreme Court, 2011)
Ervin Construction Co. v. Van Orden
874 P.2d 506 (Idaho Supreme Court, 1993)
George B. Gilmore Co. v. Garrett
582 So. 2d 387 (Mississippi Supreme Court, 1991)
Goff v. City of Airway Heights
730 P.2d 691 (Court of Appeals of Washington, 1986)
Eastlake Construction Co. v. Hess
686 P.2d 465 (Washington Supreme Court, 1984)
Precision Homes, Inc. v. Cooper
671 S.W.2d 924 (Court of Appeals of Texas, 1984)
Eastlake Construction Co. v. Hess
655 P.2d 1160 (Court of Appeals of Washington, 1982)
Turner, Collie & Braden, Inc. v. Brookhollow, Inc.
642 S.W.2d 160 (Texas Supreme Court, 1982)
Liner v. Armstrong Homes of Bremerton, Inc.
579 P.2d 367 (Court of Appeals of Washington, 1978)
Don L. Cooney, Inc. v. Star Iron & Steel Co.
528 P.2d 487 (Court of Appeals of Washington, 1974)
Fuller v. Rosinski
488 P.2d 1061 (Washington Supreme Court, 1971)
Swenson v. Lowe
486 P.2d 1120 (Court of Appeals of Washington, 1971)
Valley Construction Co. v. Lake Hills Sewer District
410 P.2d 796 (Washington Supreme Court, 1966)
Inwood Construction Co. v. Huntington Corp.
400 S.W.2d 372 (Court of Appeals of Texas, 1965)
Nelson v. Hazel
406 P.2d 138 (Idaho Supreme Court, 1965)
Ridley Investment Co. v. Croll
192 A.2d 925 (Superior Court of Delaware, 1963)
Ridley Investment Company v. Croll
192 A.2d 925 (Supreme Court of Delaware, 1963)
Odgers v. Held
362 P.2d 261 (Washington Supreme Court, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
213 P. 10, 123 Wash. 630, 1923 Wash. LEXIS 812, Counsel Stack Legal Research, https://law.counselstack.com/opinion/white-v-mitchell-wash-1923.