Liner v. Armstrong Homes of Bremerton, Inc.

579 P.2d 367, 19 Wash. App. 921, 1978 Wash. App. LEXIS 2189
CourtCourt of Appeals of Washington
DecidedMay 8, 1978
Docket2560-2
StatusPublished
Cited by18 cases

This text of 579 P.2d 367 (Liner v. Armstrong Homes of Bremerton, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Liner v. Armstrong Homes of Bremerton, Inc., 579 P.2d 367, 19 Wash. App. 921, 1978 Wash. App. LEXIS 2189 (Wash. Ct. App. 1978).

Opinion

*922 Soule, J.

This is an appeal from a judgment and an award of damages in favor of Armstrong Homes on its counterclaim.

On October 30, 1974, the parties involved entered into a written contract for the construction of a prefabricated home on property recently purchased by plaintiffs in Kitsap County. The purchase price of the home was $31,305.30. This total included both a salesman's commission of $1,179.04 and a 25 percent profit factor. The contract contained several provisions which imposed various obligations on the parties. Armstrong Homes, as the contractor, was required "To give all requisite notices to the proper authorities; obtain all official inspections, permits, certificates and licenses made necessary by the work in his charge."

The contract also stipulated "Power and water are to be provided by the owner prior to starting date."

Additionally, the contract was conditioned on the approval of the site by local health authorities, the building authorities and the owner's procurement of a loan, if necessary.

Prior to the October 30 agreement, the plaintiffs had contacted Sun Industries, Inc., a public water-source supplier which serviced an existing neighboring development known as Green Mountain. Plaintiffs learned that for an initial hook-up charge of $200 and $4 per month thereafter, their water needs would be satisfied.

On December 3, 1974, plaintiffs submitted a building site application to the county health officials. This application was a prerequisite in Kitsap County to obtaining a building permit. Its approval hinged on existence of an available and adequate water supply whose private or public nature must also be revealed. The plaintiffs' application was denied because their contemplated public water supply, Sun Industries, was not a state-approved water supply service. Plaintiffs immediately confronted Sun Industries with this disconcerting information and were assured that it planned *923 to update its system in April 1975 to meet state requirements.

On January 3, 1975, the plaintiffs reapplied, and on this occasion represented on the basis of information received from the prior owner that there was an independent private water supply on their property in the form of an existing well. At plaintiffs' direction, a drain field diagram was marked with an "X" designating the well's alleged location. Plaintiffs informed the health department officials that they thought the well was too shallow and its quality too low (impure) to be used permanently, but that its temporary use until Sun Industries attained state clearance, was practical and feasible. Based on these representations, the application was issued with the notation that the private supply, the well, would be utilized as temporary water until Sun Industries was approved.

On January 14, 1975, Metropolitan Federal Savings & Loan Association, the finance company which, through arrangements made by defendant, had earlier agreed to furnish plaintiffs a loan, questioned the adequacy of the property's water supply. It requested some assurance that there was a supply agreement between plaintiffs and Sun Industries. On January 15, 1975, plaintiffs furnished via one of defendant's salesmen, a statement from Sun Industries reflecting that it had been willing to supply water to one of the prior property owners and there was other evidence that such willingness was continuing.

On January 15, 1975, the building plans were finalized by the parties and plaintiffs made a $5,065 payment. On January 22, 1975, Metropolitan informed defendant that it could commence construction. Defendant then applied for a building permit. The submission of the previously approved building site application enabled and ensured the permit's issuance on January 28, 1975. This same day, defendant called the factory in Auburn, Washington, and ordered the framing of the house. On January 30, 1975, defendant was advised by Metropolitan that a water supply problem still persisted and that until the Sun Industries' supply was *924 state-approved or plaintiffs proved the existence of their well and that it would meet purity standards, no funds would be forthcoming. Defendant immediately contacted the factory and halted the construction. Defendant's evidence was that by this time, $6,276.22 in construction costs had been incurred along with $1,179.04 in salesman's commission.

After plaintiffs were told of this development by the defendant, they made no attempt to locate the alleged well and further refused to provide one and sought return of their $5,065 payment.

The special custom design of plaintiffs' home prevented defendant's complete recoupment of its expenditures on materials. After diligent efforts, defendant was able to resell only a portion of the cut materials at a price of $2,576.63. The remainder had no value.

The trial court found plaintiffs had breached the contract. Damages were fixed by cumulating the sales commission, the construction costs incurred to date of cessation and adding a 25 percent profit to the construction costs.

The gross total found by the court was $9,024.72. We will review the computations of credits to be allowed at a later point.

Plaintiffs' main contention on appeal is that the unavailability of Sun Industries as a water source excused their performance under the contractual doctrine of impossibility of performance. We find that impossibility was not established and also find that an independent ground justifies imposition of liability on plaintiffs.

In Washington, a false representation as to a material fact is actionable although made through an honest mistake. Such representations constitute constructive fraud despite the presence of good faith. Thompson v. Huston, 17 Wn.2d 457, 135 P.2d 834 (1943); Stanley v. Parsons, 156 Wash. 217, 286 P. 654 (1930); McDaniel v. Crabtree, 143 Wash. 168, 254 P. 1091 (1927); Pratt v. Thompson, 133 Wash. 218, 233 P. 637 (1925). It is evident that plaintiffs' representations regarding the presence of a well on their *925 property were made carelessly without knowledge as to their truth or falsity. These representations were the catalyst which triggered the approval of the building site application. This application in turn was explicitly relied upon by defendant in obtaining the building permit. The issuance of the building permit and defendant's subsequent commencement of construction are inextricably interwoven and are a product of plaintiffs' representations. Absent these representations, the building site application would have been denied, no building permit would have been issued and no construction would have begun.

Plaintiffs unquestionably knew of defendant's intent to use the application to acquire a building permit and to begin construction soon thereafter. In their anxious and expectant "new home" mood, plaintiffs desired such action. The evidence is clear that plaintiffs made material misrepresentations of fact which were relied upon by defendant to its detriment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fitness International, Llc, V. 135th & Aurora, Llc
Court of Appeals of Washington, 2024
Bob Spain Real Estate Services Inc. v. William T. Cox
Court of Appeals of Washington, 2015
Perez Trucking, Inc. v. Ryder Truck Rental, Inc.
886 P.2d 196 (Court of Appeals of Washington, 1994)
Washington State Hop Producers, Inc. v. Goschie Farms, Inc.
754 P.2d 139 (Court of Appeals of Washington, 1988)
Golsen v. ONG Western, Inc.
756 P.2d 1209 (Supreme Court of Oklahoma, 1988)
Martin v. City of Seattle
728 P.2d 1091 (Court of Appeals of Washington, 1986)
Thornton v. Interstate Securities Co.
666 P.2d 370 (Court of Appeals of Washington, 1983)
Carpenter v. Folkerts
627 P.2d 559 (Court of Appeals of Washington, 1981)
Dugan v. Jones
615 P.2d 1239 (Utah Supreme Court, 1980)
Weyerhaeuser Real Estate Co. v. Stoneway Concrete, Inc.
614 P.2d 249 (Court of Appeals of Washington, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
579 P.2d 367, 19 Wash. App. 921, 1978 Wash. App. LEXIS 2189, Counsel Stack Legal Research, https://law.counselstack.com/opinion/liner-v-armstrong-homes-of-bremerton-inc-washctapp-1978.