J. D. Harms, Inc. v. Meade

57 P.2d 1052, 186 Wash. 287, 1936 Wash. LEXIS 526
CourtWashington Supreme Court
DecidedMay 19, 1936
DocketNo. 25993. Department One.
StatusPublished
Cited by9 cases

This text of 57 P.2d 1052 (J. D. Harms, Inc. v. Meade) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. D. Harms, Inc. v. Meade, 57 P.2d 1052, 186 Wash. 287, 1936 Wash. LEXIS 526 (Wash. 1936).

Opinion

Mitchell, J.

J. D. Harms, Inc. (hereinafter spoken of as Harms) obtained a contract with the United States government for the building of a road in Rainier National Park. He sublet a portion of the work by written subcontract with Zora E. Meade, individually *288 and as executrix of the estate of John W. Meade, operating’ as Meade’s Transfer and Garage (hereinafter spoken of as Mrs. Meade). In the subcontract, Harms is called the contractor, and Mrs. Meade is spoken of as the subcontractor. Certain provisions of the subcontract, material to this case, are as follows:

“Whereas, the contractor has entered into a contract dated October 31, 1932, with the United States of America, hereinafter referred to as the U. S., for the .construction of a highway of approximately 2% miles, . . . ; and
“Whereas, the sub-contractor is desirous of entering into an agreement with the contractor for hauling all excavated materials;
“Now, Therefore, in consideration of the mutual covenants of the respective parties, it is agreed as follows : . . .
“(2) Duties of Sub-contractor: The sub-contractor agrees to do all the hauling from the excavations on the above job; to furnish sufficient trucks on duty at all times to handle the work (each truck having a minimum capacity of 6 yards); to pay for all labor and insurance of all kinds as specified by the contractor, furnish proof to contractor of such payments, and to give a bond in the sum of $6,000 in terms and form to be approved by the attorneys for the contractor.
“(3) Duties of Contractor: The contractor agrees to pay the sub-contractor for actual yardage hauled, at the rate of 8c per cu. yd. free haul .limit, and at the rate of %c per station yard, in addition, for overhaul.
“(4) Specific Supplies: It is agreed that the contractor will buy gas, oil, grease, tires and tubes for use by the sub-contractor, the cost of which shall be deducted each month from the payments to be made by the contractor to the sub-contractor.”

Both parties signed the contract and were acquainted with the location of the road.

Mrs. Meade commenced work under the contract, using trucks of the ordinary kind, until wet ground *289 was struck, then Linn and Dump tor trucks (crawling or caterpillar type) were used .for a few days, and then again the common kind was used a few days until taken off permanently by Mrs. Meade, who refused to go on with her contract. Harms thereafter completed the hauling, using trucks of the common kind, except for a few days on which he used the caterpillar kind of trucks.

Afterwards, this suit was brought by Harms against Mrs. Meade on two causes of action: (1) For the balance due in the sum of $1,056, on account of supplies, etc., furnished Mrs. Meade; and (2) for breach of the contract to remove all excavated materials. Upon issues joined, the case was tried without a jury. Findings, conclusions and judgment were entered in favor of the plaintiff. Defendant has appealed.

The first assignment is that the court erred in holding the contract between the parties to be bilateral. The argument is that it was lacking in mutuality, and that, therefore, the appellant cannot be held in damages for refusal to perform it.

The written contract, upon mentioning the fact that Harms has a contract with the United States for the construction of the highway, recites that:

“Whereas, the sub-contractor [Mrs. Meade] is desirous of entering into an agreement with the contractor [Harms] for hauling all excavated materials;
“Now, Therefore, in consideration of the mutual covenants of the respective parties, ...”

Mrs. Meade agrees to do all the hauling from the excavations on the job, to furnish sufficient trucks on duty at all times to handle the work, to pay all labor and insurance, and give a bond in the sum of six thousand dollars, etc., and, on the other side, Harms agrees to pay Mrs. Meade for the yardage hauled 8e per cu. yd., free haul limit, and at the rate of %c per *290 station yard, in addition, for overhaul. Mrs. Meade gave to Harms, as she agreed, a subcontractor’s bond, the amount of which was ascertained or fixed upon the basis of the total amount of all excavated materials to be hauled, as shown by the terms, estimates and profiles of the original contract with the United States.

Before and during the short period of time the appellant worked under the contract, the respondent, according to its promise in the contract, furnished a large quantity of supplies, etc., embraced in the first cause of action. Here was part performance on the part of each party to a contract specifically describing the total amount of work to be done.

But, independent of part performance, this contract, from the words employed, shows the intention of the parties. The subject matter is not in doubt, but clearly expressed. It is not the hauling of some or a part, but all, of the excavated materials in the construction of the highway, the plans, specifications and profiles of which the parties had before them in the government contract which was referred to in the contract between these parties. The contractor agreed to pay the specified amount for the yardage hauled, and Mrs. Meade agreed to do the hauling. It is a case o.f a written contract in which one party agrees to work and the other party agrees to pay — mutual covenants; a promise for a promise.

Appellant’s contention is, as we understand it, that the contract should have contained an additional specific provision that “Harms agrees to deliver the excavated material to be hauled by Mrs. Meade,” or words of similar import. How much plainer would that have made the contract? By undeniable implication, that is precisely what the contract means, taken altogether; so that, if resort need be had to this common method *291 of ascertaining the meaning of the contract, the result is the same.

In McCartney v. Glassford, 1 Wash. 579, 20 Pac. 423, Glassford agreed to freight certain produce to a certain point at so much per pound, and McCartney and others agreed to pay the freight charges at so much per pound. It was held that there was a corresponding obligation on the part of McCartney and others to furnish the produce for being carried, and that the contract was bilateral. In discussing this phase of the case, it was said:
“The real contention of the appellee, however, seems to be that the contract is wanting in mutuality, binding only the appellee to carry the freight, and not requiring appellant to furnish any; or, even if he is so required, that by the subsequent waiver of time, he is relieved from any time for performance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Liner v. Armstrong Homes of Bremerton, Inc.
579 P.2d 367 (Court of Appeals of Washington, 1978)
Warburton v. Tacoma School District No. 10
350 P.2d 161 (Washington Supreme Court, 1960)
Reeker v. Remour
244 P.2d 270 (Washington Supreme Court, 1952)
Westland Construction Co. v. Chris Berg, Inc.
215 P.2d 683 (Washington Supreme Court, 1950)
Byrne v. Bellingham Consolidated School District No. 301
108 P.2d 791 (Washington Supreme Court, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
57 P.2d 1052, 186 Wash. 287, 1936 Wash. LEXIS 526, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-d-harms-inc-v-meade-wash-1936.