Byrne v. Bellingham Consolidated School District No. 301

108 P.2d 791, 7 Wash. 2d 20
CourtWashington Supreme Court
DecidedJanuary 7, 1941
DocketNo. 28132.
StatusPublished
Cited by6 cases

This text of 108 P.2d 791 (Byrne v. Bellingham Consolidated School District No. 301) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Byrne v. Bellingham Consolidated School District No. 301, 108 P.2d 791, 7 Wash. 2d 20 (Wash. 1941).

Opinions

Steinert, J.

Plaintiff, an electrical contractor, brought this action to recover damages alleged to have been sustained by him and his assignor because of the delay to which they had been subjected during their performance of certain work connected with the construction of a school building. Trial before the court, without a jury, resulted in findings from which the court concluded that plaintiff was not entitled to recover. From a judgment of dismissal, plaintiff has appealed.

On or about October 14, 1936, the Henrikson-Alstrom Construction Company, hereinafter referred to as the general contractor, entered into a written contract with respondent, Bellingham Consolidated School District No. 301, Whatcom county, Washington, for the construction of a school building in the city of Belling-ham at an estimated cost of approximately eight hundred thousand dollars. At about the same time, W. A. Watts, doing business as Watts Electric Company, entered into a written contract with respondent *23 for the performance of certain electrical work upon, and in connection with the construction of, the building. It is that contract with which we are here primarily concerned. A third, contemporaneous contract was executed by and between respondent and Arthur J. Blyth for the performance by the latter of certain mechanical work upon the same building. An architect was employed by respondent as its agent to supervise and direct the entire construction. The school building was a Federal works project, which required that the work be done under the supervision and direction of the public works administration, and in the performance of which at least ninety per cent of the persons employed were to be taken from the public relief rolls.

Each of the three contracts provided, among other things, that the work contracted for was to be completed before June 1, 1937; that liquidated damages in the sum of fifty dollars was to be paid to respondent for each day that the work remained uncompleted after that date; that all time limits were of the essence of the particular contract; that the general contractor was to prepare a progress chart, and that all other contractors were to conform to the progress of the general contractor; that each contractor, including the general contractor, was to maintain on his work, during its progress, a competent superintendent, who was not to be changed except with the consent of the architect; that each contractor was to coordinate his work with that of the other contractors; that each contractor was to employ, so far as possible, such methods and means in carrying out his work as would not cause any interruption or interference with any other contractor; that the architect was authorized to withhold from each contractor any certificate of payment to the extent that might be necessary in order to protect respondent *24 from loss on account of damage to any other contractor; and that each contractor was to pay for any damage caused to another contractor, and, if such other contractor should sue respondent for such damage, the party at fault was to pay any judgment obtained against respondent.

The two principal provisions of the contract, in so far as this controversy is concerned, read as follows:

“Art. 18. Delays and Extension of Time. — If the Contractor be delayed at any time in the progress of the work by any act or neglect of the Owner [respondent] or the Architect, or of any employe of either, or by any other Contractor employed by the Owner, or by changes ordered in the work, or by strikes, lockouts, fire, unusual delay in transportation, unavoidable casualties or any causes beyond the Contractor’s control, or by delay authorized by the Architect pending arbitration, or by any cause which the Architect shall decide to justify the delay, then the time of completion shall be extended for such reasonable time as the architect may decide. . . .
“This article does not exclude the recovery of damages for delay by either party under other provisions in the contract documents.”
“Art. 31. Damages. — If either party to this Contract should suffer damage in any manner because of any wrongful act or neglect of the other party or of anyone employed by him, then he shall be reimbursed by the other party for such damage.
“Claims under this clause shall be made in writing to the party liable within a reasonable time at the first observance of such damage and not later than the time of final payment, except as expressly stipulated otherwise in the case of faulty work or materials, and shall be adjusted by agreement or arbitration.”

We shall hereinafter refer to these two series of provisions as article 18 and article 31, respectively.

As required by the contracts, Watts and the general contractor and Blyth, respectively, furnished perform- *25 anee bonds guaranteeing faithful performance of their particular work.

Watts began work under his contract in November, 1936, as soon as he was directed to do so by the architect, and was furnished with a progress schedule prepared by the general contractor providing for the completion of the building before June 1, 1937. Watts, in turn, also made up a progress schedule, which tied in the electrical work with that of the general contractor, and likewise provided for completion before June 1, 1937.

On January 18,1937, Watts executed to Harry Byrne, doing business as North Coast Electric Company, and hereinafter referred to as appellant, an assignment of Watts’ contract with respondent, together with all moneys forthcoming thereon. Appellant, it appears, was a wholesaler of electrical supplies who had guaranteed Watts’ bond to respondent and had also furnished all of the material and funds necessary to be used in performing that contract. After the assignment, appellant employed Watts to continue with, and complete, the electrical work in the building.

The assignment was approved, as provided for in the contract, by the state director of the public works administration on March 17, 1937. At that time, the work on Watts’ contract had been completed to the extent of only about 11.6%, and the work of the general contractor had been completed to the extent of only about 27.62%. The electrical work, of course, could not be done except in accordance with the progress of the work of the general contractor, nor could the electrical work be finished in all its details until the building itself was, for all practical purposes, completed. It is not disputed that, if the building had progressed to completion according to the general contract, appellant would likewise have been able to com- *26 píete the electrical work before June 1, 1937, as called for by Watts’ contract. However, the building was not completed until on or about April 15, 1938, which was ten and one-half months after the completion date specified in the general contract. As a consequence, the electrical work required eighteen months for its completion, instead of the maximum period of seven and one-half months provided for in Watts’ contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
W.D. Washington, 2026
In Re A.n.c
Court of Appeals of Washington, 2022
Estate Of Lois S. Carter v. Bryan D. Carden, Et Ux
455 P.3d 197 (Court of Appeals of Washington, 2019)
Dobson v. Rutgers, State University
384 A.2d 1121 (New Jersey Superior Court App Division, 1978)
Nelse Mortensen & Co. v. Group Health Cooperative
566 P.2d 560 (Court of Appeals of Washington, 1977)
City of Seattle v. Dyad Construction, Inc.
565 P.2d 423 (Court of Appeals of Washington, 1977)
Ericksen v. Edmonds School District No. 15
125 P.2d 275 (Washington Supreme Court, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
108 P.2d 791, 7 Wash. 2d 20, Counsel Stack Legal Research, https://law.counselstack.com/opinion/byrne-v-bellingham-consolidated-school-district-no-301-wash-1941.