Reichenbach v. Sage

43 P. 354, 13 Wash. 364, 1896 Wash. LEXIS 53
CourtWashington Supreme Court
DecidedJanuary 9, 1896
DocketNo. 1711
StatusPublished
Cited by21 cases

This text of 43 P. 354 (Reichenbach v. Sage) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reichenbach v. Sage, 43 P. 354, 13 Wash. 364, 1896 Wash. LEXIS 53 (Wash. 1896).

Opinion

The opinion of the court was delivered by

Dunbar, J.

On the 8th day of October, 1889, the respondent entered into a contract with the defendants Sage & Stratton whereby Sage & Stratton agreed to erect and complete a certain two-story residence with a stone basement in the city of Tacoma except the plumbing and the gas-fitting for the sum of $7,450. They contracted that the work should be commenced on or before October 30, 1889, and that the entire contract should be performed as rapidly as possible consistent with durability and safety and should be completed on or before February 10,1890, that in case of failure to complete the contract by February 10, 1890, they would pay as damages a sum equal to $10 for each and every day said work and contract was delayed beyond said date through any fault or negligence of Sage & Stratton. The building was not completed until August 28,1890, being a delay of 199 days, and plaintiff brings this action to recover $10 per day as stipulated damages. The trial of the case resulted in a verdict for the plaintiff in the sum of $1,160, judgment was rendered and an appeal taken from said judgment.

The main features of the answer were:

1st. That the delay was caused by the plaintiff and his architect in this, that on account of the unusual [366]*366cold and wet weather they stopped the plastering of said building and that the contractors were not allowed to plaster during the cold weather, and that by such orders they were delayed and hindered, without their fault or negligence, and that the plaintiff thereby contributed to and caused such delay.

2d. That the winter of 1889-90 was unusually and extraordinarily cold and wet, and that it was impossible to proceed with the ordinary work of building.

3d. That the delay was caused by the failure of plaintiffs to furnish the plumbing and gasfitting for the house, and that the delay of plaintiff in this regard contributed to and was the cause of the delay complained of.

4th. That they were unavoidably delayed in procuring mill work for the building.

5th. That they were delayed by the failure of the plaintiffs to furnish the mantels, hearths and tiles and the art glass for the building.

6th. That the plaintiffs failed to furnish the details of the mill work at a proper time, and that they were delayed on that account.

We think the question which should be logically first settled in this case is: Was the contract to pay the damages specified, a provision for a penalty or for liquidated damages? There has been some conflict of authority on this question, each case, however, necessarily being decided with reference to its own particular circumstances and the particular language of- the contract. We are satisfied, however, that the overwhelming weight of authority sustains the contention that this contract provides for liquidated damages; there is nothing inequitable in the terms of this provision; the amount does not seem to us to be excessive or unreasonable; it does not provide for the payment of [367]*367a sum in gross on the failure to comply with the contract at the expiration of the time limited, but the damages accrue according to the length of" time the breach continues; and again, there is an element of uncertainty as to the real damages which would be maintained by the plaintiff which renders it more or less impracticable to be determined by a jury. Values of rents are fluctuating, and dwelling houses of the character and description of this one are ordinarily not built for rent at all, but for the convenience and comfort of the owners, and inasmuch as the parties saw fit to settle in advance the question of damages, and it seems to be on an equitable basis, we do not feel justified in disturbing that contract and holding that it was a contract which the parties had no right to make.

In Texas, etc., Ry. Co. v. Rust, 19 Fed. 239, it was held that—

“A provision in a contract to build a railroad bridge that, in case of non-completion of the bridge or providing a crossing for trains by a given date, the sum of $1,000.00 per week should be deducted from the contract price of the bridge for the time its completion or provision for crossing trains is delayed beyond that date, is a stipulation for liquidated damages.”

In Cotheal v. Talmage, 9 N. Y. 551 (61 Am. Dec. 716), it was held that—

“Where the damages resulting from the breach of an agreement are in their nature entirely indefinite and uncertain, and the parties have mentioned a specific sum as liquidated damages, such sum will be regarded as damages, and not as a penalty, unless the amount be greatly disproportioned to any probable estimate of the actual damages.”

To the same effect is Ward v. Hudson River Bldg. Co., 125 N.Y. 230 (26 N.E. 256). In Dwinel v. Brown, 54 Me. [368]*368470, the court in the course of its remarks sustaining the provisions of a contract similar to this one, said:

"The parties themselves best know what their expectations are in regard to the advantages of their undertaking, and the damages attendant on its failure, and when they have mutually agreed upon the amount of such damages in good faith, and without illegality, it is as much the duty of the court to enforce that agreement as it is the other provisions .of the contract. . . It is not for the court to sit in judgment upon the wisdom or folly of the parties in making a contract, when their intention is. clearly expressed, and there is no fraud or illegality. No judges, however eminent, can place themselves in the place or position of the parties, when the contract was' made, scan the motives and weigh the considerations which influenced them in the transaction, so as to determine what would have been best for them to do, who was least sagacious, or who drove the best bargain. Courts of common law cannot, like courts where the civil law. prevails, award such damages as they may deem reasonable, but must allow the damages, whether actual or estimated, as agreed upon by the parties. The bargain may be an unfortunate one-for the delinquent party, but it is not the duty of courts of common law to relieve parties from the consequences of their own improvidence, where these contracts are free from fraud and illegality.”

The same doctrine is announced in Clement v. Cash, 21 N. Y. 253, and in the case of De Graff v. Wickham, (Iowa), 52 N. W. 503, which was a case where the amount of forfeiture was the same as in this case, viz., $10 for every day the house should remain uncompleted, the same being a dwelling house, the court, held that the sum named was liquidated damages, which might be recovered in case of a failure to complete the erection of the house according to the terms of the contract.

[369]*369We think these contracts should be sustained, where no fraud or illegality appears, as a matter of policy, for it' would frequently save expensive and troublesome litigation, if the parties could contract in advance with reference to damages, with the knowledge that such contracts would without question be enforced.

We have examined the testimony in this case in detail, and a great deal of it we think was plainly inadmissible and was admitted over the objections of the plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Watson v. Ingram
881 P.2d 247 (Washington Supreme Court, 1994)
Smith v. Phillips Pipe Line Co.
128 F. Supp. 61 (N.D. Oklahoma, 1955)
Foster v. Montgomery Ward & Co.
163 P.2d 838 (Washington Supreme Court, 1945)
Byrne v. Bellingham Consolidated School District No. 301
108 P.2d 791 (Washington Supreme Court, 1941)
Smith v. Lambert Transfer Co.
187 P. 362 (Washington Supreme Court, 1920)
Grand Union Laundry Co. v. Carney
153 P. 5 (Washington Supreme Court, 1915)
Sheard v. United States Fidelity & Guaranty Co.
107 P. 1024 (Washington Supreme Court, 1910)
Williams v. Lewis N. Rosenbaum, Inc.
106 P. 493 (Washington Supreme Court, 1910)
Wallis v. Inhabitants of Wenham
90 N.E. 396 (Massachusetts Supreme Judicial Court, 1910)
Isaacson v. Starrett
104 P. 1115 (Washington Supreme Court, 1909)
Madler v. Silverstone
104 P. 165 (Washington Supreme Court, 1909)
Erickson v. Green
92 P. 449 (Washington Supreme Court, 1907)
Jenkins v. American Surety Co.
88 P. 1112 (Washington Supreme Court, 1907)
Canady v. Knox
86 P. 930 (Washington Supreme Court, 1906)
Drumheller v. American Surety Co. of New York
71 P. 25 (Washington Supreme Court, 1902)
Jennings v. McCormick
65 P. 764 (Washington Supreme Court, 1901)
Long v. Pierce County
61 P. 142 (Washington Supreme Court, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
43 P. 354, 13 Wash. 364, 1896 Wash. LEXIS 53, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reichenbach-v-sage-wash-1896.