Long v. Pierce County

61 P. 142, 22 Wash. 330, 1900 Wash. LEXIS 275
CourtWashington Supreme Court
DecidedApril 7, 1900
DocketNo. 3190
StatusPublished
Cited by27 cases

This text of 61 P. 142 (Long v. Pierce County) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Long v. Pierce County, 61 P. 142, 22 Wash. 330, 1900 Wash. LEXIS 275 (Wash. 1900).

Opinion

The opinion of the court was delivered by

Fullerton, J.

On the 19th day of September, 1890, the appellant and respondent entered into a written contract, by the terms of which the appellant agreed to furnish all the necessary materials, and erect and finish for the respondent a court house and jail, for the consideration of $270,000. The contract provided that the work should be performed under the direction and to the satisfaction of Proctor & Dennis, architects, acting as agents of the respondent, who should, “as the work proceeds,” furnish estimates of the value of the work done and material furnished, upon which the contractor was to be paid eighty-five per cent, of the value of same; and, upon the comple[335]*335tion of the building to the satisfaction of the architects, they were to so certify, and final payment was thereupon to be made to the contractor. The contract contained the following clauses:

2d. Should it appear that the work hereby intended to be done, or any of the matters relative thereto, are not sufficiently detailed or explained on the said drawings, or in the said specifications, the contractor shall apply to the architects for such further drawings or explanations as may be necessary, and shall conform to the same as part of this contract, so far as they may be consistent with the original drawings, and in event of any doubt or question arising respecting the true meaning of the drawings or specifications, reference shall be made to the architects, whose decision thereon, being just and impartial, shall be final and conclusive. It is mutually understood and agreed that all drawings, plans and specifications are and remain the property of the architects.

“ 3d. Should any alterations be required in the work shown or described by the drawings or specifications, a fair and reasonable valuation of the work added or omitted shall be made by the architects, and the sum herein agreed to be paid for the work according to the original specification shall be increased or diminished as the case may be. In case such valuation is not agreed to, the contractor shall proceed with the alteration, upon the written order of the architects, and the valuation of the work added or omitted shall be referred to three (3) arbitrators (no one of whom shall have been personally connected with the work to which these presents refer), to be appointed as follows: one by each of the parties to this contract, and the third by the two thus chosen; the decision of any two of whom shall be final and binding, and each of the parties hereto shall pay one-half of the expense of such reference.

4th. The contractor shall, within twenty-four hours after receiving written notice from the architects to that effect, proceed to remove from the grounds or building all materials condemned by them, whether worked or unworked, or take down all portions of the work which the architects shall condemn as unsound or improper, or as [336]*336in any way failing to conform to the drawings and specifications, and to the conditions of this contract. The contractor shall cover, protect and exercise dne diligence to secure the work from injury, and all damage happening to the same by his neglect shall he made good by him.

“ 6th. The contractor shall and will proceed with the said work, and every part and detail thereof, in a prompt and diligent manner, and shall and will wholly finish the said work according to the said drawings and specifications and this contract, on or before the fifteenth day of September, in the year one thousand eight hundred and ninety-two (provided that possession of the premises be given the contractor, and, lines and levels of the building furnished him, on or before the 15th day of September, in the year one thousand eight hundred and ninety), and in default thereof the contractor shall pay to the owner seventy-five dollars for every day thereafter that the said work shall remain unfinished, as and for liquidated damages.

“ Tth. Should the contractor be obstructed or delayed in the prosecution or completion of the work by the neglect, delay or default of any other contractor; or by any alteration which may he required in the said work; or by any damage which may happen thereto by fire, or by the unusual action of the elements, or otherwise; or by the abandonment of the work by the employees through no default of the contractor, then there shall be an allowance of additional time beyond the date set for the completion of the said work; but no such allowance shall he made unless a claim is presented in writing at the time of such obstruction or delay. The architects shall award and certify the amount of additional time to be allowed; in which case the contractor shall he released from the payment of the stipulated damages for the additional time so certified and no more. The contractor may appeal from such award to arbitrators constituted as provided in Article 3d of this contract.

“ 14th. Tt is further mutually agreed between the parties hereto that no certificate given or payment made under this contract, except the final certificate or final payment, shall be conclusive evidence of the performance of [337]*337this contract, either wholly or in part, against any claim of the owner, and no payment shall be construed to be an acceptance of any defective work.”

On entering in to the contract the appellant proceeded with the work, and on the 8th day of May, 1893, notified the architects that the building was ready for their acceptance. The architects refused, on the ground that the building had not been completed in accordance with the contract, to issue the final certificate. After some controversy, and for the purpose of settling their differences, the appellant and respondent entered into a supplemental agreement, dated the 21st day of June, 1893, which recited that the appellant claimed that he had fully completed his contract; that some question had arisen between the parties as to the construction and interpretation of the plans and specifications, and as to whether or not the building had been completed in accordance therewith; that, notwithstanding the conflicting claims between the parties, the building was in a situation for occupancy and at least partial use by the respondent; “that it is desired by all parties hereto to expedite the settlement of all court house matters, and lessen the expense of all parties to such settlement, and establish the claims of the first party for damages for nonperformance, and those of the second party for extras, and all other claims that may justly arise on behalf of either of said parties under said contract and matters pertaining thereto;” and proceeds in part as follows :

“ Now, therefore, It is agreed by all parties hereto, that the party of the first part shall have the right to use and occupy any and all portions of said court house; that such occupation and use by said party of the first part shall not prevent the party of the second part from completing or finishing any parts or portion of said court house that may [338]*338be ascertained to be incomplete, and tbe second party desires to complete.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rosellini v. Banchero
517 P.2d 955 (Washington Supreme Court, 1974)
Iverson v. Peterman
335 P.2d 819 (Washington Supreme Court, 1959)
Conran v. White & Bollard, Inc.
167 P.2d 133 (Washington Supreme Court, 1946)
City of Lawton v. Sherman MacHine & Iron Works
1938 OK 175 (Supreme Court of Oklahoma, 1938)
Lord v. Commissioner
30 B.T.A. 425 (Board of Tax Appeals, 1934)
Manett, Seastrunk & Buckner v. Terminal Building Corp.
39 S.W.2d 1 (Texas Supreme Court, 1931)
Inman v. W. E. Roche Fruit Co.
298 P. 342 (Washington Supreme Court, 1931)
Hill Et Ux. v. Scott
143 A. 276 (Supreme Court of Vermont, 1928)
Winn v. Stanton
262 P. 645 (Washington Supreme Court, 1928)
Barbo v. Norris
245 P. 414 (Washington Supreme Court, 1926)
La Plante v. Hubbard
217 P. 20 (Washington Supreme Court, 1923)
Sunset Copper Co. v. Black
196 P. 640 (Washington Supreme Court, 1921)
Moore v. Stetson Machine Works
188 P. 769 (Washington Supreme Court, 1920)
McMahon v. Matthews
48 App. D.C. 303 (D.C. Circuit, 1919)
Tacoma & Eastern Lumber Co. v. Field & Co.
170 P. 360 (Washington Supreme Court, 1918)
Rose v. Kimball
91 Wash. 60 (Washington Supreme Court, 1916)
Russell & Gallagher v. Yesler Estate, Inc.
154 P. 188 (Washington Supreme Court, 1916)
Stofferan v. Depew
139 P. 1084 (Washington Supreme Court, 1914)
Wiley v. Hart
132 P. 1015 (Washington Supreme Court, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
61 P. 142, 22 Wash. 330, 1900 Wash. LEXIS 275, Counsel Stack Legal Research, https://law.counselstack.com/opinion/long-v-pierce-county-wash-1900.