City of Lawton v. Sherman MacHine & Iron Works

1938 OK 175, 77 P.2d 567, 182 Okla. 254, 1938 Okla. LEXIS 126
CourtSupreme Court of Oklahoma
DecidedMarch 15, 1938
DocketNo. 26631.
StatusPublished
Cited by12 cases

This text of 1938 OK 175 (City of Lawton v. Sherman MacHine & Iron Works) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Lawton v. Sherman MacHine & Iron Works, 1938 OK 175, 77 P.2d 567, 182 Okla. 254, 1938 Okla. LEXIS 126 (Okla. 1938).

Opinion

WELCH, J.

This is an appeal from the district court of Comanche county upon two eases consolidated therein and tried to the court. Plaintiff recovered judgment upon allegations of balances due it under construction contracts, and the defendant city has perfected the appeal. We will refer to the parties as plaintiff and defendant, as they appeared in the trial court.

In March, 1930, the defendant city voted .bonds in the sum of $600,000 for waterworks improvements. Thereafter plaintiff contracted with defendant under three separate contracts made under three separate bids to construct such improvements. Contract No. 1 was for the furnishing of materials and construction of a 24-inch supply main from the defendant’s filtration plant to the' Fort Sill area, and a 16-inch line in and about such areas. Such contract was entered into in January, 1931.

Under contract No. 2 a 24-inch pipe line running from what is known as station 300 to the city of Lawton was constructed, two old pipe lines being taken up and the pipe relaid at various points, and certain improvements and extensions to the existing distribution system within the city of Law-ton were made. Such contract was made on January 17, 1931.

Under contract No. 3 h new filtration plant was constructed. Such contract was made on May 15, 1931. The first contract had been completed and the work accepted and paid for.

Plaintiff brought suit on contract No. 2, alleging a balance due thereunder of $22,404.43, being the difference between $164,008.62, the alleged total amount payable under the contract, and the total payments of $141,604.19.

Plaintiff also brought separate suit on contract No. 3, alleging a balance due thereunder of $16,729.68, same being the difference between $141,311.09, the alleged total amount due under the contract, and the total payments of $124,581.41.

The defendant answered in both of the cases, denying generally, and specifically alleging inferior workmanship, materials, etc.. and denying that the plaintiff had performed in accordance with the contracts, and alleging fraud upon the part of two of its engineers. The cases were consolidated for trial, and shortly before trial the defendant, by amendment, and over plaintiff’s objections duly saved, alleged as a counterclaim pertain alleged overpayments and damages arising from various alleged details under contract No. 1. A jury was waived and the cause tried to the court, resulting in a judgment in favor of plaintiff substantially^ as prayed.

One of the questions for us to determine is whether the defendant may properly *256 plead matters relating to contract No. 1 as a counterclaim in the present cause. The defendant urges that the point is controlled by the case of Donaldson & Yahn v. Benight, 105 Okla. 108, 232 P. 116, wherein this’ court treated several projects as com stituting one contract involving the extension of the waterworks system for the city of Perry. It appears to be the settled law of this jurisdiction that the demands of a counterclaim may not be asserted where they arise wholly out of a separate contract (Allison v. Shinner, 7 Okla. 272, 54 P. 471; Harris v. Warren-Smith Hdw. Co., 44 Okla. 477, 144 P. 1050; Haffner v. First National Bank of Seiling, 152 Okla. 169, 5 P.2d 351, and Gooldy v. Klein Iron & Foundry Co., 170 Okla. 466, 40 P.2d 1070) ; and that rule was recognized in the Benight Case, supra, but in that case all the parties had treated the projects or contracts as one contract. Observe the following statement of the court therein:

“Benight treats the three contracts as one contract for the construction work in his action to recover on the assignment. He treats the assignment as one cause of action against the city. It appears that all parties treated the contracts as one contract in doing the construction work, as it related to the completion of a single project”

—which, together with other facts, justified this court in treating the contracts there as one.

We do not find that the parties here treated the three contracts as one. They were each bid upon and executed separately and at different times; the work appears to have progressed separately, and all the parties at all times appear to have treated them as entirely separate contracts. The work on contract No. 1 was performed and accepted by the city and paid for in full without reserving any of the amounts due as provided therein. The plaintiff brought separate suits upon each of contracts Nos. 2 and 3.

We do not consider the mere fact that the contracting parties are the same, and that the contracts each related to waterworks projects, sufficient to justify the legal conclusion that the counterclaim herein pleaded arose out of the same contract upon which plaintiff’s actions are based. We therefore conclude that the trial court should have excluded from consideration any evidence pertaining • to contract No. 1, and we shall not give the same consideration herein.

The record and briefs are lengthy, and we will endeavor to consider the questions as nearly as possible in the order presented by the defendant’s brief, omitting, however, any discussion concerning contract No. 1. It is said that the trial court made no distinction in its finding of fact between apparent and latent defects. Our attention is called to National Surety Co. v. Board of Education of City of Hugo, 62 Okla. 259, 162 P. 1108. It is further suggested that it is apparent from the findings of fact that the trial court considered the final certificate of the engineer as binding, in the absence of a showing of “absolute fraud.” The defendant urges the following quotations as stating the applicable law relative to the reports of engineers, and this the plaintiff does not dispute.

“There can be no doubt that notwithstanding the fact that a contract makes the certificate, report, oxnnion, or decision of an engineer or architect conclusive on the parties, the law writes into this provision that the conduct of the engineer or architect must be free from fraud. Fraud on his part 'destrojrs the effect of the provisions. Therefore, if the engineer or architect fails to exercise his honest judgment, or makes such gross mistake as implies bad faith, his decision, report, certificate, or opinion may be impeached." Vol. 6 R. C. L. par. 341.

And in Ilse v. Aetna Indemnity Co. (Wash.) 104 P. 787:

“It is urged by the plaintiff • that the certificate of the architect must be deemed to be conclusive of the amount due the plaintiff, inasmuch as the contract expressly states that the certificate of the architects shall be conclusive between the parties. It is the general rule of law that parties to building contracts may agree that the certificate of an architect or an award by an arbitrator shall be a condition precedent to the right of action or conclusive as to the amount due on the contract. This rule is not without its excexstions. It hg.s accordingly been held that the certificate or award must be made upon such knowledge of the subject matter as to warrant an opinion binding upon the parties. This principle finds expression in the cases of Van Hook v. Burns, 10 Wash. 22, 38 P. 763; McDonald v. Lewis, 18 Wash. 300, 51 P. 387; Long v. Pierce County, 22 Wash. 354, 61 P. 142. This is consistent with the rule that a certificate may be impeached for fraud or for such gross mistake or error as would imply bad faith.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

FOUNDATION INTERN. v. ET Ige Const.
78 P.3d 23 (Hawaii Supreme Court, 2003)
Cook v. Oklahoma Board of Public Affairs
1987 OK 22 (Supreme Court of Oklahoma, 1987)
ANTRIM LUMBER COMPANY v. Bowline
1969 OK 161 (Supreme Court of Oklahoma, 1969)
Flour Mills of America, Inc. v. American Steel Building Co.
449 P.2d 861 (Supreme Court of Oklahoma, 1969)
City of Granville v. Kovash, Incorporated
118 N.W.2d 354 (North Dakota Supreme Court, 1962)
Lippert Bros. v. City of Atoka
94 F. Supp. 630 (E.D. Oklahoma, 1950)
Jackson Materials Co. v. Grand River Dam Authority
1945 OK 228 (Supreme Court of Oklahoma, 1945)
Barron v. Chicoraske
1941 OK 149 (Supreme Court of Oklahoma, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
1938 OK 175, 77 P.2d 567, 182 Okla. 254, 1938 Okla. LEXIS 126, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-lawton-v-sherman-machine-iron-works-okla-1938.