National Surety Co. v. Board of Edu. of City of Hugo

1917 OK 109, 162 P. 1108, 62 Okla. 259, 1917 Okla. LEXIS 292
CourtSupreme Court of Oklahoma
DecidedJanuary 23, 1917
Docket7700
StatusPublished
Cited by9 cases

This text of 1917 OK 109 (National Surety Co. v. Board of Edu. of City of Hugo) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Surety Co. v. Board of Edu. of City of Hugo, 1917 OK 109, 162 P. 1108, 62 Okla. 259, 1917 Okla. LEXIS 292 (Okla. 1917).

Opinion

Opinion by

GAILBRAITH, C.

This action was commenced by the defendant in error against the contractor and the surety company to recover damages for breach of a building contract. It was charged that in October, 1905, the school authorities of the town of Hugo entered into a contract with R. O. Langworthy whereby he undertook and agreed to furnish the material and to erect a two-story brick school building and to place therein a heating plant of definite description and capable of producing a specified result, and that the contractor executed a bond, with the surety company as surety, in the sum of $4,123, conditioned for the faithful performance of the contract on the part of the contractor ; that the contractor had failed to perform the contract, and damages had been sustained on account thereof in the sum of $3,306; that the contractor had failed to pay the damages, and the surety company had failed to- pay upon demand, and judgment was prayed in the amount of the damages sustained against the contractor and the surety company. The contractor, being a nonresident of the state, •was not served with process and made no appearance in the action The surety company answered and denied liability on the grounds: (1) That material changes had been made in the plans and specifications without the knowledge or consent of the defendant, and that the contract had been thereby modified and changed so as to relieve it from liability; (2) that under the contract the architect was made the arbiter as between the owner and the contractor as to the completion of the con tract, and that his final certificate was Con elusive upon them as to the performance of the contract, and that the architect had issued a final certificate, and that the building had been accepted and paid for, and therefore there was no liability on the part of the surety company; and (3) that the contract provided that payments to the contractor should be made every two weeks up to 80 per cent, of the work then finished, and that 20 per cent, of these payments should be retained until after the completion of the building, and all claims and demands against it discharged, and that the owner had not retained this 20 per cent, as the contract provided, and that therefore the surety was relieved from liability on its bond. A reply was filed denying that the payments to the contractor had not been made in strict compliance with the terms of the contract, and also denied that any material changes had been made in the plans and specifications, and admitted that the final certificate of the architect had been issued and the building had been accepted and paid for by the owners, but averred that such final certificate was wrongfully issued by the architect, in this, that he *260 either knew of the failure of the contractor to erect and equip the building as specified in the plans and specifications, or if he did not know this the want of knowledge was due to gross negligence, and his act in issuing the certificate was in effect a fraud upon the owner, and they were therefore not bound by it. Upon the issues thus'formed, the cause was tried to the court and a jury, and a verdict returned for the plaintiff. To review that judgment this appeal has been prosecuted.

It is first complained that the trial court erred in permitting an amendment to the petition just before the. trial, and some two years after the filing of the original petition, and after the cause had been tried and judgment entered and an appeal taken to the Supreme Court, and the cause reversed for a new trial, for the reason that the amended petition so filed substantially changed the cause of action from one of nonperformance or malperformance of the contract to one for the recovery of the quantum meruit for damages arising since the completion of the building.

We are not able to agree with this contention. It does not seem tha t the amended petition complained of in any material matter changed the cause of action set out in the pleading amended. The original cause of action was for breach of the building contract. The amended pleading charged a breach of the same contract, and ehárged the damages arising therefrom in practically the same form, and it was not error in the' trial court to permit this amendment to the pleading to he filed. Limerick v. Lee, 17 Okla. 165, 87 Pac. 859.

It is complained that the trial court erred in admitting the building contract in evidence over the objection of the defendant. This contract was set out in the petition and attached thereto as an exhibit. It was a part of and to be construed with the bond sued upon (National Surety Co. v. Haley et al., 58 Okla. 263, 159 Pac. 292), and it was properly admitted in evidence (Henry v. Allen, 49 Ark. 122, 4 S. W. 201).

Again, it is complained that the court erred in admitting over the objection of the defendant Exhibit D, being the contract entered into by the school authorities for “overhauling the steam heating apparatus” in the building. This writing was admitted in the course of the examination of a witness who was' testifying as to the damages sustained by reason of the contractor’s failure to put in the heating plant as he had agreed to do, according to the plans and specifications, and who was testifying as to the amount of damages that had been sustained by the failure to perform the contract in this respect. This evidence was incompetent, and the objection to it should have been sustained. The contract may have been an improvident one, and the building contractor and his surety were not bound by it. First National Building Co. v. Vandenberg, 29 Okla. 583, 119 Pac. 224. However, it does not appear that the plaintiff in error was prejudiced by this error, inasmuch as there was ample competent evidence, excluding this exhibit entirely, to show that damages had been sustained in an amount equal to and in excess of the verdict of the jury.

Again, it is complained that the court erred in excluding a deposition offered on the ground that the objection to the deposition was too general.. This was a deposition of the general attorney for the surety company, who resided in New York, and the purpose of his deposition was to show that the surety company did not have notice of the changes made in the construction of the building, and the manner of payments to the contractor. The objection was “to each and every one of these questions as incompetent, irrelevant, and immaterial, and as calling for the conclusions of the witness; the witness not being qualified to testify as to the matters inquired about.” The contract provided:

“It is also further agreed that the said party of the second part may make any alteration by adding, omitting or deviating from the aforesaid plans, drawings and specifications, or either of them, which he shall deem proper, and the .said architect shall advise, without impairing the validity of the contract, and in all such cases the said architect shall value or appraise such alteration, and add to or deduct from the amount herein agreed to be paid to the said first party the excess or deficiency occasioned by such alteration.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cook v. Oklahoma Board of Public Affairs
1987 OK 22 (Supreme Court of Oklahoma, 1987)
Haggerty v. Selsco
534 P.2d 874 (Montana Supreme Court, 1975)
ANTRIM LUMBER COMPANY v. Bowline
1969 OK 161 (Supreme Court of Oklahoma, 1969)
Flour Mills of America, Inc. v. American Steel Building Co.
449 P.2d 861 (Supreme Court of Oklahoma, 1969)
Mitchell v. Carlson
313 P.2d 717 (Montana Supreme Court, 1957)
City of Lawton v. Sherman MacHine & Iron Works
1938 OK 175 (Supreme Court of Oklahoma, 1938)
Fuqua v. Tulsa Masonic Bldg. Ass'n
1928 OK 71 (Supreme Court of Oklahoma, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
1917 OK 109, 162 P. 1108, 62 Okla. 259, 1917 Okla. LEXIS 292, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-surety-co-v-board-of-edu-of-city-of-hugo-okla-1917.