National Surety Co. v. Haley

159 P. 292, 58 Okla. 263, 1916 Okla. LEXIS 45
CourtSupreme Court of Oklahoma
DecidedJuly 25, 1916
Docket4506
StatusPublished
Cited by5 cases

This text of 159 P. 292 (National Surety Co. v. Haley) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Surety Co. v. Haley, 159 P. 292, 58 Okla. 263, 1916 Okla. LEXIS 45 (Okla. 1916).

Opinion

TURNER, J.

On September 22, 1911, in the district court of Oklahoma county, W. P. Haley, defendant in error, sued Geo. W. Binning, as principal, and National Surety Company, plaintiff in error, as surety, to recover on a bond dated December 18, 1909, given to secure the faithful performance of a contract, whereby Binning agreed to erect a building for plaintiff in Oklahoma City within 90 days from the date thereof for $21,500, according to certain plans and specifications made a part of the contract, which was dated December 7, 1909, and made a part of the bond.

The breach of the bond was alleged to be that Binning had abandoned the contract, whereupon plaintiff was compelled to take charge of the building and complete the same at his own expense and at a loss- of $9,862.25, for which, after alleging a compliance'with all conditions precedent to recover thereupon, he prayed judgment against Binning as principal and ¿gainst the surety company for $4,300, the full amount of the bond. For answer, the surety company, after general denial and a specific denial of the performance of conditions precedent to a right to *265 recover, admitted the execution of the bond, and for further defense specifically alleged:

“That many material changes and alterations were made by plaintiff and the defendánt Binning in the plans and specifications • and in the erection of said building, which were made without the- knowledge, consent or approval of this defendant, and that by reason of such changes having been made, without the knowledge, consent or approval of this defendant, the National Surety Company, and its obligation upon said surety bond was absolved and this defendant released from further responsibility thereon.”

Binning made default. On trial to the court, there was judgment for plaintiff and against Binning and the surety company, as prayed, and, after motion for new trial was filed and overruled, the surety company brings the case here.

As to the surety company, the judgment is neither contrary to the law nor to the evidence, as contended.- On this point the evidence discloses that the bond, after making the contract a part thereof, among other things, provides:

“Now, therefore, the condition of this instrument is such that if the said principal shall well and truly perform the terms and provisions of said contract on the part of said principal required to be performed, then this instrument shall be null and void, otherwise to be and remain in full force and effect: Provided, however, and this instrument is executed by the company as surety upon the following express conditions, which shall be precedent to the right of recovery hereunder. * * * The obligee shall, at the times and in the manner specified in said contract,' perform all the covenants, matters and things required to be by the obligee performed; and if the obligee^ default in the performance of any matter or thing in this instrument, or in said contract agreed or required to be *266 performed by the obligee, the company shall thereupon he relieved from all liability hereunder. * * * If any changes or alterations by the principal and obligee be made in the plans or specifications for the work mentioned in said contract, the obligee shall immediately so notify the company of such, changes or alterations, giving a description thereof and stating the amount of money involved by such changes or alterations: Provided, however, that when the cost of said changes or alterations shall in the aggregate amount to a sum equal to 10 per cent, of the penal sum of this bond, no further changes or alterations shall be agreed upon by the principal and obligee, until the consent of the company shall first be obtained thereto.”

The evidence further discloses that on February 18, 1910, and while Binning was at work on the building, plaintiff sent by registered mail to the office of the surety company in New York an itemized list of changes from the original plans which, he wrote the company, had been agreed upon between him and Binning. Some of the 17 items in the list showed changes which added to the contract price $509.58; others showed changes which reduced it $809.40; and others which did not affect it at all. In the list was an item providing for piping gas to the front store room, for two openings for light, and the halls above first floor, “cost not yet ascertained.” Another provided for wiring for three electric signs, “cost not yet ascertained”; but it seems the cost of both these items was furnished on a later list. On March 13, 1910, plaintiff sent to the surety company a similar list which, he wrote the company, had been agreed upon between him and Binning, containing 28 items, some of which added to the contract price $40.18, and others which reduced it $36. All of them provided for changes in the plans and specifications; the last item on the list provided for margins on floors of rooms of upper story to be stained, “cost not *267 ascertained.” The cost oí this item also was furnished on a later list. On March 5, 1910, plaintiff and Binning entered into an agreement, supplemental to that of December 7th, consisting of 26 items, some of which added to the contract price $452.16, and some deducted therefrom $324.40, and some did not affect it at all, but all provided for changes in the plans and specifications. As defendant does not complain of want of notice of these changes, we presume the same was given. On April 3d Binning quit the contract, after receiving some $18,000 of the contract price of $21,500 for the building, whereupon plaintiff, about June 1st, completed the same, as he had a right to do under the contract, at a cost of $9,862.25 in excess of the contract price, after which he brought this suit; from all of which it is contended that, as the bond is in the penal sum of $4,300, and the increased cost of the changes in the first list of items exceeded 10 per cent, of the penal sum of the bond, the consent of the company thereto as to such excess was not only a condition precedent to the right of plaintiff and Binning to agree to make them, but a condition precedent to plaintiff’s right to recover on the bond; and that, as the evidence discloses such consent was never had before the changes were made, plaintiff cannot recover. This contention cannot be sustained.

Standing alone, the changes made were expressly authorized without the consent of any one, save the parties to the contract, by that part of the qontract which provides: *268 (from the contract price), without in any wise affecting this instrument.” (Words in parentheses are ours.)

*267 “It is mutually understood by the parties hereto that any changes made in the plans and specifications for the foregoing building (shall be binding) if a' mutual agreement is made in writing and witnessed (and), the amount of same may be added or deducted, as the case may be

*268

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Plywood Corp. v. Continental Casualty Co.
157 A.2d 286 (District of Columbia Court of Appeals, 1960)
Andes Co-Operative Dairy Co. v. Commercial Casualty Insurance
207 A.D. 102 (Appellate Division of the Supreme Court of New York, 1923)
National Surety Co. v. Board of Edu. of City of Hugo
1917 OK 109 (Supreme Court of Oklahoma, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
159 P. 292, 58 Okla. 263, 1916 Okla. LEXIS 45, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-surety-co-v-haley-okla-1916.