American Surety Co. of New York v. Scott & Co.

1907 OK 4, 90 P. 7, 18 Okla. 264, 1907 Okla. LEXIS 110
CourtSupreme Court of Oklahoma
DecidedFebruary 13, 1907
StatusPublished
Cited by11 cases

This text of 1907 OK 4 (American Surety Co. of New York v. Scott & Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Surety Co. of New York v. Scott & Co., 1907 OK 4, 90 P. 7, 18 Okla. 264, 1907 Okla. LEXIS 110 (Okla. 1907).

Opinion

Opinion of the court by

Pancoast, J.:

Seven different propositions are contended for as ground of error. We will notice these in their order. The first is as to the examination of some of the jurors. Certain questions were asked some of the jurors on their voir dive, which were objected to and the objections sustained by the court. 'While we think the objections were properly sustained, yet, even if there was error in this regard, it is not preserved in the record. The questions did not go to the competency of the jurors nor to their qualifications as jurors in this particular case, but, it is claimed, the questions were asked for the purpose of enabling the defendant to intelligently use its peremptory challenges. In order to preserve .such matters for review in this court, it is neces *268 sary that the record show that the particular jurors were among the number selected to try the case, and also that the defendant had exhausted its peremptory challenges, for, however erroneous the ruling of the court might be in refusing to allow the jurors t.o answer certain questions, if the jurors are not finally selected to try the case, the error will be immaterial, and if the complaining party does not exhaust its peremptory challenges, still it cannot be heard to complain.

The next contention is that after the execution of the. contract and bond, certain alterations and changes were made in the contract without the knowledge or consent of the surety and without notice to it. Two classes of alterations are alleged to have been made, the first being a change in the foundation of the building, and the second, some minor changes with reference to guttering and the size of bathrooms. As to the first alleged alteration, it is shown that when the excavation for the building was being proceeded with, it was found that a stratum of sand existed beneath the surface, and at a point where “the foundation was intended to have been laid, which prevented the construction of the building on such a foundation, and, in order to procure a proper foundation for such a building, it became necessary to excavate further and commence the foundation deeper than was originally intended and provided for in the plans and specifications. When this condition was ascertained, the contractors were instructed to proceed with the excavation to a depth at which a foundation could properly be started, and did so. Upon one side it is claimed that there was a separate contract for this extra excavation and foundation, while on the other it is claimed that no separate contract was made, but that *269 the contractors were instructed to proceed to a point necessary for a proper foundation, and that the extra expense, whatever it might be, would be paid for. The work was proceeded with. The extra foundation was laid and the building constructed upon the foundation as provided for in the plans and specifications.

There was a clause in the contract which provided that no alterations should be made in the work, except upon the written order of the architct, and when so made, the value of the work added or omitted should be computed by the architect and the amount so ascertained should be added to or deducted from the contract price; and another provision which was that should Scott and Company require any changes, additions or omissions, they should be at liberty to do so, without affecting the bond or making void the contract. Whether or not this extra work of excavation a.nd foundation was ordered by the architect, is not made clear in the record, but, inasmuch as the architect was present, supervising the entire structure, it is fair to presume that the work was done under his orders. It is certainly clearly shown by the record that the cost was computed and paid for, in excess of the contract price. Under the provisions of the contract, no notice of this extra work was necessary to be given to the suretj'' company, but the provision in the contract in this regard is that it should be on the order of the architect, and this evidently for the purpose of keeping a correct account of any extra work so that the cost thereof might be correctly computed.

The other alterations are very slight and immaterial, consisting of a change in the position of the guttering on one *270 side of the building, and a possible change in the size of the bathrooms.

.Counsel for plaintiff in error cite a large array of authorities to uphold the proposition here contended for. We have examined those at our command and find that those holding a contract void because of certain changes made are, many of them, cases where no changes are provided for in the contract, and where the changes made are material ones, or in cases where the surety signs as an accommodation for the contractor, without any consideration. Some of the authorities cited do not support the position contended for by counsel. The material difference between the cases cited and the case at bar, is, first, that the contract specifically provides that changes may be made without avoiding the bond, and, second, that the surety company .is an insurer for a consideration. Hence, the doctrine contended for by counsel for appellant can not have much application to the case at bar. One of the cases cited by counsel, Risse v. Hopkins, 40 Pac. 904, may be used as an illustration of some of the cases cited. In this case it is held that “A slight departure from the plans and specifications of the work, without the knowledge of the sureties upon the bond, where alterations are authorized by the contract the performance of which the bond was given to secure, will not relieve the sureties from liability upon the bond.”

The next contention is that Scott .and Company extended the time within which the building was to be completed, without the knowledge and consent of the surety company, or notice to it. The contract contained a provision that the contractors would complete the work comprehended *271 in the agreement, and have the same ready for acceptance on the 22nd day of November, 1901, and also contained a provision that upon failure to complete the building within the time specified the contractors should pay to Scott and Company five dollars per day as liquidated damages. The contractors did not complete the building within the time provided, but continued the work until a later date. The fact that the contractors proceeded with the work after the date which the contract required for its completion, did not amount to a contract of extension of time; such condition was provided for in the contract and a penalty was provided for a failure to complete the building within the time. There is, therefore, no merit in this contention, and the instruction of the court given under this head is correct.

The next contention is that the obligees in the bond, by the failure to give notice to the surety of any default on the part of the contractors within ten days after the occurrence of such default, released the surety from its obligation. Notice was given to the surety within ten days from the time that the contractors abandoned the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walton Et Ux v. Denhart Et Ux
359 P.2d 890 (Oregon Supreme Court, 1961)
Fuqua v. Tulsa Masonic Bldg. Ass'n
1928 OK 71 (Supreme Court of Oklahoma, 1928)
Community Bldg. Co. v. Maryland Casualty Co.
8 F.2d 678 (Ninth Circuit, 1925)
Lamson v. Maryland Casualty Co.
196 Iowa 1185 (Supreme Court of Iowa, 1923)
State v. Hudson Paving & Construction Co.
113 S.E. 251 (West Virginia Supreme Court, 1922)
Lumber Co. v. . Johnson
97 S.E. 732 (Supreme Court of North Carolina, 1919)
Guilford Lumber Manufacturing Co. v. Johnson
177 N.C. 44 (Supreme Court of North Carolina, 1919)
National Surety Co. v. Haley
159 P. 292 (Supreme Court of Oklahoma, 1916)
Evatt v. Dulaney
1915 OK 580 (Supreme Court of Oklahoma, 1915)
Young Men's Christian Ass'n v. Ritter
133 P. 894 (Supreme Court of Kansas, 1913)
Lakeside Land Co. v. Empire State Surety Co.
117 N.W. 431 (Supreme Court of Minnesota, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
1907 OK 4, 90 P. 7, 18 Okla. 264, 1907 Okla. LEXIS 110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-surety-co-of-new-york-v-scott-co-okla-1907.