State v. Hudson Paving & Construction Co.

113 S.E. 251, 91 W. Va. 387, 1922 W. Va. LEXIS 130
CourtWest Virginia Supreme Court
DecidedMay 23, 1922
StatusPublished
Cited by4 cases

This text of 113 S.E. 251 (State v. Hudson Paving & Construction Co.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. Hudson Paving & Construction Co., 113 S.E. 251, 91 W. Va. 387, 1922 W. Va. LEXIS 130 (W. Va. 1922).

Opinion

MeRedith, Judge:

This is an action in debt instituted in the name of the State for the use of the county court of Randolph County against R. M. Hudson Paving and Construction Company, hereinafter called the “contractor,” and United States Fidelity and Guaranty Compaq, its surety, upon a bond executed in favor of plaintiff in the sum of $46,000, conditioned for the faithful performance by the contractor of a road building contract, being one of five contracts, executed by the same contractor for the building of certain roads in Leadsville District, under a road bond issue. The particular contract is known as “Contract No. 1 Beverly Pike and Seneca Road.” It is dated August 12, 1916, and is one of the “blanket form” contracts commonly used in the con-[389]*389struetion of permanent roads. The plans, specifications and bids were made a part of the contract. The bid of the contractor was upon a unit basis, and covered various specified kinds of materials, such as concrete, tarvia penetration, as-phaltic concrete penetration, water bound macadam, brick paving and rocmac, for each of which prices were named by the bidder. The Beverly Pike portion of the contract was to be paved with concrete. That part was finished in 1916, and is not involved in this controversy. This action concerns only the uncompleted portion of the Seneca Eoad. The contract was let upon the unit basis and called for rocmac construction with a four-inch crushed stone base on the Seneca Eoad. The contractor was to do all the -work and furnish all the materials and appliances. It was to do the grading at 50 cents per cubic yard, furnish and lay the rocmac with crushed stone base at $1.19 per square yard, furnish and lay the required 18 inch vitrified pipe at $1.15 per lineal foot, and the 12 inch vitrified pipe at 75 cents per lineal foot. The State Eoad Bureau refused to approve the rocmac construction and in February, 1917, it was agreed between the county court and the contractor that a five inch concrete roadway nine feet wide of a 1-2-4 mixture would be built on the Seneca Eoad in lieu of the rocmac roadway of the same width as originally agreed upon, and that for this paving the contractor should receive the same price per-square yard as for the rocmac. The other items were not changed. The contractor proceeded with the work, completing all of the grading but 1000 cubic yards, laid all of the concrete paving but 4500 square yards, and furnished and put in all but 60 lineal feet of the 18 inch pipe and 60 lineal feet of the 12 inch pipe; it quit the job sometime late in 1917. No further work was done. The World War was in progress and the contractor excused itself from going on with the work by reason of railroad embargoes on road materials and on account of the scarcity of labor. The contractor became insolvent. It appears that this did "not become known to the county court until the spring of 1918. In April, 1918, a representative of the contractor appeared at Elkins and endeavored to enter into a new contract to [390]*390finish the road, but this was refused. The court directed its engineer to notify-the contractor to proceed with the work and also to notify the surety to have the contractor complete its contract or that the surety itself take over and complete it. The matter drifted along till February, 1919, without result. The county court then notified the contractor and its surety to begin work under the contract within 10 days and to prosecute the work to completion at the earliest possible date and that unless notice should be received by the court within 15 days from the receipt by them of its notice that they or one of them intended to complete the work according to the contract, then the county court would complete the work as provided by the terms of the contract. The contractor and surety failed to go on with the work and the county court in April, 1919, advertised for and received bids on the work to be done, but deeming the bids too high, all bids were rejected. This suit was instituted August 5, 1920, and the case was tried about March 21, 1921, resulting in a verdict in favor of the plaintiff for the sum of $5,329.22, upon which judgment was entered. The surety obtained a writ of error.

There are but three main questions in this case, all involving a construction of the contract, and they will be taken up in order.

First: Was the county court bound to take over and complete the work before bringing suit ? This point is raised by defendant’s demurrer to plaintiff’s declaration, and also by its special plea No. 4 which was rejected by the court. The defendant claims that the remedy provided by the contract, in case of the contractor’s default, is exclusive. The provision in the contract upon which defendant’s counsel rely in this respect is as follows:

“If the Contractor shall become insolvent, or be declared bankrupt, or shall from any other cause, in the judgment of the engineer, be unable to carry, on .the work; or if he shall make default in the due performance of the agreement or any or all of the conditions herein enumerated, or in diligently proceeding with the work, and the Engineer shall give notice in writing of such delay, neglect or default to [391]*391the Contractor, specifying the same, and if the Contractor shall, for a period of ten (10) days after such notice, not proceed satisfactorily in accordance therewith, then the County Court shall, on written certificate of the Engineer of the fact of such delay, neglect or default, and on the Contractor’s failure to comply with such notice, have full power and authority, without violating this contract, to take the work wholly or in part out of the hands of said Contractor, to appropriate and use any or all of the materials and tools on the ground as may be suitable and acceptable, and may enter into a contract for the completion of said work according to the terms and provisions of the contract. The cost and charges incurred by the Court, together with the cost of the completion of said work,'shall be deducted from any moneys due or which may become due said Contractor, and in case the expense so incurred by the Court is less than the sum which would have been payable under this contract if the same had been completed by the said Contractor, then the said Contractor shall be entitled to receive the difference, and in case- such expense shall exceed the last sum, then the Contractor shall on demand, pay the amount of said excess to the County Court, but such excess to be paid by the Contractor shall not exceed the amount of the security for the performance of this contract.”

For this proposition we are cited to the case of Goss v. Northern Pacific Hospital Association, 50 Wash. 236, 96 Pac. 1078, and to 13 C. J. 696. The case cited arose upon a building contract. The principal contractor sued the owner for certain deductions made by the architect and for extra work done and for damages occasioned by the delay of another who had an independent contract to do the plumbing work. Goss was employed to build the hospital but he was not 'required to put in the plumbing nor to install the heating plant in the buildings. Goss’s work was delayed through the fault of the plumbing contractor. It was provided in Goss’s contract: "Should the contractor be obstructed or delayed in the prosecution or completion of his work by the act, neglect, delay or default of the owner or the architect, or any other contractor employed by the owner upon the work, or by any damage which may happen by fire, lightning, earthquake or [392]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
113 S.E. 251, 91 W. Va. 387, 1922 W. Va. LEXIS 130, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-hudson-paving-construction-co-wva-1922.