Hayden v. Cook

52 N.W. 165, 34 Neb. 670, 1892 Neb. LEXIS 163
CourtNebraska Supreme Court
DecidedMay 18, 1892
StatusPublished
Cited by18 cases

This text of 52 N.W. 165 (Hayden v. Cook) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hayden v. Cook, 52 N.W. 165, 34 Neb. 670, 1892 Neb. LEXIS 163 (Neb. 1892).

Opinion

Norval, J.

The plaintiff in error brought suit in the court below against J. A. Cook, as principal, and John Green, as surety, on a bond given for the faithful performance by Cook of his building contract with the plaintiff. The bond is as follows:

[672]*672Know all men by these presents, that we, J. A. Cook, principal, and John Green, sureties, are held and firmly bound unto J. A. Hayden in the sum of one thousand dollars, for which payment, well and truly to be made, we do bind and obligate ourselves, our heirs, executors, administrators, or assigns, each and every of them, firmly by these presents. Sealed with our seals this May 12, A. D. 1888.
“ Whereas J. A. Cook has contracted with J. A. Play-den to execute, construct, and complete a frame story-and-a-half cottage for the sum of eighteen hundred and thirty-seven dollars, by a contract dated May 12, A. D. 1888, hereto annexed: Now, the condition of this obligation is, that if the said J. A. Cook shall duly perform and keep his agreements as in said contract set forth, and shall pay for all material and work in and about said building, so that the same shall not be liable to any mechanics’ or other liens, and shall at all times protect said J. A. Hayden against any and all liens on said work and material, then this obligation is to be void, but if otherwise, the same shall be and remain in full force and virtue.
“J. A. Cook,
Contractor, Lincoln, Neb.
“John Green.
“In presence of
tt__n

The contract price for the building was $1,837. Cook was to furnish all labor and materials. The plaintiff claims damages in the sum of $500 by reason of the failure and refusal of Cook to pay for all the materials used and labor performed in the construction of the building mentioned in said bond, in consequence of which mechanics’ liens were filed against said building.

The defendant Cook is now a non-resident of the state, and was not served with a summons, nor did he appear in the action.

[673]*673The defendant Green answered, alleging, in substance, that Hayden and Cook never executed a written contract for the erection of the building, but entered into a verbal contract for the construction of a dwelling which cost a much larger sum than was contemplated by the proposed written agreement, for which the bond was given; that he never agreed to allow said bond to stand as security for said verbal contract, nor for the construction of the building which was erected by Cook.

The answer denies that any mechanics’ liens were filed against plaintiff’s building, or that plaintiff has been compelled to pay out the sum mentioned in the petition, or any other sum, in consequence of the failure of Cook to keep and perform his covenants. The answer further avers that “said plaintiff never notified him that he would look to him (this defendant) to make good any loss on account of the contract of said Cook, or that he relied, or expected to rely, upon any obligation made by this defendant, or the said Cook was failing in any manner to comply with his agreement, or that he was failing to furnish any pay for the materials according to his agreement, or that he had failed to pay persons to whom he was indebted for work or materials on account of said contract with said plaintiff, or that liens were filed orto be filed against said premises; but, on the contrary, the said plaintiff paid out moneys to the said Cook when he knew that it was before the time provided by the statute at which said claims for materials became due and collectible, contrary to his duty in that regard, and thereby reduced the funds in plaintiff’s hands that would otherwise have been abundant to have paid off and satisfied all liens against said premises.”

All allegations of the answer were denied by the reply.

At the close of plaintiff’s testimony the defendant Green moved for a nonsuit, on the ground of the insufficiency of the evidence, which was granted, and the suit was dismissed at the costs of the plaintiff. If, under the evidence [674]*674adduced by the plaintiff, he was not entitled to recover anything, the judgment of nonsuit was proper. We will, notice the grounds urged by counsel for defendant in error why the ruling should be sustained.

The first contention is that there is no proof that a written contract for the erection of the building was ever entered into between Cook, the contractor, and Hayden, the owner of the building. The evidence shows that a contract for the erection of the building mentioned in the bond was prepared according to the direction and understanding of the parties, which contract bears date May 12,1888. For some cause, doubtless an oversight, neither Cook nor Hayden signed it. It does, however, appear that the bond on which the suit was brought was written upon the back of said contract. It will be observed that the bond recites that Cook has contracted with Hayden to construct a frame story-and-a-half cottage for a specified sum, according to a contract dated May 12, 1888. One of the conditions in the bond is that Cook “shall duly perform and keep his agreements as in said contract set forth.” The defendant in error ii-j estopped by these recitals to deny the execution of the contract. The rule is as well settled as anything in the law that sureties are estopped to deny the facts recited in their obligations; in other words, they cannot set up and prove facts to contradict their own bonds. (Brandt on Suretyship & Guaranty, sees. 29, 30; Gudtner v. Kilpatrick, 14 Neb., 347; Adams v. Thompson, 18 Id., 541; Love v. Rockwell, 1 Wis., 331; U. S. v. Bradley, 10 Peters [U. S.], 365; People v. Hoson, 20 Pac. Rep. [Cal.], 369; Rogers v. U. S., 32 Fed. Rep., 890; Collins v. Mitchell, 5 Fla., 364; Green v. Wardwell, 17 Ill., 278; Shaw et al. v. Havekluft et al., 21 Id., 127; Otto v. Jackson, 35 Id., 349.) The same principle was recognized and applied in the case of Gudtner v. Kilpatrick, cited above. That was a suit upon an appeal undertaking. The defense was that no appeal was taken, nor could be, for the reason that the same was prohibited [675]*675by law. This court- held that the defendants were estopped to deny that an appeal had been taken in contradiction of the recital in their undertaking. ,To the same effect is the case of Adams v. Thompson, supra.

Otto v. Jackson, supra, is analogous to the case at bar. That was an action upon a guaranty of the faithful performance by tenants of the covenants of their lease. On the trial objection was made to the introduction of the lease in evidence, for the reason that the execution by one of the lessees was not proven. It was held that the guarantors were estopped by their guaranty from denying the execution of the lease. So in this case, we think, Green is estopped to deny that the contract, upon the back of which the bond was written, was neither executed by, nor was it the contract of Cook and Hayden. The bond in express terms refers to and recognizes such instrument as being the contract under which the building was to be constructed, and its terms and conditions are as binding upon the obligors of the bond as though the same were set out at length in the body of the bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

U. S. Fidelity & Guaranty Co. v. Henderson County
276 S.W. 203 (Texas Commission of Appeals, 1925)
State v. Hudson Paving & Construction Co.
113 S.E. 251 (West Virginia Supreme Court, 1922)
Morrow Transfer & Storage Co. v. Wells Bros.
106 S.E. 200 (Court of Appeals of Georgia, 1921)
Doyle v. Faust
153 N.W. 725 (Michigan Supreme Court, 1915)
Pulaski Hall Ass'n v. American Surety Co.
143 N.W. 715 (Supreme Court of Minnesota, 1913)
Massachusetts Bonding & Insurance v. Realty Trust Co.
73 S.E. 1053 (Supreme Court of Georgia, 1912)
Bartlett & Kling v. Illinois Surety Co.
119 N.W. 729 (Supreme Court of Iowa, 1909)
McMullen v. United States
167 F. 460 (Ninth Circuit, 1909)
Red Wing Sewer Pipe Co. v. Donnelly
113 N.W. 1 (Supreme Court of Minnesota, 1907)
Enterprise Hotel Co. v. Book
85 P. 333 (Oregon Supreme Court, 1906)
Kretschmar v. Bruss
84 N.W. 429 (Wisconsin Supreme Court, 1900)
Higgins v. Quigley
54 N.E. 136 (Indiana Court of Appeals, 1899)
United States v. Freel
92 F. 299 (U.S. Circuit Court for the District of Eastern New York, 1899)
Northern Light Lodge, No. 1 v. Kennedy
73 N.W. 524 (North Dakota Supreme Court, 1897)
De Mattos v. Jordan
46 P. 402 (Washington Supreme Court, 1896)
O'Rourke v. Burke
63 N.W. 17 (Nebraska Supreme Court, 1895)
Howard County v. Baker
24 S.W. 200 (Supreme Court of Missouri, 1894)

Cite This Page — Counsel Stack

Bluebook (online)
52 N.W. 165, 34 Neb. 670, 1892 Neb. LEXIS 163, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hayden-v-cook-neb-1892.