United States v. Freel

92 F. 299, 1899 U.S. App. LEXIS 2968
CourtU.S. Circuit Court for the District of Eastern New York
DecidedFebruary 15, 1899
StatusPublished
Cited by11 cases

This text of 92 F. 299 (United States v. Freel) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the District of Eastern New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Freel, 92 F. 299, 1899 U.S. App. LEXIS 2968 (circtedny 1899).

Opinion

THOMAS, District Judge.

Tbe question presented on this demurrer is whether tbe sureties of a contractor, who undertook by contract concluded with tbe United States, on tbe 17th November, 1892, in consideration of $612,000, to build a dry dock, “to be located at such place on tbe water line of tbe navy yard, Brooklyn, N. Y., as shall be designated,” are relieved from liability by reason of a change of such contract by a supplemental agreement concluded between the contractor and tbe United States, on tbe 16th day of June, 1893, whereby it was stipulated that tbe dry dock should be extended to tbe length of 670 feet, which was 70 feet in excess of tbe length as originally provided, at an agreed price of $45,556, whereby also “tbe time fixed in tbe original contract for tbe completion of the said dry dock shall be extended three (3) months, on account of the extra labor,” etc., or are relieved from liability by reason of an agreement concluded on the 17th of August, 1893, between the contractor and the United States, whereby, in consideration of $5,063.18, to.be paid the contractor, it was stipulated to “change its location to one sixty-four (64) feet further inland than that laid down and staked out when the •said contract was entered into,” and whereby the contractor undertook that “he will perform all the additional excavation necessary at the entrance of the dry dock in consequence of the said change of location; also, all the additional work necessary to lengthen the suction pipes provided to be laid down from the present pump house, including the piping, round piles, sheet piles, timber, iron work, excavation, and back filling, etc., and all other work incident to said change of location, supplying all the labor and materials therefor,” whereby also “the time limited by the said contract for the completion of the dry dock shall be extended for a period of eight (8) weeks.” The plaintiff answers the contention that the supplementary contracts effect the discharge of the sureties by the claim that such contracts were made pursuant to the seventh article of the contract, whereby the sureties anticipated such contracts, and consented there[301]*301to. Before considering tbe seventh article, a survey of the applicable law may be obtained by summarizing the holdings:

1. The obligation of the surety is coincident primarily with that of his principal. Benjamin v. Hillard, 23 How. 149, 164; McCluskey v. Cromwell, 11 N. Y. 593, 598; Bank v. Dillon, 30 Vt. 122, 126.

2. In estimating the extent of the liability of a surety for the performance of a contract, the true intent, meaning, and fair scope of the contract should be ascertained. U. S. v. Boyd, 15 Pet. 187, 208; Smith v. U. S., 2 Wall. 219, 235; Lee v. Dick, 10 Pet. 482; McCluskey v. Cromwell, 11 N. Y. 593, 598; Gates v. McKee, 13 N. Y. 232, 235; Dobbin v. Gradley, 17 Wend. 422, 425; Crist v. Burlingame, 62 Barb. 351, 355; Lodge v. Kennedy (N. D.) 73 N. W. 524; Wehr v. Congregation, 47 Md. 177, 187; Beers v. Wolf, 116 Mo. 179, 184, 22 8. W. 620; Lionberger v. Krieger, 88 Mo. 160; Locke v. McVean, 33 Mich. 473.

3. In ascertaining its true intent, meaning, and scope, the same rules of construction should be employed as are used in the interpretation of other contracts. The extent: of the surety’s obligation must be determined from the language used, read in the light of the circumstances surrounding the transaction. But, when tiie intention of the parties has thus been ascertained, then the courts carefully guard the rights of the surety, and protect him against a liability not strictly within the precise terms of his contract. Leggett v. Humphreys. 21 How. 66, 73; Association v. Conkling, 90 N. Y. 116, 121, 122; McCluskey v. Cromwell, 11 N. Y. 593; Crist v. Burlingame, 62 Barb. 351; Ludlow v. Simond, 2 Caines, Cas. 1; Plow Co. v. Walmsley, 110 Ind. 242, 246, 11 N. E. 232; Irwin v. Kilburn, 104 Ind. 113, 3 N. E. 650; Birdsall v. Heacock, 32 Ohio St. 177; Dobbin v. Bradley, 17 Wend. 422, 425; Gamble v. Cuneo, 21 App. Div. 413, 47 N. Y. Supp. 518; People v. Backus, 117 N. Y. 196, 201, 22 N. E. 759; 8mith v. Mollesen, 148 N. Y. 241, 246. 42 N. E. 669; Gates v. McKee, 13 N. Y. 232, 237; Belloni v. Freeborn, 63 N. Y. 383; Brandt, Sur. § 54.

4. The liability of the surety cannot be extended by implication. Miller v. Stewart, 9 Wheat. 680; B. S. v. Boyd, 15 Pet. 187, 298; Smith v. U. S., 2 Wall. 219, 234; U. S. v. Boecker, 21 Wall. 652; U. S. v. American Bonding & Trust Co., 89 Fed. 925; Dobbin v. Bradley, 17 Wend. 422, 425; Livingston v. Moore, 15 App. Div. 15, 44 N. Y. Supp. 125; Raney v. Baron, 1 Fla. 327; Field v. Rawlings, 6 Ill. 581; Bank v. Cole, 39 Me. 188; Blair v. Insurance Co., 10 Mo. 559; Henderson v. Marvin, 31 Barb. 297; Grant v. Smith, 46 N. Y. 93, 97.

5. A surety has the right to stand on the very terms of his contract; and if he does not assent to any variation of it, and a variation is made, his liability will be extinguished, even though such alteration be for his own benefit. Miller v. Stewart, 9 Wheat. 680; Id., 4 Wash. C. C. 26, Fed. Cas. No. 5,951; U. S. v. Boecker, 21 Wall. 652, 657; Smith v. U. S., 2 Wall. 219; Martin v. Thomas, 24 How. 315, 317; Reese v. U. S., 9 Wall. 13, 21; U. S. v. Tillotson, 1 Paine, 305, 324, Fed. Cas. No. 16,524; U. S. v. American Bonding & Trust Co.; 89 Fed. 925; Earnshaw v. Boyer, 60 Fed. 528; Ludlow v. Simond, 2 Caines, Cas. 1; U. S. v. Hillegas, 3 Wash. C. C. 70, Fed. Cas. No. [302]*30215,366; Grant v. Smith, 46 N. Y. 93, 97; Paine v. Jones, 76 N. Y. 274, 279; Page v. Krekey, 137 N. Y. 307, 314, 33 N. E. 311; Dobbin v. Bradley, 17 Wend. 422; Bangs v. Strong, 7 Hill, 250; Livingston v. Moore, 15 App. Div. 15, 44 N. Y. Supp. 125; Mackay v. Dodge, 5 Ala. 388; Bethune v. Dozier, 10 Ga. 235; Taylor v. Johnson, 17 Ga. 521; Plow Co. v. Walmsley, 110 Ind. 242, 11 N. E. 232; Mayhew v. Boyd, 5 Md. 102; Brigham v. Wentworth, 11 Cush. 123; Bank v. Cole, 39 Me. 188, 193; Simonson v. Grant, 36 Minn. 439, 31 N. W. 861; Beers v. Wolf, 116 Mo. 179, 22 S. W. 620; Ryan v. Morton, 65 Tex. 258; Wylie v. Hightower, 74 Tex. 306, 11 S. W. 1118; Bonar v. MacDonald, 3 H. L. Cas. 226, 239; Rees v. Berrington, 2 Ves. Jr. 540. (a) While the authorities state that the surety is relieved, whether the alteration is material or not (Paine v. Jones; Page v. Krekey; Livingston v. Moore, supra), yet it is probable that trivial or very minor changes, relating to detail, and not effecting any substantial change in the terms of the contract, will not release the sureties. Grant v. Smith, 46 N. Y. 93, 96; U. S. v. Tillotson, 1 Paine, 305, Fed. Cas. No. 16,524; Mayhew v. Boyd, 5 Md. 102; Plow Co. v. Walmsley, 110 Ind. 242, 11 N. E. 232. (b) Changes in the specifications of building contracts fall within this rule. Evans v. Graden, 125 Mo. 72, 28 S.W. 439; Beers v. Wolf, 116 Mo. 179, 22 S. W. 620.

6. A variance in the agreement, without the sureties’ consent, by a modifying contract, releases the sureties, although the alleged liability is incurred under the original contract. Bonar v. MacDonald, 3 H. L. Cas. 226; Pybus v. Gibb, 38 Eng. Law & Eq. 57.

7. A contract for new work, by which no new terms are added to-the original contract, and whereby the prior contract is in no way embarrassed by greater difficulties of fulfillment, does not release the sureties. Ryan v. Morton, 65 Tex. 258; Barclay v. Deckerhoof, 151 Pa. St. 375, 24 Atl. 1067, where the contract for additional work was indorsed on the original contract. See, also, Warden v. Ryan, 37 Mo. App. 467.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glens Falls Insurance v. Wright Contracting Co.
276 F. Supp. 122 (D. Maryland, 1965)
Maryland Casualty Co. v. City of South Norfolk
54 F.2d 1032 (Fourth Circuit, 1932)
Morrow Transfer & Storage Co. v. Wells Bros.
106 S.E. 200 (Court of Appeals of Georgia, 1921)
Hustace v. Davis
23 Haw. 606 (Hawaii Supreme Court, 1917)
Bullard v. Norton
182 S.W. 668 (Texas Supreme Court, 1916)
American Bonding Co. v. United States
167 F. 910 (Ninth Circuit, 1909)
Orleans & J. Ry. Co. v. International Const. Co.
37 So. 10 (Supreme Court of Louisiana, 1903)
United States v. Freel
99 F. 237 (Second Circuit, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
92 F. 299, 1899 U.S. App. LEXIS 2968, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-freel-circtedny-1899.