Maryland Casualty Co. v. City of South Norfolk

54 F.2d 1032, 1932 U.S. App. LEXIS 2980
CourtCourt of Appeals for the Fourth Circuit
DecidedJanuary 12, 1932
Docket3239
StatusPublished
Cited by48 cases

This text of 54 F.2d 1032 (Maryland Casualty Co. v. City of South Norfolk) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maryland Casualty Co. v. City of South Norfolk, 54 F.2d 1032, 1932 U.S. App. LEXIS 2980 (4th Cir. 1932).

Opinion

PARKER, Circuit Judge.

This is the second appeal in a suit instituted in the court below to determine the liability of a surety under a contractor’s bond. Hudson & Scruggs, Inc., was the contractor, the city of South Norfolk, Va., was the obligee, and the Maryland Casualty Company was the surety. We shall refer t-o them hereafter as “the contractor,” “the city,” and “the surety,” respectively. The judge below referred the cause to a special master, who filed a report determining the amounts of the claims asserted by various materialmen under the bond. He reported that two general questions affecting the rights of all claimants were whether the surety was liable under the bond to subcontractors for labor and materials furnished, and whether, if liable thereunder, the liability extended to labor and materials furnished for work done under a supplemental contract claimed to be a mere extension of the original contract. He was of opinion that, if liability existed, it extended to labor and materials furnished under the supplemental, *1034 as well as under the original, contract, but that there was no liability under the bond with respect to either.-

The ease was heard by the District Judge upon exceptions to the report of the special master, and he held that there was no liability under the bond for materials furnished the contractor, and entered a decree in favor of the surety on that ground. The materialmen thereupon appealed to this court; and we reversed the decree below, holding that the bond was intended to protect, and did protect, laborers and materialmen. This was the only question decided on the former appeal. Daughtry et al. v. Maryland Casualty Co. (C. C. A. 4th) 48 F.(2d) 786.

Upon the receipt of the mandate from this court, the court below proceeded to pass upon and allow the claims of the defendants and interveners, and allowed the claims of those who had furnished materials to the contractor for the completion of the supplemental, as well as for the completion of the original, contract. From a decree in favor of these materialmen, the surety has appealed; and the principal question presented by its assignments of error is with respect to its liability for materials furnished the contractor under the supplemental contract. We shall come at once, therefore, to the consideration of that question.

The contract between the contractor and the city was entered into on October 22,1928; and bond in the sum of $75,900 guaranteeing its performance and the payment of laborers and materialmen was executed by the surety at the same time. The contract was based on a proposal to do paving work at certain Unit prices, and bound the contractor to do the work and furnish the materials necessary to construct "and complete ready for use the street improvements of the eity of South Norfolk in accordance with the specifications attached, the drawings, instructions to bidders, the proposal, and such detail directions, drawings, etc., as might be given by the engineer from time to time during the construction. It was understood and agreed between the contractor and the city that the amount to be expended for paving at the unit prices was approximately $150,000, and this fact was communicated to the surety. The amount of the bond was fixed at $75,000, because this was 50 per cent, of the estimated contract pnce; and a premium of $1,500 was collected from.the contractor, same being 1 per cent, of that price. While the streets to be paved were not designated at the time the contract was executed, it was understood in a general way where the work contracted for was to be •done; and within two or three weeks thereafter the city engineer determined upon a list of the streets which were to be paved under the contract “with question marks on two or three streets,” and notified the contractor of his determination. Following this, there were only minor changes in the work as determined, “cutting off a block here and a block there, and adding one here,” to use the language of the engineer.

The contract provided that work should be commenced not later than November 1, 1928, and completed not later than April 1, 1929, with provision for extension of time in case of interruption of work- or delivery of materials by the council of the eity, or in ease the council in its discretion should agree to extend the time. Work was duly commenced as provided in the contract, and was continued until, on April 1,1929, it was practically completed. Of the work laid out for the contemplated expenditure of the $150,000 under the contract, that which remained uncompleted amounted to less than $6,000'.

On April 3,1920, two days after the time for the completion of the work under the original contract, the council of the eity, without in terms extending that time, passed a resolution directing the city engineer to instruct the contractor to proceed with the paving of thirteen additional streets at the unit prices prevailing under the original contract and at an estimated total cost of $42,-551. On April 9th the city engineer directed the contractor to pave these streets, stating that the work would be executed as “an extension” of the contract then in force between the contractor and the eity. On April 10th, in a letter to the eity engineer, the contractor accepted the additional work, and agreed to proceed with its construction. No additional bond was given by the contractor, however, and none was required by the eity. No notice was given the surety of the additional contract, and nothing was said by any one to indicate that the bond executed by it to guarantee the performance of the original contract was expected to cover this supplemental contract or “extension.” On the contrary, one of the officers of the contractor stated to the agent of the surety, some time after-wards, that he was doing some additional work for the eity which was not a part of the contract and on which he did not propose to pay a premium.

The contention of the appellees is that the agreement for the additional paving was not a supplemental or additional contract, but *1035 merely an. agreement for additional work provided" for under article 8 of the existing contract, and that same is protected by the bond securing the performance of that contract just as is the work originally contemplated. Article 8 of the contract is as follows:

“The council, through the engineer, shall have the right to make any alterations in the plans and quantity of the work or materials herein contemplated, and it is expressly agreed and understood that such alterations, additions, modifications, or omissions, shall not in any way violate this contract, and the contractor hereby agrees not to claim or bring suit for any damage, whether for loss of profit or otherwise. Whenever, during the progress óf the work, any additional work or material, or changes or modifications in the work or materials contracted for, are agreed upon between the said council and the contractor, such additional work or materials, alterations or modifications shall be considered and treated as though originally contracted for, and shall be upon and subject to all terms, conditions, and provisions of the original contract.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Andrulonis v. Andrulonis
998 A.2d 898 (Court of Special Appeals of Maryland, 2010)
Carolina Care Plan Inc. v. McKenzie
467 F.3d 383 (Fourth Circuit, 2006)
Automotive Finance Corp. v. Barthelmes (In Re Barthelmes)
318 B.R. 364 (D. South Carolina, 2004)
Chesley v. Goldstein & Baron, Chartered
806 A.2d 296 (Court of Special Appeals of Maryland, 2002)
Faumuina v. Vaouli
31 Am. Samoa 2d 2 (High Court of American Samoa, 1996)
Hawes v. Liberty Homes, Inc.
640 A.2d 743 (Court of Special Appeals of Maryland, 1994)
Cruickshank & Co. v. Dutchess Shipping Co.
805 F.2d 465 (Second Circuit, 1986)
Cruickshank & Co. v. Dutchess Shipping Co.
112 F.R.D. 4 (S.D. New York, 1986)
Werner v. Carbo
731 F.2d 204 (Fourth Circuit, 1984)
Daniels v. Gilbreath
668 F.2d 477 (Tenth Circuit, 1982)
Hysell v. Iowa Public Service Co.
559 F.2d 468 (Eighth Circuit, 1977)
Taylor v. Wahby
314 A.2d 100 (Court of Appeals of Maryland, 1974)
Johns Hopkins University v. Hutton
316 F. Supp. 698 (D. Maryland, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
54 F.2d 1032, 1932 U.S. App. LEXIS 2980, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maryland-casualty-co-v-city-of-south-norfolk-ca4-1932.