United States v. Poe

114 A. 705, 138 Md. 466, 1921 Md. LEXIS 118
CourtCourt of Appeals of Maryland
DecidedMay 5, 1921
StatusPublished
Cited by4 cases

This text of 114 A. 705 (United States v. Poe) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Poe, 114 A. 705, 138 Md. 466, 1921 Md. LEXIS 118 (Md. 1921).

Opinion

*467 Boyd, C. J.,

delivered the opinion of 'the court.

This is one of several appeals heard at the present term of this Court, which were taken from orders of the lower court refusing to allow certain claims of creditors of the United Surety Company of Baltimore, which was placed in the hands of receivers on January 13th, 1911. This claim was made by the United States of America, and is for the amount of the penalty of a bond ($42,000) given by the Midland Land & Improvement Company on August 13th, 1907, with the United Surety Company as surety, for the performance of a contract made by it with the United States for dredging in Newark Bay and Passaic River, N. J. A similar bond was entered into the same day by the Bankers Surety Company in the penalty of $58,000. The contract was dated the 12th of August, 1907, and was entered into on behalf of the United States by Col. D. W. Lockwood, Corps of Engineers, IT. S. Army.

Another contract was made on August 3rd, 1911, between the Midland Land & Improvement Company and the United States, represented by Col. Wm. T. Russel, Corps of Engineers, and the appellees contend that that contract was an alteration of the one in 1907 of a material ldnd, and, as it was not consented to by the United Surety Company, or by them as receivers, that company was discharged from all liability on tbe bond. The auditor so held, and disallowed the claim of the United 'States, and the lower court having overruled exceptions taken to the auditor’s report in reference to said claim, this appeal was taken.

The advertisement for bids for the original contract was for “Proposals for dredging in Newark Bay and Passaic River, N. J.,” and there were a number of specifications. Amongst them was one that “it is understood and agreed that the quantities given in these specifications are approximate only.” One of the “special conditions” was that the River and TIarbor Act, approved March 2, 1907, contains the following provision:

*468 “Improving channel in Newark Bay and Passaic River, New Jersey, in accordance with the report submitted in House Document Numbered' Four Hundred and Forty-one, Fifty-ninth Congress, second session, two hundred thousand dollars: Provided that the Secretary of War may enter into a contract or contracts for such materials and work as may be necessary for the prosecution of said work, to an amount not exceeding in the aggregate six hundred and fifty thousand dollars, to be appropriated for, from time to time, according to law, in addition to the amounts herein and heretofore appropriated.”

Under the head of “Description of Work” is the following:

“The work to be done under these specifications consists in dredging a channel as above authorized 16 feet in depth at mean low water through Newark Bay and Passaic River from Staten Island Sound to the Montclair and Greenwood lake Railroad bridge, a distance of 10.8 miles. The width of this channel to be 300 feet to the Nairn Linoleum Works, a distance of 9.7 miles; thence 200 feet in width 11 miles, to the Montclair and Greenwood Lake Railroad bridge.
“Depth, Side Slopes and Tides: Under the project of June 13, 1902, a channel is in progress 200 feet wide throughout the reach to be improved. This channel is to be 12 feet deep to the Nairn'Linoleum Works and 10 feet deep above that point, and of the 10.8 miles to be dredged, about 8 miles from Newark Bay up have been completed; and the entire channel will be completed under certain contracts now in force and in progress. There are no natural depths in the river in excess of those to be dredged under the project of 1902. The minimum depths in the river on either side of this channel are from 6 to 8 feet up to the vicinity of the Nairn Linoleum Works and about 4 feet above that locality.
*469 “The depth required is sixteen (16) feet at mean low water; an allowance of one (1) foot for overdepth in dredging will be made.”

In the contract it was provided:

“That in conformity with the advertisement and specifications hereunto attached, which form a part of this contract, the said Colonel D. W. Lockwood, Corps of Engineers, for and in behalf of the United States of America, and the said Midland Land and Improvement Company, do covenant and agree, to and with each other, as follows:
“That the said party of the second part shall furnish the necessary labor and plant, and dredge about four million, one hundred and seventy-seven thousand, one hundred and ten (4,177,110) cubic yards of material, scow measurement, in Newark Bay and Passaic River, N. J., and that the said party of the second part shall be paid therefor at the rate of sixteen and one-quarter (16%) cents per cubic yard, scow measurement, amounting to about $678,780.38 for all material which shall have been satisfactorily removed and disposed of.”

The agreement also contains the following provision in reference to a change or modification of the contract:

“If, at any time during the prosecution of the work, it be found advantageous or necessary to make any change or modification in the project, and this change or modification should involve such change in the specifications as to character and quantity, whether of labor or material, as would either increase or diminish the cost of the work, then such change or modification must be agreed upon in writing by the contracting parties, the agreement setting forth fully the reasons for such change, and giving clearly the quantities and prices of both material and labor this substituted, for those named in the original contract, and before taking effect must be approved by the Secre *470 tary of War: Provided, that no payment shall he made unless such supplemental or modified agreement was signed and approved before the obligation arising from such modification was incurred.”

The supplemental agreement was dated the 3rd of August, 1911. The recitals in it state asi reasons- for modifying, the contract of August 12, 1907, that since it was entered into’ requests have been made by interested parties

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bopst v. Columbia Casualty Co.
37 F. Supp. 32 (D. Maryland, 1940)
Maryland Casualty Co. v. City of South Norfolk
54 F.2d 1032 (Fourth Circuit, 1932)
Reinhart Construction Co. v. Mayor of Baltimore
146 A. 577 (Court of Appeals of Maryland, 1929)
Lamson v. Maryland Casualty Co.
196 Iowa 1185 (Supreme Court of Iowa, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
114 A. 705, 138 Md. 466, 1921 Md. LEXIS 118, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-poe-md-1921.