Bopst v. Columbia Casualty Co.

37 F. Supp. 32, 1940 U.S. Dist. LEXIS 2133
CourtDistrict Court, D. Maryland
DecidedDecember 27, 1940
DocketCivil 756
StatusPublished
Cited by5 cases

This text of 37 F. Supp. 32 (Bopst v. Columbia Casualty Co.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bopst v. Columbia Casualty Co., 37 F. Supp. 32, 1940 U.S. Dist. LEXIS 2133 (D. Md. 1940).

Opinion

CHESNUT, District Judge.

At the trial of this case the defendant moved for a directed verdict which was rejected with the reservation of the question in accordance with Rule 50 of the new Federal Rules of Civil Procedure, 28 U.S.C.A. following section 723c. These motions have been argued by counsel and I have given further consideration to the subject.

The nature of the suit, and a summary of the evidence at the trial, appears in the charge to the jury which has been transcribed .by the stenographer.

The jury found a verdict for the plaintiff in the amount of $3,243.17, and filed with their verdict a written memorandum in which they stated that the amount of the verdict was computed as follows:

“40 days at $100. per day damage $4,000.00
Casing work on boilers....... 2,133.40
Cost of welding clips......... 159.77
■$6,293.17
(Sum retained by Bopst from bal. due Thurston on contract price) .............. 3,050.00
$3,243.17”

The significance of this computation will appear upon reading the charge to the jury.

The defendant’s motion for a directed verdict was based on the ground that the defendant’s surety bond guaranteed the performance by Thurston & Sons, the plaintiff’s subcontractor, of a specified contract between the plaintiff and Thurston, dated April 25, 1939; that with the knowledge of the plaintiff a copy of this contract, then unexecuted by the plaintiff and Thurs-ton, was submitted to the defendant Surety Company as a basis for the issuance of its bond, on May 18, 1931, and the defendant’s surety bond was then executed referring to the form of contract so submitted as the contract to be guaranteed; and that there *33 after the plaintiff and Thurston instead of executing the contract which had been submitted to the Surety Company made a material change in the contract, with respect to the time of completion of performance by the sub-contractor, in consequence whereof the surety is not obligated on its bond. The difference between the contract as submitted to the Surety and as later actually executed was that in the former the time for completion was 80 days from the date of the contract; while in the contract as finally signed the time for completion was made 45 days after notice to sub-contractors to proceed. The contract contained a liquidated damage clause of $100 per day for the delay. As above stated the jury allowed forty days’ delay with damages of $4,000. It is obvious, therefore, that the particular clause of the contract to which the change related was a very material one to the parties.

At the trial of the case I had very substantial doubt as to whether the effect of the change was not as a matter of law one that discharged the Surety; but time did not afford then to study the papers and consider the matter very fully. Since hearing argument on the present motions and further study of the papers in the case and the applicable law, I have reached the conclusion that the motion for a directed verdict should have been granted.

The sequence of events with respect to the execution of the surety bond and the contract are as follows: Under date of April 12, 1939, Thurston made written application to the Surety Company for the bond. In the application he stated that work must begin about May 15, 1939, but that there was no required time for it to be finished and no penalty for non-compliance on time. Thurston applied for the bond to the local Norfolk agent of the Columbia Casualty Company who corresponded with the home office in New York upon the subject. The New York office did not immediately act upon the application. On April 25, 1939, Bopst, the plaintiff, sent to Thurston the form of contract in duplicate and also the form of surety bond that he wanted. The contract contained the following clause as to time of completion: “All of which shall be done and completed within eighty (80) calendar days from date hereof as the sub-contractor doth hereby covenant to do”. The contract was not executed by Bopst but was dated April 25, 1939. Thurston handed the papers to Farant, the defendant’s local agent at Norfolk, who transmitted them to New York.

On May 17, 1939, Thurston orally conferred with Farant regarding the bond; and thereafter on the same day Farant wrote to the defendant in New York saying:

“Your wire this even date told us that you would not authorize us to execute the form of bond which we attached to our letter of May 15th, in lieu of the standard Columbia contract bond form which we have already executed in this caption, until you had received from us a copy of the contract. We are therefore attaching hereto a copy of this contract and ask that you please wire us tomorrow, Thursday, May 18th.”

It is important to note the postscript on this letter from, Farant to the defendant, the full significance of which was possibly not sufficiently considered at the trial. This postscript was as follows:

“P. S. We want to call your attention to a couple of things. In the application you will see that there is no special time required to finish the job, and no penalty for failing to do so. This was changed after we executed the bond, we understand, and is now work to be completed eighty (80) days after notice to proceed to work, with $100. per day penalty for non-completion on time, although the contract says ‘80 days from date hereof’. Our Principal says that they can complete the job within 45 days after notice to proceed.” (Italics supplied)

On May 18, 1939, the Surety Company authorized Farant to execute the bond and he did so and delivered it to Thurston. On May 19, Thurston wrote Bopst enclosing the bond and also the contract, dated April 25, 1939 (which had been sent to him by Bopst), then signed by Thurston but not by Bopst. Thurston called attention to the fact that before signing the contract he had changed the wording of the time of completion clause to read as follows:

“All of which shall be done and completed within sixty (60) days after our being notified that the boilers are in place and ready for bricking and refractory work.”

And added:

“You will note that the contract as drawn states that we are to have completed our work within eighty (80) calendar days from the date of contract and as you know we will not be able to start work until on *34 or about the I’Sth of July and that would only give us 5 days to complete our job. Thanking you to insert this wording in the copy of contract you have and to mail us back the enclosed copy after signing, we are,” etc.

On May 20, 1939, Bopst (apparently after some further conversation with Thurston in person or by telephone) returned the contract signed by him but only after changing the 60-day period in the contract as originally signed by Thurston, to 45 days. Bopst called attention to this and requested Thurston to initial the change which was finally done.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glens Falls Insurance v. Wright Contracting Co.
276 F. Supp. 122 (D. Maryland, 1965)
Chester v. Schleisner Co.
167 F. Supp. 697 (D. Maryland, 1958)
De Jean v. Great American Indemnity Co.
126 F. Supp. 931 (W.D. Louisiana, 1954)
Capital Transit Co. v. Crusade
68 A.2d 207 (District of Columbia Court of Appeals, 1949)
Crusade v. Capital Transit Co.
63 A.2d 878 (District of Columbia Court of Appeals, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
37 F. Supp. 32, 1940 U.S. Dist. LEXIS 2133, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bopst-v-columbia-casualty-co-mdd-1940.