Glens Falls Insurance v. Wright Contracting Co.

276 F. Supp. 122, 1965 U.S. Dist. LEXIS 9785
CourtDistrict Court, D. Maryland
DecidedOctober 5, 1965
DocketCiv. No. 15431
StatusPublished
Cited by4 cases

This text of 276 F. Supp. 122 (Glens Falls Insurance v. Wright Contracting Co.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Glens Falls Insurance v. Wright Contracting Co., 276 F. Supp. 122, 1965 U.S. Dist. LEXIS 9785 (D. Md. 1965).

Opinion

THOMSEN, Chief Judge.

This action involves claims, counterclaims and cross claims between (1) Wright Contracting Company (Wright), a principal contractor on a Maryland State Roads Commission project, (2) Delta Coastal Corporation (Delta), with which Wright entered into a subcontract, and (3) Glens Falls Insurance Company (Glens Falls), Delta’s surety. Glens Falls’ principal contention is that it was released from liability under its bond because the contract relationship between Wright and Delta, upon which its bond was based was changed without its knowledge or consent to an arrangement by which the officers and employees of Delta became in effect employees of Wright.

The parties have agreed that all questions of liability shall be determined at this time by the Court without a jury, leaving for future hearing and determination the amount of damages which may be awarded under the decision now being made.

Issues

The basic issue is whether Wright and Delta abandoned the written contract, which provided that Delta should be a subcontractor, and proceeded under a modified arrangement which made the officers and employees of Delta in fact employees of Wright, subject to Wright’s direct control.

If there was such a change in the arrangement :

A-l. Did it release Glens Falls from liability under its surety bond (a) on ordinary principles of the law of surety-ship, or (b) on grounds of illegality or public policy, in that the matter was handled by Wright in such a manner as to evade a rule of the Commission?

A-2. What were the respective rights and obligations of Wright and Delta under the new arrangement? Was either of them guilty of a breach which imposed on it a legal liability to the other? Does Delta have a claim against Wright on a quantum meruit or other basis ?

If there was no such change in the arrangement:

B-l. Was Delta guilty of such a breach as justified Wright in terminating [124]*124the contract? If so, is Wright entitled to recover from Glens Falls and Delta under the bond, or to recover damages from Delta on some other theory?

B-2. Was Wright guilty of a breach of the contract, making it liable in damages to Delta?

Facts

The determination of the facts has been made difficult because many of the witnesses who testified in the case were not fully credible, for one reason or another,1 the testimony of other witnesses has to be scrutinized very carefully to determine whether their inferences and stated conclusions are based upon established facts, and some Important original records of all three parties either had been destroyed or were not produced.

The findings of fact set out below are based upon a careful weighing of the conflicting testimony and the documentary evidence.

Wright is a general contractor engaged in highway construction, with its home office in Columbus, Georgia, and a regional office in Odenton, Maryland. Its officers and principal employees involved in this case are experienced, shrewd and ruthless.

On or about September 26, 1962, Wright entered into a contract with the Maryland State Roads Commission for the construction of 1.30 miles of the Cabin John Parkway, Montgomery County, Maryland, consisting of a dual section of road, bridges, culverts and walls, for a total price of $1,499,901.40, the work to be cpmpleted in 290 working days.

Wright began work on its contract in the autumn of 1962 and subcontracted portions of the work to several subcontractors not involved in this case, all of whom were pre-qualified with the Commission in accordance with the requirements of sec. 10.03-2 of the State Roads Commission Specifications for 1962.

Two of the bridges covered by Wright’s contract, B-6 and B-7, which were of box girder design,2 crossed Cabin John Creek, B-6 carrying the southbound lane and B-7 the northbound lane. B-6 was located under a much longer bridge, which carried the George Washington Memorial Parkway east along the Potomac River. That bridge was being built by Blackwell Construction Co., another principal contractor. By February, 1963, Wright had already ordered the structural steel, some concrete and other material for B-6 and B-7, but work on those bridges was being delayed by Blackwell. Their construction presented difficult problems both with regard to the substructures (which included some tall, thin, concrete piers) and the superstructure (because of the unusual box girder design). An employee of Wright got in touch with Robert Massey to see if he was willing to undertake the construction of B-6 and B-7.

Robert Massey and his brother Howard were capable and experienced bridge builders but were poor businessmen. They were the principals in J. R. Massey & Sons, Inc., a corporation which employed union labor, but they had decided to organize another corporation, defendant Delta, which was incorporated on March 1, 1963, to engage in non-union operations. The Masseys were willing to have Delta undertake the work for $225,-975, which was $10,000 less than Wright had allocated to that portion of the work in its estimate. Delta, however, needed financing, and Wright agreed to finance Delta’s payrolls, as well as to advance the money to pay for the material which Wright had already ordered. That agreement was reached on February 20, 1963, .when Robert Massey, president-to-be of Delta, and his attorney Farrell went to Wright’s Odenton office. Later that afternoon an employee of Wright filled out a printed subcontract form, which was dated February 20, and prepared a [125]*125supplemental letter agreement dated February 21, both of which were signed on behalf of Wright and sent to Massey on February 21, with a covering letter.

The subcontract form referred to the principal contract indicating the items which were covered by the subcontract, some of which were lump sum items and some unit price items. It called for completion of the work by January 1, 1964, with liquidated damages of $165 a day thereafter. It required Delta to carry certain insurance and to furnish a performance and payment bond. It did not refer to the letter agreement.3

The letter agreement provided that Wright was to furnish and pay for specified materials at the prices stipulated “to be incorporated by you as subcontractor” into the work covered by the principal contract, “charging to your account and deducting from any and all sums due you for estimates earned”. There followed a list of the materials to be supplied by Wright, with their estimated quantities, units and prices. The materials listed were “bearing assemblies”, “reinforcing steel”, “Class A concrete” and “Class C concrete”. The letter agreement continued: “It is further agreed that we will pay the payrolls and all applicable insurance and taxes on your employees used on the above project, charging to your account and deducting from any and all sums due for estimates earned.” The letter agreement did not indicate that Delta’s officers and employees should become, in effect, members of the Wright organization.

The evidence is conflicting as to why the entire agreement was not included in one document.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
276 F. Supp. 122, 1965 U.S. Dist. LEXIS 9785, Counsel Stack Legal Research, https://law.counselstack.com/opinion/glens-falls-insurance-v-wright-contracting-co-mdd-1965.