Wehr v. German Evangelical Lutheran Saint Matthew's Congregation

47 Md. 177
CourtCourt of Appeals of Maryland
DecidedJune 19, 1877
StatusPublished
Cited by9 cases

This text of 47 Md. 177 (Wehr v. German Evangelical Lutheran Saint Matthew's Congregation) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wehr v. German Evangelical Lutheran Saint Matthew's Congregation, 47 Md. 177 (Md. 1877).

Opinion

Alvey, J.,

delivered the opinion of the Court.

When the case of Heise & Company, and others, against the present appellees was before this Court at the October Term, 1875, reported in 44 Md., we declined passing upon the question, then discussed by counsel, as to whether the sureties in the bond of Siegman & Jones, the contractors, were discharged by reason of the facts there alleged ; those facts depending as they did upon a conflict of evidence. We declined deciding the question, supposing it to he more appropriate that the conflicting evidence should be passed upon by a jury; and there was also the further reason, that all the parties obligated by the bond were not then before the Court. As no definitive order or decree could then be passed against the bond, to bind all the parties thereto, we deemed it proper to remit the whole question of the liability of the bond to a Court of law. That question has been properly raised by an action on the bond, and has been decided adversely to the defendants, the present appellants, and from that decision they have taken this appeal.

The case was tried in the Court below before the Judge, acting in the double capacity of Court and jury. Each party, at the close of the evidence, tendered certain legal propositions, which they prayed to be affirmed by the Court and- taken as rules for its decision upon the facts that might be found. The Court filed in the case a written opinion, which appears in the record, and in which are discussed both law and fact; and in the conclusion the several propositions offered by the parties are ruled upon [189]*189by tbe Court. There is but one exception presented, and that was taken by the appellants to the rejection of their propositions and the granting of those on the part of the appellees, and to the rulings of the Court in its opinion. This, of course, does not embrace the rulings or findings of the Court as to matters of fact. All the facts stated as found, and upon which the verdict is based, must be taken as conclusively established, and therefore not open to review in this Court. Whether the finding of facts by the Court be general or special, such finding has the same effect as a verdict of a jury rendered in the particular form; and this Court has no more power over the facts in the one case than in the other. It is only the propositions of law, ruled upon by the Court below, that can be reviewed here, when properly presented.

The bond sued on recites that Siegman & Jones, by their contract of the same date of the bond, had contracted with the appellees to erect and complete a church, according to the plans and specifications, and upon the terms and conditions mentioned in the said contract; and the condition of the bond is, that the contractors should well and faithfully fulfil said contract, and in all respects perform and keep all and singular the stipulations on their part to be done and performed under the same. The breaches assigned are, that the contractors failed to erect, finish and complete the building and works in the time, with the materials, and in the manner provided for by the contract, or according to the plans and specifications in the contract referred to ; and further, that the contractors did not find, provide and deliver at their own cost and charge, free from all claims, liens, and charges whatsoever, all the work and materials necessary and proper for the complete execution of the building, as they were bound to do by their contract.

The sureties resist recovery on the bond, and take the defence that they have been discharged, by reason of cer[190]*190tain additions and alterations in the work, not warranted by the original contract. And the additions and alterations supposed to have this effect were, 1st, the extension of the length of the building 3-J feet; 2nd, the change in the foundation of the building- from a brick to a stone wall, with additional- excavations; 3rd, the placing of moveable pews in the basement of the church ; 4th, the furnishing and placing of ventilators, and some slight change about the pulpit and the chancel; and it is objected, 5th, that the specifications or supplemental contracts for the additional work were not executed in manner required by the original contract; and 6th, that there was no time extended for doing the additional work.

These matters were all made subjects of legal propositions submitted to the Court by the appellants, but which were refused.

With respect to the general principle relied on by the appellants, there'is really no question. All the difficulty consists in its application to the particular facts of this case.

It is perfectly well settled that a surety has the right to' stand upon the very terms of his contract; and if such contract be altered or varied in any material point without his consent, so as to constitute a new agreement varying substantially from the original, he is no longer bound. Mayhew vs. Boyd, 5 Md., 102; Miller vs. Stewart, 9 Wheat., 680 ; Whitcher vs. Hall, 5 B. & Cr., 269 ; Bonar vs. Macdonald, 3 H. L. Cas., 226, 239. And any subsequent addition to, or deviation from the contract, is such an alteration as will discharge the surety. But if, by the terms of the original contract, additions to or alterations in the work are provided for, or left to the judgment and discretjon of the other contracting party, either without limit or within certain limits, then the variation, if within the limits prescribed, is allowed by the contract itself, and the surety cannot complain of a variation which [191]*191he has agreed to by the original contract. Stewart vs. McKean, 10 Exch., 675. And whether the present case falls .within the principle there stated, depends upon the terms and construction of the original contract, and the nature and extent of the changes in, and additions to, the plan and finish of the work as originally contemplated.

The original contract referred to in the bond, provided, among other things, that the contractors should find, provide and delivery at their own cost and charge, free from all claim, liens and charges whatsoever, all and every kind of material, and work and labor which might “ be necessary and proper for the complete execution of the building, and erect, build, finish and complete, in a good and perfect manner, (to the entire satisfaction of the architects,) the buildings and works, agreeably and conformably, in all and every respect, to the specifications, drawings, dimensions, and explanations which may become necessary, according to the true intent and meaning of the drawings, and specifications.” It is further provided, that if it should appear that any of the work intended to be done, was not fully explained and detailed in the specifications and drawings, the contractors should apply to the architects for such further detailed explanations, and perform their orders as part of the contract. Then follow these important provisions : —

“And it is distinctly understood and hereby agreed, that should the building committee appointed by said congregation desire to make any change from the drawings or specifications at any time during the progress of the works, the same shall be carried out by said Siegman & Jones without making void or in any manner affecting this contract.

“Such changes, whether in addition to or deduction from the original works, shall be specified in writing, signed by the contractors, the architects, and the building committee. The sum to be paid or allowed for.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Silverberg v. Silverberg
130 A. 825 (Court of Appeals of Maryland, 1925)
State v. Hudson Paving & Construction Co.
113 S.E. 251 (West Virginia Supreme Court, 1922)
United States v. Poe
114 A. 705 (Court of Appeals of Maryland, 1921)
Hardy v. Carter
163 S.W. 1003 (Court of Appeals of Texas, 1914)
Trustees of Seventh Baptist Church v. Andrew & Thomas
81 A. 1 (Court of Appeals of Maryland, 1911)
McMullen v. United States
167 F. 460 (Ninth Circuit, 1909)
United States v. Freel
92 F. 299 (U.S. Circuit Court for the District of Eastern New York, 1899)
United States Glass Co. v. Mathews
89 F. 828 (Fourth Circuit, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
47 Md. 177, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wehr-v-german-evangelical-lutheran-saint-matthews-congregation-md-1877.