American Bonding Co. v. United States

167 F. 910, 93 C.C.A. 310, 1909 U.S. App. LEXIS 4396
CourtCourt of Appeals for the Ninth Circuit
DecidedFebruary 1, 1909
DocketNo. 1,570
StatusPublished
Cited by14 cases

This text of 167 F. 910 (American Bonding Co. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Bonding Co. v. United States, 167 F. 910, 93 C.C.A. 310, 1909 U.S. App. LEXIS 4396 (9th Cir. 1909).

Opinion

MORROW, Circuit Judge.

The dredging contract entered into between Colonel Heuer, of the Corps of Engineers, for and on behalf of the United States, and Rudolf Axman, on November 21, 1902, provided, among other things, in paragraph 1, that:

“The said Rudolf Axman will do such dredging in San Pablo Bay, California, as may be required by the said W. H. Heuer, in accordance with the [911]*911specifications hereunto annexed, and that he, the said W. IT. Heuer, or his successor, will pay to the said Itudolf Axinan- the sum of eleven and forty-four one hundredths cents per cubic yard for all such dredging as shall be done in strict accordance with the said specifications hereunto annexed, and is ordered and accepted by the said W. H. Heuer, or his agent.”

In paragraph 3 of the agreement it was provided: .

“The said party of the second part shall commence, prosecute, and complete the work herein contracted for as set forth in paragraphs 31 and 46 of the attached spocifica lions.”

In paragraph 4 of the agreement it was provided:

“If, in any event, the party of the second part (Asman) shall delay or fail to commence with the delivery of the material, or the performance of the work, on the day specified herein, or shall, in the judgment of the engineer In charge, fail to prosecute faithfully and diligently the work in accordance with the specifications and requirements of • this contract, then, in either case, the party of the first part, or his successor legally appointed, shall have power with the sanction of the Chief of Engineers to annul this contract by giving notice in writing to that effect to the party (or parties, or either of them) of the second part, and upon the giving of such notice all payments to the party or parties of the second part under this contract shall cease, and all money or reserved percentage due or to become due the said party or parties of fhe second part, by reason of this contract, shall be returned, by the party of the first part until the final completion and acceptance of the work herein stipulated to be done; and the United States shall have the right to recover from the party of the second part whatever sums may be expended by the party of the first part in completing the said contract in excess of the price herein stipulated to be paid the party of the second part for completing the same.”

It was provided in paragraph 6 of the agreement that:

“If, at any time during the prosecution of the work, it be found advantageous or necessary to make any change or modification in the project, and this change or modification should involve such change in the specifications as to character and quantity, whether of labor or material, as would either increase or diminish the cost of the work, then such change or modification must bo agreed upon in writing by the contracting parties, the agreement setting forth fully the reasons for such change, and giving clearly the quantities and prices of both material and labor thus substituted for those named in the original contract, and before taking effect must be approved by the Secretary of War; provided, that no payments shall be made unless such' supplemental or modified agreement was signed and approved before the obligation arising from such modification ivas incurred.”

The specifications referred to in the agreement provided in paragraph 31 that:

“The contractor will be required to commence work under the contract within sixty days after the date of notification of approval of the contract by the Chief of Engineers, U. S. Army, to prosecute the said work with faithfulness and energy, and to complete it within twenty-eight (28) months, after the date of the commencement.”

In paragraph 35 it was provided that:

“The shoal to be dredged is in San I’ablo Bay, California, is about 5 miles in length, and has a least depth of 19 feet at low water. Tt extends from Pinole Point to Lone Tree Point, and is distant Hi to iy2 statute miles N. W. of the points referred to. The average depth of the excavation is about 9 feet.”

[912]*912In .paragraph 36 it was provided:

“The work to be doné is to excavate a channel through the shoal, to have a bottom .width of 300 feet, a depth of 30 feet at mean low water, and a length of about 27,000 feet; to deposit the spoil as near the south shore as practicable, within lines drawn between Pinole -Point and Lone Tree Point, at such places as may be designated by the engineer officer in charge; and to impound the material behind bulkheads or dykes of suitable construction, subject to approval by the engineer officer in charge, which must be built and maintained by and at the expense of the contractor during the life of the contract.”

In paragraph 38 it was provided:

“Material dredged outside the .designated lines of excavation, below the depths provided in paragraph 37, or deposited otherwise than as herein specified, directed and agreed upon, will not be paid for. The total amount to be dredged is estimated at 2,721,000 cubic yards, more or less.”

In paragraph 33 it whs provided:

“All dredged material is to be deposited within the limits of the area described in paragraph 36. The method of deposit will be subject to approval by the engineer officer in charge.”

in paragraph 40 it was provided:

“The part of the area available for the deposit of material from scows has an average width of about % of a mile. Its distance from the site of dredging varies from 1 to 2 miles. The location of the place of deposit, the depths of the water therein, and the location of the dredging, are shown on maps on file in this office.”

In paragraph '46 it was provided:

“The work must progress at the rate of at least 100,000 cubic yards per month,, .and to entitle the contractor 'to ■ the monthly payments provided for in paragraph 30 of these specifications, an average of not less than 100.000 cubic yards per month must have been dredged and deposited; the calculation of averages to be made from the day on which the contractor requires the work to be commenced.”

In paragraph 48 it was provided:

“.If at any time after the date set for beginning work it shall be found that the required minimum rate of progress is not being maintained, the engineer officer in. charge shall have the power, after due notice in writing to the contractor, to employ such additional plant or purchase such materials as. may be necessary to ensure the completion of the work within the time specified, charging the cost thereof against such sums as may be due or become due to'the'con tráetoi*;-'¡This'pro visions-however, shall not be construed to affect the right of the Ufiited States to annul the contract as provided for in the form of contract to be entered into.”

In-paragraph 49 it was provided:

“Work must be pushed continuously, except on Sundays and legal holidays. Night work will be permitted, when proper provision must be made, in all cases by the contractor at his expense, for the comfort of the inspectors and other United States employees who may be on the work.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern Surety Co. v. American Const. Co.
36 S.W.2d 212 (Texas Commission of Appeals, 1931)
Brighton Theatre Co. v. Graf
248 Ill. App. 140 (Appellate Court of Illinois, 1928)
County of Blue Earth v. Bisballe Construction Co.
213 N.W. 30 (Supreme Court of Minnesota, 1927)
Massachusetts Bonding & Ins. Co. v. Davis
274 S.W. 230 (Court of Appeals of Texas, 1925)
United States v. Poe
114 A. 705 (Court of Appeals of Maryland, 1921)
United States v. Weisberger
206 F. 641 (Ninth Circuit, 1913)
United States v. Axman
193 F. 644 (Ninth Circuit, 1912)
City of Fergus Falls v. Illinois Surety Co.
128 N.W. 820 (Supreme Court of Minnesota, 1910)
Chesapeake Transit Co. v. Mott
169 F. 543 (Third Circuit, 1909)
Axman v. United States
167 F. 922 (Ninth Circuit, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
167 F. 910, 93 C.C.A. 310, 1909 U.S. App. LEXIS 4396, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-bonding-co-v-united-states-ca9-1909.