American Surety Co. v. Woods

105 F. 741, 45 C.C.A. 282, 1901 U.S. App. LEXIS 3898
CourtCourt of Appeals for the Fifth Circuit
DecidedJanuary 8, 1901
DocketNo. 919
StatusPublished
Cited by15 cases

This text of 105 F. 741 (American Surety Co. v. Woods) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Surety Co. v. Woods, 105 F. 741, 45 C.C.A. 282, 1901 U.S. App. LEXIS 3898 (5th Cir. 1901).

Opinion

SHELBY, Circuit Judge,

after stating the case as above, delivered the opinion of the court.

The question to be considered is the charge of tbe court on the measure of damages. The instruction, in effect, was that the measure of damages was the difference between the contract price and what ir. would have cost to finish the sewers, and that, to recover this difference, it was not necessary for the sewerage company to complete the work. “Where the object of the contract is anything but the payment of money, the damages due to the creditor for its breach are the amount of the loss he has sustained and the profit of which he has been deprived,” under certain exceptions and modifications not material to this case. Rev. Civ. Code La. art. 1934. This statute merely undertakes to secure full indemnity to the aggrieved party. Reading v. Donovan, 6 La. Ann. 491. Article 2709 is the same in legal effect. To authorize recovery under the statute, two things must concur, — the inexecution of the obligation, and damages to the party complaining. This statute does not conflict with the common law, for by its rule there must be, to authorize a recovery, a breach of the contract, which causes damages. If the breach only is shown, there could be only a verdict for a nominal sum. Sedgw. Meas. Dam. (8th Ed.) § 98. When a contractor is discharged unlawfully, he can, in a suit for damages, recover his outlay and the probably certain profits he would [744]*744have made if he had been permitted to proceed with the work. His profits in such case would have been a gain he would have received but for the unlawful act of his employer. The courts uniformly sustain the right to recover profits in such cases. U. S. v. Behan, 110 U. S. 338, 4 Sup. Ct. 81, 28 L. Ed. 168; Railroad Co. v. Howard, 13 How. 307, 14 L. Ed. 157; Masterton v. Mayor, etc., 7 Hill, 61. It is argued from this proposition that, if the contractor wrongfully abandons the contract and refuses to do the work he has contracted to do, the employer, in a suit for damages for breach of the contract, may recover the difference between the contract price and the sqm which it would have cost the employer to have the work done, although the employer in fact does not have the work done. To apply the principle to this case, the contention is that, as Stewart & McDermott agreed to finish the sewers for sums aggregating $739,500, and then abandoned the work, and as it would have cost'the sewerage company $912,099.09 to complete the work, the receiver of the sewerage company is entitled to recover the difference between the contract price and what it would-have cost to finish the work, to wit, $172,599.09, though in fact the work was riot finished, and no money actually expended to finish it. By the terms of the contract sued on, the contractors were to furnish all necessary labor to excavate and build the sewers. The sewerage company was to furnish at its own cost all material of every kind required to construct the sewers. We must keep in mind, therefore, that the contract on the part of the contractors was one to labor or to furnish labor. The question involved here can be made clear by an illustration of a suit on a short contract to do wprk. A merchant employs a clerk, by written contract, to work for one year at $50 a month, payable monthly. The clerk works two months, and without causé repudiates the contract and quits, receiving only the two months’ pay. The merchant sues for damages for breach of the contract. The proof shows that he could not get another clerk to do the same work for the succeeding 10 months for less than $100 a month. But it also appears that he did not employ any one to take the clerk’s place. Can the merchant recover $500, — the difference between the contract price and the cost of securing another clerk, that he never employed? Does the fact, if it be conceded as a fact, that the clerk would have lost $500 by working for less than his services were worth, show that the contract was worth that sum to the employer, and entitle him to recover a sum not paid, but which would have been paid if he had employed a substitute?

It is contended that as the contractor, in the case of a breach of the contract by the employer, can recover his lost profits, and that-he would be permitted to prove what it would cost to complete the work he was prevented from doing, and, where it cost less than the contract price, could recover the difference, as the profit which he would have made; that, in all fairness, the same rule should apply when a breach of the contract is made by the contractor. There are several considerations making differences in the two cases. When the contractor is stopped from work by the owner or employer who is to furnish tne iriaterials, he cannot go on and finish the work. He cannot, by com[745]*745pleting the work himself or by others, show just what his profit, if any, would be. When he sues for damages, therefore, he must,-to recover.profits, prove, if he can, what he would have made had he not been' stopped. He is prevented from finishing the work, and such evidence is necessary to show what gain or profit to him was in the contract. On the other hand, when the contractor abandons the work the owner or employer is left in possession. He is free to employ others to finish the work. The contract often, as in this case, provides that he may employ others to finish it if the contractor quits. He therefore usually has it in his power by employing others to complete the work and ascertain exactly the amount of his damages. The contractor, when' stopped or unlawfully discharged by the breach of the contract by the employer, has not this power. For the breach of a contract the in-, jured party is entitled in a suit for damages to receive compensation-for his loss, — compensation and nothing more. “Damages are given as a compensation, recompense, or satisfaction to the plaintiff for any> injury actually received by him from the defendant. They should be precisely commensurate with the injury, — neither more nor less, — and this whether it be to his person or estate.” Dow v. Humbert, 91 U. S. 294, 299, 23 L. Ed. 370; 2 Greenl. Ev. § 253. The contractor or builder stopped from his work by the breach of the contract committed by his employer has clearly lost the profit that he would certainly have made by the completion of the work. Can it be said that the employer who has obtained a contract securing services at cheap rates, when the contractor refuses to do the work, has certainly lost the difference between the contract price and the cost of having the work finished, when the employer does not have the work finished? Is this difference a certain gain or profit or value that the employer has lost?. His loss would be certain, we think, only in the event he had the work-done at a cost greater than the contract price. The contention that the measure of his damages is the difference between the contract-price and a greater price which he has never paid must be based on-the erroneous theory that the contract is necessarily worth to him the sum above the contract price that it would cost the contractor to finish-the work. The fact that the contractor would lose a fixed sum by-completing the work does not show that the employer loses that sum by the failure of the contractor to finish it. If thie contractor stops' the work, and the employer does not complete it, it cannot be said he has been damaged what the former would harm lost had he not stopped the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Spencer v. Luckenbach Gulf S. S. Co.
2 So. 2d 53 (Supreme Court of Louisiana, 1941)
Noonan v. Independence Indemnity Co.
41 S.W.2d 162 (Supreme Court of Missouri, 1931)
In re Carrier
21 F.2d 589 (D. Massachusetts, 1927)
County of Blue Earth v. Bisballe Construction Co.
213 N.W. 30 (Supreme Court of Minnesota, 1927)
Massachusetts Bonding & Ins. Co. v. Davis
274 S.W. 230 (Court of Appeals of Texas, 1925)
Illinois Cent. R. v. Orleans-kenner Electric Ry. Co.
100 So. 704 (Supreme Court of Louisiana, 1924)
Maryland Casualty Co. v. Town of Wellston
1915 OK 121 (Supreme Court of Oklahoma, 1915)
Brown v. Producers Oil Co.
64 So. 674 (Supreme Court of Louisiana, 1914)
Long v. American Surety Co.
137 N.W. 41 (North Dakota Supreme Court, 1912)
American Bonding Co. v. United States
167 F. 910 (Ninth Circuit, 1909)
Simons v. Wittmann
88 S.W. 791 (Missouri Court of Appeals, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
105 F. 741, 45 C.C.A. 282, 1901 U.S. App. LEXIS 3898, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-surety-co-v-woods-ca5-1901.