Illinois Cent. R. v. Orleans-kenner Electric Ry. Co.

100 So. 704, 156 La. 522, 1924 La. LEXIS 2050
CourtSupreme Court of Louisiana
DecidedMarch 17, 1924
DocketNo. 24408
StatusPublished

This text of 100 So. 704 (Illinois Cent. R. v. Orleans-kenner Electric Ry. Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Illinois Cent. R. v. Orleans-kenner Electric Ry. Co., 100 So. 704, 156 La. 522, 1924 La. LEXIS 2050 (La. 1924).

Opinion

OVERTON, J.

The tracks of the OrleansKenner Electric Railway Company (hereinafter referred to as the “Kenner Company") were in process of construction in 1915. It was necessary for its tracks to cross those of the Illinois Central Railroad Company (hereinafter referred to as the “Railroad Company”) at Harahan yard, in the parish of Jefferson, and accordingly negotiations were begun with the end in view of obtaining thé right to cross. Tfiese negotiations resulted in the execution of a contract between the two companies on March 16, 1915. By this contract the Railroad Company granted to the Kenner Company the right to construct, maintain, and operate a double-track electric railway under its tracks at Harahan yard. In order to enable the Kenner Company to accomplish these things it was necessary that the Railroad Company should raise its tracks to a sufficient height to permit the cars of the Kenner Company to pass under them. It was therefore stipulated that the Railroad Company should raise its tracks at the crossing granted, at its own expense, to a height not exceeding 13 feet above the elevation existing at the time of the execution of the contract, so as to provide the necessary clearance between the tracks of the Kenner Company and the lowest downward projection in the permanent structure to be built for the support of the tracks of the Railroad Company, and thereby provide a passage for the cars of the Kenner Company. To accomplish this, and at the same time to enable the Railroad Company to operate its trains and the Kenner Company to make use of the crossing, during the progress of the work, it was deemed necessary to erect a temporary structure of sufficient strength to support the trains of the Railroad Company while going over the crossing. The contract provides for such a' structure, and the Kenner Company bound itself to furnish the necessary material upon the ground for its construction, and the Railroad Company obligated itself to erect the structure and to remove it upon the completion of the bridge, the Kenner Company to pay the expense incurred in erecting and removing it.

Article 4 of the contract, which we quote in full as it plays an important part in the determination of this case, reads as follows:

[525]*525“When the Railroad Company shall have completed said temporary work and the elevation of its tracks, the Kenner Company shall, and hereby agrees that it will, construct a steel and concrete bridge at the location aforesaid according to plans and specifications approved by the chief engineer of the Railroad Company, to carry the two present tracks of the Railroad Company over the tracks of the Kenner Company at said crossing, and the said bridge shall upon completion become the property of, and shall be maintained, by the Railroad Company. Provided, however, that if, in the opinion of said chief engineer, the progress of the work on said permanent bridge is unduly delayed the Railroad Company shall have the right, upon giving the Kenner Company ten (10) days’ notice in writing of its intention so to do, to proceed with the completion of said work, and the railroad company is hereby authorized to render a bill against the Kenner Company for the cost of all material furnished and work performed in the completion of said bridge, and the Kenner Company shall, upon receipt of said bill, pay the amount thereof to the Railroad Company.”

The contract then provides that the Kenner Company shall deliver to the Railroad Company a bond, in the penal sum of $7,500, conditioned upon the faithful performance by the Kenner Company of the obligations stipulated in article 4 of the contract, quoted above — that is to say, conditioned upon the construction of the steel and concrete bridge to the satisfaction of the chief engineer of the Railroad Company, or, in case that company should elect to complete the bridge, as provided in article 4 of the contract, then conditioned upon the payment of all expenses incurred by it in constructing the bridge. The contract contains other provisions, not necessary to mention, or, at least, to mention at present.

The Kenner Company furnished the bond mentioned in the preceding paragraph with the Maryland Casualty Company as surety thereon. The bond sets out in full article 4 of the contract, quoted above, and contains conditions, among others, to the effect that, if the Kenner Company shall indemnify the Railroad Company against any- loss or damage arising directly from the failure of the Kenner Company to faithfully perform its contract, then the bond shall be void, otherwise' it shall remain in full force and effect, and to the effect that no claim, suit, or action, by reason of any default of the Kenner Company, shall be brought against that company, or its surety, the Maryland Casualty Company, after March 5, 1916, nor upon any claim for damages accruing after that date.

Tlie Railroad Company did all that it was required to do under the contract. It furnished the Kenner Company with the plans' and specifications, approved by its chief engineer, for the construction of the steel an'd concrete bridge, erected the temporary structure called for by the contract, elevated its tracks to the required height, and notified the Kenner Company that everything was in readiness for the construction of the steel and concrete bridge. However, the Kenner Company, notwithstanding the fact that the Railroad Company had complied with its part of the contract, failed to construct the bridge, and in November, 1915, the Railroad Company made written demand on the Kenner Company to construct it, thereby placing it in default, and sent a copy of the letter to the surety. Neither the Kenner Company nor its surety made any response.

As a result of the failure to construct the bridge the Railroad Company in February, 1915, less than a month before the expiration of the time within which it was permitted to sue under the terms of the bond, instituted this proceeding to recover judgment against the Kenner Company and its surety, insólido, in the sum of $7,500, the amount of the bond, and against the Kenner Company for the further sum of $6,169, with legal interest on both amounts from judicial demand until paid. These sums aggregate [527]*527$13,669, the amount required to construct the bridge.

The petition sets forth, in substance, the foregoing facts. The contract, the bond, and the written demand, placing the Kenner Company in default, are attached to and made part of the petition.

The Maryland Casualty Company excepted to plaintiff’s demand on the ground that it is premature, and further upon the ground that the petition discloses no cause of action. The Kenner Company and the Maryland Casualty Company then filed their answers.

The exception of no canse of action, here filed, involves within its scope the right or one to sue on a contract for the value of that which one of the parties to the instrument has obligated itself to do, but which it has failed to do, or, in other words, to sue for the cost of the thing which one of the parties to the contract bound itself to deliver, but failed to do so, when the cost may be said to be the equivalent of the value of the thing in its completed state which it was agreed should be delivered.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lee v. Harris
82 A. 186 (Supreme Court of Connecticut, 1912)
Kidd v. . McCormick
83 N.Y. 391 (New York Court of Appeals, 1881)
Wells v. Abernethy
5 Conn. 222 (Supreme Court of Connecticut, 1824)
American Surety Co. v. Woods
105 F. 741 (Fifth Circuit, 1901)
American Surety Co. v. Woods
106 F. 263 (Fifth Circuit, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
100 So. 704, 156 La. 522, 1924 La. LEXIS 2050, Counsel Stack Legal Research, https://law.counselstack.com/opinion/illinois-cent-r-v-orleans-kenner-electric-ry-co-la-1924.