Nello L. Teer Company and United States Fidelity & Guaranty Company v. Hollywood Golf Estates, Inc.

324 F.2d 669
CourtCourt of Appeals for the Fifth Circuit
DecidedDecember 16, 1963
Docket20301
StatusPublished
Cited by19 cases

This text of 324 F.2d 669 (Nello L. Teer Company and United States Fidelity & Guaranty Company v. Hollywood Golf Estates, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nello L. Teer Company and United States Fidelity & Guaranty Company v. Hollywood Golf Estates, Inc., 324 F.2d 669 (5th Cir. 1963).

Opinion

BENJAMIN C. DAWKINS, Jr., District Judge.

Nello L. Teer Company (Teer), a Delaware corporation, contracted in writing In December, 1959, to raise the level of certain land at Hollywood, Florida, for Hollywood Golf Estates, Inc. (Estates), a Florida corporation. The fill for this purpose (a minimum of 1,250,000 cubic yards) was to be dredged from two lakes and a canal adjoining the property.

The contract provided for a unit price of 45 cents per cubic yard of fill, based upon the “assumption” that the contractor in dredging would encounter 50%' “hard digging” and 50% “easy digging.” 1 If the contractor encountered less than 50%' hard digging certain reductions in the unit price were to be made, but no provision was made for the possibility that there would be more than 50% hard digging.

As it developed, all of the digging was ■“hard.” After partial performance, having placed 275,936 cubic yards, Teer ceased operations July 13, 1961, and brought this diversity action for rescission of the contract plus recovery upon quantum meruit. It based its claims upon 1) misrepresentations it alleged were made to it by Estates, constituting fraud, that Estates had engaged engineers to take borings of the subsoil to be dredged; that reports of such borings indicated most of the dredging would be “soft digging” ; and under no circumstances would the “hard digging” exceed 50%-; and 2) alleged mutual mistake of fact as to the nature of the subsoil to be dredged.

Estates answered, denying Teer’s charges of fraud and mutual mistake of fact. It then counterclaimed for damages, interest, and attorney fees based upon its claim that Teer had breached the contract, also impleading Teer’s surety, United States Fidelity & Guaranty Company. 2

There is no need here for detailed analysis of the evidence, some of it hotly disputed, which was presented in the lower court. Upon the whole record, it is sufficient to say that, having seen and heard the witnesses and therefore being in the best position to evaluate their statements, the judge’s findings are not clearly erroneous, Rule 52(a), F.R.Civ. P. Resolving the conflicting testimony, and upon substantial evidence, he found that Teer’s claims were without merit and that Estates was entitled to recover upon its counterclaim and against United States Fidelity & Guaranty Company. To the extent of his basic findings upon the substantive rights of the parties, we affirm. 3

*671 On this appeal Teer and United States Fidelity & Guaranty Company abandoned their fraud claim, but reassert that there was mutual error in assuming the digging would be half hard, and half easy, thus vitiating the contract. They also contend that substantial error was committed by the District Court in its method of calculating the damages due to Estates; in awarding attorney fees without a hearing and in excess of the maximum allowed by Florida law; and in imposing costs in addition to those taxed by the Clerk when no motion for review had been filed by appellee within the time fixed by Rule 54(d) F.R.Civ.P.

Having already disposed of appellants’ contention as to “mutual error,” we now pass to consideration of the remaining points made by them.

First, as to the trial court’s method of calculating damages due to Estates, we believe this was error. The Court noted that, after Teer breached the contract, appellee entered into a new contract with Arundel Corporation to complete the dredging and filling required at a unit price of 62.5(5, which was 17.5(5 per cubic yard greater than provided for in the Teer contract. It then multiplied this differential by 974,064 yards, the amount of fill not placed by Teer out of the 1,-250,000 it had obligated itself to place, and arrived at a figure of $170,461.20, with 6% interest from July 13, 1961, which the Court found to be due to Estates by Teer and its surety.

Yet, there is no proof in the record as to how much fill, if any, Arundel actually delivered, or whether its price of 62.5(5 per cubic yard was the best obtainable, after diligent efforts to mitigate the damages had been made by Estates. Moreover, whereas the Teer contract recited that 470 acres were to be filled, the proof showed that Estates actually owned only 72 acres and had a purchase option on 97 more, a total of 169 acres. There was no evidence as to what rights or obligation Estates had as to the remaining 301 acres. Teer was obligated to fill the land up to certain grade posts but there was no evidence as to what that height was to be.

These serious omissions in Estates’ proof mean to us that the purely mechanical award of damages in the manner and amount stated was not justified. Merely because the contract recited that 470 acres were to be filled, and that Teer was to be paid for placing a minimum of 1,250,000 yards, does not establish an estoppel against Teer and its surety in light of the absence of proof we have outlined. It may be that upon another trial appellee can succeed in establishing its actual damages in satisfactory manner, but it has not done so as yet.

*672 We have not found, nor have we been cited to, any Florida jurisprudence squarely in point here, but we are entitled to assume that, in such a situation as this, Florida courts would follow the established rules in common law jurisdictions. As we comprehend these rules, where there has been a breach of contract as in this case, with only partial performance, the contractee first must attempt to mitigate his consequential damages with due diligence and to the best of his ability — and must prove that he has done so. Next, he must prove to a reasonable degree of certainty the amount of such damages, plus any extra expenses necessarily incurred, and any loss of profits caused by the breach. Finally, and over all, except in jurisdictions where punitive damages are allowed, he must do these things with the least burden to the wrongdoer consistent with the idea of fair compensation.

We find these principles plainly enunciated at 25 C.J.S., Damages § 71. (See also §§ 46 and 75), supported by citations to a wealth of common law jurisprudence :

“ * * * Stated in broad terms, however, the measure of damages is sueh sum as will compensate the person injured for the loss sustained, with the least burden to the wrongdoer consistent with the idea of fair compensation, and with the duty upon the person injured to exercise reasonable care to mitigate the injury, according to the opportunities that may fairly be or appear to be within his reach, and the same rule obtains whether the loss is claimed for injury to property, personal injury, or breach of contract. * *”

To the same effect see Annot. 76 A.L.R. 2d 805; § 9, pp. 830 et seq.

A fairly early decision by this Court, American Surety Co. v. Woods, 5 Cir., 105 F.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hartford Casualty Insurance v. City of Marathon
117 F. Supp. 3d 1374 (S.D. Florida, 2015)
St. John v. Coisman
799 So. 2d 1110 (District Court of Appeal of Florida, 2001)
Preston v. Keith
584 A.2d 439 (Supreme Court of Connecticut, 1991)
Julian E. Johnson & Sons, Inc. v. Balboa Ins. Co.
408 So. 2d 1044 (Supreme Court of Florida, 1982)
Catlin Aviation Co. v. Equilease Corp.
1981 OK 13 (Supreme Court of Oklahoma, 1981)
Tuttle/White Constructors v. MONTGOMERY, ETC.
385 So. 2d 98 (District Court of Appeal of Florida, 1980)
CFW Construction Co. v. Richardson Electric Co.
364 So. 2d 854 (District Court of Appeal of Florida, 1978)
Renz v. Beeman
589 F.2d 735 (Second Circuit, 1978)
Associated Hous. Corp. v. KELLER BLDG. PRODUCTS
335 So. 2d 362 (District Court of Appeal of Florida, 1976)
Travelers Indemnity Co. v. Peacock Construction Co.
423 F.2d 1153 (Fifth Circuit, 1970)
William J. Troupe v. Milford J. Seby
416 F.2d 514 (Ninth Circuit, 1969)
RK Cooper Builders, Inc. v. FREE-LOCK CEILINGS, INC.
219 So. 2d 87 (District Court of Appeal of Florida, 1969)
Equitable Fire & Marine Insurance Co. v. Tiernan Building Corporation
190 So. 2d 197 (District Court of Appeal of Florida, 1966)
Hollywood Golf Estates, Inc. v. Nello L. Teer Co.
353 F.2d 485 (Fifth Circuit, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
324 F.2d 669, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nello-l-teer-company-and-united-states-fidelity-guaranty-company-v-ca5-1963.